OBJECT OF THE INVENTION
[0001] The present invention refers to a novel system of manufacture and construction of
decks of bridges or viaducts with two tracks for light railways or metros, to be used
in urban areas, with the particularity of having an open cross-section, in the shape
of a U, being the two tracks located inside the deck.
[0002] It has special application in the field of industry related to the construction of
decks for railway tracks.
TECHNICAL PROBLEM TO BE SOLVED AND BACKGROUND OF THE INVENTION
[0003] In the current state of the art the construction of elevated metros and light railways
is being carried out through the execution of viaducts. This is replacing the traditional
underground construction, mainly due to construction and maintenance costs. Within
this type of construction, it is a common solution to make bridge or viaduct decks
with a U-shaped cross section in which the railway circulates inside the structure.
In the case of double-track railways, there are two possible alternatives. The first
consists in the realization of two independent decks, one for each track. The second
alternative consists of the realization of a single deck that houses the two tracks.
[0004] In this kind of construction, the usual structural typologies consist of concrete
decks, concreted structures, whose execution can be carried out in situ, that is,
on site, or by prefabrication of segments, prefabricated structures, which are subsequently
transported to the site for assembly.
[0005] The structures concreted in situ can be executed on formwork supported on the ground
by means of scaffolding or using steel girders that are supported on the piers to
span the complete span between piers, called MSS (Movable Scaffolding System).
[0006] The precast structures are usually formed by segments, elements that are built in
a precast yard and then transported to the construction site and placed by different
processes that, in general, require the use of auxiliary means and impose an execution
span by span, in order, following the railway line defined by the piers.
[0007] The current technology of complete precast decks is focused on construction for its
use in one-way track decks. The construction of the deck consists of a U-beam of the
same length as the complete span between piers. This structure is transported to the
site in a special transport that can circulate on the roads or streets of the cities,
as its size does not exceed the permitted limits. Subsequently, by using cranes, this
kind of U-beams are lifted and placed over the spans delimited by the piers that define
the different sections of track.
[0008] However, the use of this technique is not possible for the decks that house two tracks.
The reason is that the width of this kind of structures, which is not less than 10
meters, is greater than the maximum allowed to be transported by road or through the
streets of a city. In this way, when the possibility of being transported is discarded,
the option of executing the full span in situ, on site, could be considered. However,
this solution would not be profitable either because it is not possible to start with
the deck until the substructure was executed and a solution in situ is much slower
than the assembly of a precast solution.
[0009] For this reason, the manufacture of double-track decks is considered unviable through
this type of solution. On the other hand, for this kind of structures, the method
used consists of a solution based on the transversal segmentation of the deck in segments
of a width compatible with their transport by road to the construction site. To assemble
them in their definitive position, auxiliary means specially constructed for this
purpose are used. These auxiliary means consist of steel girders that rest on the
piers, equipped with a lifting system that allows to lift all the segments of a span
to join them later by longitudinal prestressing.
[0010] However, this construction method, despite being frequently used, presents a series
of inconveniences such as those described below.
[0011] First, the manufacture of the segments is very complex and involves not only the
need for large manufacturing facilities, but also the employment of a large number
of personnel. In addition, the segments are manufactured in conjugate form so each
segment has a unique position. If a segment breaks during any phase of the process
or any unexpected altercation occurs, the assembly is paralyzed until another identical
segment to the one that has been broken is built.
[0012] On the other hand, the necessary auxiliary means on site for the lifting and subsequent
placement and joining together of the different segments also implies a high cost
in terms of assembly and disassembly.
[0013] In addition, the use of this method of construction involves a chain assembly, so
that the reception on site of segments must be well coordinated with the assembly
and it is essential that the complete infrastructure (foundations and piers) is completed
in advance for that stoppages do not occur with the auxiliary means. If for some reason,
such as a diversion of a utility that is complicated, a break of a segment, etc.,
the assembly can be paralyzed and to continue in another part of the viaduct it is
necessary to disassemble and reassemble the auxiliary means. This triggers assembly
costs and deadlines.
[0014] The present invention comes to solve the aforementioned problems, which are not resolved
in the present state of the art, by the construction of precast beams that are subsequently
transported on site for assembly, completing a span with two longitudinal beams and
a series of transverse slabs that are located between the beams. This implies a reduction
in the following aspects:
- construction costs, without the need for large facilities or a large number of personnel,
- costs of auxiliary means for the assembly, only needing cranes for the lifting of
the beams, without the need of having auxiliary means for assembly such as segmental
gantry or beam launcher,
- time of implementation and execution of the work, because the number of elements to
be prefabricated and assembled is much lower than in the system with segments. In
addition, the beam is a much easier element to precast than the segment.
- schedule associated with the problems that occur in a span built by segments, as the
execution and assembly of a span is independent of its location. Indeed, it is not
necessary that the launching girder has reached the span in question. In case a pier
is not built in the stipulated time, the construction is not stopped, since the assembly
of the spans does not need to be sequential and it is possible to work simultaneously
in different spans that can be located in different areas of the viaduct.
DESCRIPTION OF THE INVENTION
BRIEF DESCRIPTION OF THE FIGURES
[0015] To complete the description of the invention and in order to help a better understanding
of its characteristics, according to a preferred example of realization of the same,
there is attached a set of drawings in which, for illustrative purposes and without
limitation, it has been represented the following figures:
- Figure 1 represents an elevation view of the structure of the deck to be built, formed
by two longitudinal beams and a series of transverse slabs supported between the two
beams.
- Figure 2 represents a plan view of the deck defined in figure 1.
- Figure 3 represents a side view of the deck defined in Figure 1 installed on two piers.
- Figure 4a represents an elevation view of the beginning of assembly of the first longitudinal
beam between two piers. Due to the view of the figure, only one beam is visible, but
the beams are supported at their ends in the piers, as shown in figure 3.
- Figure 4b represents an elevation view of the beginning of the assembly of the second
longitudinal beam as a next step of Figure 4a for the construction of the deck.
- Figure 4c represents an elevation view of the final assembly of the second longitudinal
beam as a next step of Figure 4b for the construction of the deck.
- Figure 4d represents an elevation view of the assembly of the transverse slabs between
the two longitudinal beams as a next step of Figure 4c for the construction of the
deck.
- Figures 5a to 5d represent views in elevation of the installation sequence of the
structure of the invention from the two longitudinal beams.
- Figures 6a and 6b respectively represent a side and rear view of a truck transporting
a longitudinal beam of those used in the invention.
- Figures 7a and 7b respectively represent a side and rear view of a truck transporting
a plurality of transverse slabs of those used in the invention.
[0016] Below is a list of the references used in the figures:
1. Longitudinal beam.
1a. Bottom flange.
1b. Web.
1c. Top flange.
2. Transversal slab.
3. Deck.
4. Pier.
5. Crane.
6. Truck.
7. Permanent bearing.
8. Temporary bearing.
DESCRIPTION OF A PREFERRED REALIZATION OF THE INVENTION
[0017] Considering the numbering adopted in the figures, the present invention consists
in the development of a novel system for the manufacture and construction of bridge
deck structures (3) for bridges or viaducts for double-track installations for the
circulation of urban railways, either metro or light rail, with the particularity
that the structure is open with a U-shaped cross section so that the double track
is housed inside.
[0018] The structures of the decks (3) are intended to be located on a series of piers (4)
that define spans, or free length between piers (4), which must be spanned by the
decks (3), as shown in figure 3
[0019] Figures 1 and 2 represent views of the structure of the deck (3), which is composed
of two longitudinal beams (1) and a series of transverse slabs (2) resting on the
longitudinal beams (1) at their ends. As shown in figure 1, the longitudinal beams
(1) are composed of a bottom flange (1a), by means of which the beams (1) rest on
the piers (4), a web (1b), which it brings to the beam (1) the height on the base
on which it supports, and an upper flange (1c) for the possible support of other structures.
The bottom flange (1a) can protrude on both sides of the web (1b) of the beam (1),
although it usually only protrudes on one side. The upper flange (1c), in the same
way, can protrude on both sides of the web (1b), on one of the sides only or even
be formed by a widening of the core (1b). In any case, it typically has a characteristic
"C", "T", " I " or "L" shape, depending on the configuration of the flanges (1a, 1c)
and the web (1b). The two longitudinal beams (1) are positioned facing each other
and between them the transverse slabs (2) are located, resting on each of the bottom
flanges of the longitudinal beams (1), configuring the deck (3) with a shape of "U",
as mentioned and shown in figure 2. This form of "U" must be understood in a broad
sense since, although it has been commented that the longitudinal beams may have a
"C" shape and it could be considered that the deck (3) also has an approximate "C"
shape (with the variations mentioned above), the reality is that the dimensions of
the upper flange (1c) of the longitudinal beams (1) is not significant compared to
the rest of the dimensions of the board (3).
[0020] The contact of the longitudinal beams (1) on the piers (4) is made by bearings (7,8),
typically made of rubber, neoprene or similar material, to absorb movements and prevent
both elements from contacting directly. In this way, between the piers (4) and the
longitudinal beams (1) there is a permanent bearing (7) and also a temporary bearing
(8), the latter being intended for stability during the construction of the decks
(3), provisional support can be replaced by another provisional system that performs
the same function.
[0021] The longitudinal beams (1) are prefabricated and have a similar length to the span
between two consecutive piers (4) where they are supported, also joining longitudinally
to the previous longitudinal beam (1). The longitudinal beams (1) are located on each
side of the cross section of the piers (4). The transverse slabs (2) are assembled
on the bottom flanges (1a) of the longitudinal beams (1), so that the interior space
between the longitudinal beams (1) and the transverse slabs (2), configured in a "U"
shape", is destined to the location of the two tracks through which the railways will
circulate.
[0022] The transverse slabs (2) are fixed to the ends of the bottom flanges (1a) of the
longitudinal beams (1), resting on them to form a monolithic and stable element in
its final state by means of specific joints. On these transversal slabs (2) is located
the railway platform which, due to this form of construction, is called ballastless
or ballasted tracks.
[0023] In this way, as shown in Figure 3, each deck (3) is located supporting each of the
ends in a pier (4) and, as the decks (3) are having a length similar to the span between
two consecutive piers (4), rest on them occupying half of the longitudinal area of
the head of the pier (4), leaving the other longitudinal half of the pier (4) for
the location of the next deck (3).
[0024] The main features of the present invention are those described below.
[0025] First, the deck (3) is not manufactured by transverse segments, as has been done
in the state of the art, but by longitudinal beams (1) of a length similar to the
span defined by the distance between two piers (4) of the viaduct destined to accommodate
the double-track. These longitudinal beams (1) constitute the lateral sections of
the deck (3).
[0026] Secondly, transverse slabs (2) are used, supported between the longitudinal beams
(1) by their bottom flanges (1a) and connected so that the final set in the form of
U being pursued is monolithic. A representation of this configuration is shown in
figures 1 and 2. In figure 2 it can be seen how, between the two longitudinal beams
(1) is arranged a plurality of transverse slabs (2) that cover the intermediate area
between the two longitudinal beams (1). This area, as mentioned, is intended to house
the two railway tracks.
[0027] Third, the deck (3) is configured in a "U" shape, focused on housing a double railway
track inside. This differs from another very usual current technique consisting of
the construction of two longitudinal beams, located between piers, above them a slab
is located on which a double railway track runs. In this case, each of the beams may
have a "U" shaped cross section, being separated or joined together in the form of
a "W", which presents a great disadvantage with respect to the present invention,
especially as regards to manufacturing and assembly costs, since a longitudinal "U"
beam and a slab, although shared, are needed for each of the two railway tracks.
[0028] The assembly of the structure of the deck (3) of the modular system of the invention
is represented in the sequence defined by figures 4a to 4d. To understand this assembly,
it is necessary to take into account Figure 3, to see that the longitudinal beams
(1) rest on two piers (4) at the ends, since in the side views shown in Figures 4a
to 4d, only is shown one of the piers (4).
[0029] The longitudinal beams (1) are transported in trucks (6), as will be commented below,
which are parked between the two piers (4) between which the longitudinal beam (1)
will be located to facilitate its later collection and erection up to the pier (4)
by a crane (5).
[0030] As shown in figure 4a, by means of a crane (5), the longitudinal beam (1) located
on the truck (6) is hooked and raised to position each of the ends on one of the sides
of each of the piers (4) between which it supports. Subsequently, once the first longitudinal
beam (1) is located, the operation is repeated with a second longitudinal beam (1),
picking up the beam (1), as shown in Figure 4b, and positioning the ends on the other
side of the piers (4), as shown in Figure 4c. As shown in Figures 4a and 4b, the piers
(4) already have on top the bearings (7, 8) for the location of the longitudinal beams
(1).
[0031] It must be taken into account that, for the support of the longitudinal beams (1)
on the piers (4), bearings (7, 8) are placed on the piers (4) that define the position
of the longitudinal beams (1) and avoid direct contact between the two elements.
[0032] Finally, transverse slabs (2) are collected with the crane (5) to position them between
the longitudinal beams (1), as shown in Figure 4d to finalize with a configuration
according to the one provided in Figure 3.
[0033] The construction of the deck (3) is defined in Figures 5a to 5c, although neither
the piers (4) nor the bearings (7, 8) have been represented in these figures.
[0034] Figure 5a shows how initially the two longitudinal beams (1) should be positioned,
facing symmetrically and resting inferiorly on the bottom flange (1a), which serves
as the base. In these figures, it can be checked that the section of the longitudinal
beam (1) may not be horizontal, as shown in Figure 1. This is because it may be convenient,
for aesthetic or materials resistance reasons, that the bottom flange (1a) vary the
inclination, although in the area at the ends, where it rests on the piers (4), it
is always horizontal, parallel to the upper flange (1c).
[0035] Subsequently, both the absolute position of the longitudinal beams (1) on the piers
(4) and the relative position between the longitudinal beams (1), it is convenient
that are controlled by means of a bracing of those known in the state of the art,
as it can be by incorporating auxiliary beams that connect the upper flanges (1c)
of the longitudinal beams (1) so that, both the separation distance between the longitudinal
beams (1) and the parallelism between them, is defined and also the stability against
overturning of the longitudinal beams (1) is guaranteed. Other means of bracing can
be by placing mechanical stops that indicate without question the position of each
of the longitudinal beams (1) or by fixing the beams (1) by wiring.
[0036] Subsequently, as shown in Figure 5b, the transverse slabs (2) are placed, placing
them supported on the free ends of the bottom flanges (1a) of the longitudinal beams
(1).
[0037] Subsequently, to ensure that all the elements form a monolithic structure, the longitudinal
beams (1) and the transverse slabs (2) are fixed firmly, as shown in Figure 5c, either
by filling the joints with concrete, with mortar or by any other fixing means known
in the state of the art.
[0038] Finally, the transverse slabs (2) are joined together, either by threading and prestressing
tendons or steel bars, or by leaving a separation between the transverse slabs (2)
that are filled with concrete once they are all positioned for guarantee to convert
the independent slabs (2) into a monolithic slab.
[0039] Once it has been ensured that the joining method between beams (1) and transverse
slabs (2) used has been completed, either by hardening the concrete or mortar of the
joints, or any other method used, the provisional bracings that could have been placed
in an earlier stage are removed. then the construction of the deck is being completed
(3).
[0040] The advantages of the present invention with respect to the state of the art are
based on three concepts:
- a) the needs in terms of production of the construction elements,
- b) the transport of the constructive elements, and
- c) the needs for the placement of the constructive elements.
[0041] Regarding the production needs, consider that, by means of this construction process,
all the structural elements, both the longitudinal beams (1) and the transverse slabs
(2), require manufacturing conditions that are quite small in terms of facilities.
Facilities for a production of three beams (1) per week per cast and considering a
total of two casts, can consist of a shed of 180 meters in length and 25 meters in
width. For the collection of components and finished elements would require an esplanade
of 200x60 m
2. Since the production depends mainly on the number of casts available, the way to
increase it is achieved mainly with the increase in the number of casts.
[0042] Regarding the transportation of the construction elements, consider that the longitudinal
beams (1) can be transported to the site in conventional transports, such as trucks
(6), appropriately adapted for the displacement of elements of great length, where
two trailers are used with a single tractor, as shown in Figures 6a and 6b. On the
other hand, the transverse slabs (2), which measures can be 3 meters wide by 7 meters
long, are located in conventional vehicles, i.e. usual trucks (6), that can load without
problems four transverse slabs (2) by simply turning them to position them along the
length of the truck loading platform (6).
[0043] Finally, regarding the needs on site for the placement of the construction elements,
the longitudinal beams (1) can be erected by conventional cranes (5), without great
technical requirements, so that, for example, two cranes (5) LTM 1500 can be used.
The transverse slabs (2) can be erected in the same way, for example by using a crane
(5) LTM 1160 or, even, by gantry cranes (5) supported on the longitudinal beams (1).
In this way, the raising and subsequent installation of the prefabricated elements
is quite simple. In Figures 4a to 4c it can be seen how the assembly of the longitudinal
beams (1) is carried out, while in Figure 4d it can be seen how the assembly of the
transverse slabs (2) is carried out. The construction rate, considering a team of
two cranes (5) LTM 1500 with six operators for the longitudinal beams (1) and a team
of a crane (5) LTM 1160 with five operators for the transverse slabs (2), is calculated
that it can be of two beams (1) per night and a span of slabs (2) per day. The construction
is based on the number of teams, so it can be regulated according to needs.
[0044] The savings in execution time due to the lower complexity of the manufacturing plant,
the lower cost of transport and savings in erection and assembly of elements can exceed
37% compared to the traditional way of building by erecting transverse segments. This,
without counting the losses due to delays caused by lack of synchronization or errors
in the delivery of material on site or stops due to delays in the construction of
the piers (4) where the launching gantry that raises the segments is supported. In
addition, this prefabrication methodology reduces the increasing of schedule associated
with the problems that occur in a span built by segments, as it is independent the
execution and assembly of a span of its location (does not need that the launching
gantry has reached that span) and as many spans as desired can be executed simultaneously
depending on the disposition of a greater number of automobile cranes, of great availability
in the market and with easy mobilization period.
[0045] The advantages of the construction method allowed by the present invention are therefore
based on the flexibility to prefabricate, on the viability of transport with conventional
means, on the ease and speed in the arrangement of the cranes necessary for the assembly
of construction elements, in the flexibility in the assembly of elements along the
railway, because they can be assembled alternately, by not depending on the supply
of certain elements and by the speed in the assembly of stations, as it is possible
to build the spans before and after the station at the same time than the station
itself.
[0046] This manufacturing configuration using precast longitudinal beams (1) and transverse
slabs (2) located over the longitudinal beams (1) is known in the state of the art,
as it has been mentioned above, although for the construction of closed structures
where the railway circulates above the structure, or for the construction of beams
on which a slab is subsequently placed above, on which the railway circulates, without
having been able to develop effectively for the construction of open structures for
the location of a double railway track where the railway circulates through its interior,
a requirement that is essential in the type of constructions to which the present
invention is dedicated, that is to say, the circulation of railways inside the deck
(3).
[0047] Anyway, it must be taken into account that the present invention should not be limited
to the way of realization described here. Other configurations may be made by those
skilled in the art in view of the present disclosure. Accordingly, the scope of the
invention is defined by the following claims.
1. : Longitudinal modular system by means of decks (3) of bridges for the installation
of double-track for the circulation of railways, the modular system is
characterized by that the deck (3) is located between two consecutive piers (4) and comprises:
- A pair of longitudinal beams (1) comprising a bottom flange (1a), intended to be
the support on the piers (4), a web (1b), intended to raise the structure of the deck
(3) and an upper flange (1c), designed to accommodate an additional structure
- A plurality of transverse slabs (2) intended to be fixed by their ends on the bottom
flanges (1a) of the longitudinal beams (1), which support as a base on the piers (4),
to achieve a configuration shape of an "U",
where:
- the length of the longitudinal beams (1) is substantially similar to the span between
two piers (4), and
- the configuration of the deck (3) has a "U" cross section so that the railway runs
inside this "U" shape.
2. Longitudinal modular system by means of decks (3) of bridges for the installation
of a double track for the circulation of railways, according to claim 1, characterized in that between a pier (4) and the deck (3) there is a definitive bearing (7) to avoid direct
contact between the two elements.
3. Longitudinal modular system by means of decks (3) of bridges for the installation
of a double track for the circulation of railways, according to claim 1, characterized in that a provisional bearing (8) is located between a pier (4) and the board (3) for the
levelling of the longitudinal beams (1) and to avoid their overturning.
4. Construction method of the longitudinal modular system described in claim 1,
characterized in that it comprises the following phases:
a) Manufacturing of longitudinal beams (1) and transverse slabs (2),
b) Transportation of a pair of longitudinal beams (1) to the piers (4) on which they
will be located,
c) Lifting and placing a first longitudinal beam (1) on the piers (4),
d) Lifting and placing a second longitudinal beam (1) on the piers (4),
e) Transportation of a plurality of transversal slabs (2) to the piers (4) on which
they will be located,
f) Lifting and sequential positioning of a plurality of transverse slabs to complete
the length of the longitudinal beams (1),
g) Fixation of the transverse slabs (2) to the longitudinal beams (1),
5. Construction method of the longitudinal modular system, according to claim 2, characterized in that after phase d) comprises the following phase:
h) Place bracing means for controlling the position of the longitudinal beams (1)
both absolute, with respect to the piers (4), and relative, with respect to themselves.