FIELD OF THE INVENTION
[0001] The present invention relates to a submerged floating tunnel, and more particularly
to an incremental launching process for a submerged cable-stayed floating tunnel.
BACKGROUND OF THE INVENTION
[0002] "Submerged Floating Tunnel" is abbreviated as "SFT" in English. It is also called
"Archimedes Bridge", or "PDA" bridge for short in Italy. Generally, it is composed
of a tubular body floating in the water at a certain depth (the tubular body has a
large space enough to meet the requirements of road and railway traffic), a support
system (anchor cables anchored on the seabed, piers or buoyancy tanks on the water),
and structures on both shores. It is a novel structure for means of transportation
to cross both shores separated by deep water, is suitable for all means of transportation
that need to travel through the water, can be passed by trains, cars, small motor
vehicles and pedestrians, and can also be made into service channels through which
various pipes and cables pass. The difference between the submerged floating tunnel
and the traditional submerged tunnel or tunneling tunnel is: the floating tunnel structure
is surrounded by water, is neither on the ground nor crossing the ground, but mainly
depends on the gravity of its own structure, the buoyancy of the structure and the
anchoring force of the support system to retain at a fixed position. The floating
tunnel is sealed all around. This structure has all the characteristics of an ordinary
tunnel. From the perspective of use, it should be regarded as a "tunnel" rather than
a "bridge".
[0003] The floating tunnel can traverse different waters, such as rivers, fjords, straits
and lakes etc., and provides a possible and acceptable form of fixed spanning structures
for the places that are considered uncrossable due to deep water or long distance
between both shores. The floating tunnel is built at a certain depth underwater. Compared
with the open water channel and ferry transportation, bad weathers such as wind, waves,
fog, rain and snow etc. will not affect all-weather operation of the floating tunnel.
Under the premise of ensuring the same navigable capacity, the floating tunnel has
a smoother slope and a shorter total length than a bridge. The construction and use
of the floating tunnel will not affect the environment and natural landscape. When
a certain span and water depth is exceeded, the unit cost of the floating tunnel will
not increase significantly with the increase of span length or channel depth, while
the unit costs of cable-stayed bridges and suspension bridges increase significantly
with the increase of span.
[0004] Although the floating tunnel has certain advantages compared with sea-crossing channel
schemes of immersed tube tunnels, deep-buried tunnels, bridges and the like, the design
and construction of the floating tunnel are still worldwide problems. So far, no floating
tunnel has been built. At present, the floating tunnel is mainly researched in 7 countries
(Norway, Italy, Japan, China, Switzerland, Brazil, and the United States) in the world.
Many technical problems found in the research are: overall structural layout, tunnel
materials, structural types of anchor systems, tunnel connection types, design of
shore connecting structures, implementability of tunnel structures, construction and
operation risks, etc. Whether these problems can be solved determines whether the
floating tunnel can move from a feasible scheme to an actual project.
[0005] So far, in the research of floating tunnels, according to the relationship between
the gravity of the floating tunnels and the buoyancy, the proposed structural types
may be roughly divided into three types: pontoon type, anchored type, and pier type.
The pontoon type floating tunnel is suspended on a pontoon on the water through anchor
cables or chains, and the gravity of the tunnel is greater than the buoyancy, so the
tunnel is greatly affected by fluctuation of the tide rise and fall in the vertical
direction; the anchored type floating tunnel is anchored to an anchorage foundation
under the seabed through tension legs or anchor cables, and the gravity of the tunnel
is smaller than the buoyancy, so the tunnel will be displaced or wobbled under the
action of hydrodynamic force; and the pier type floating tunnel is actually a tunnel
bridge supported on submerged piers, and therefore, is difficult and expensive to
construct. Because the tunnel floats in the water, the installation and construction
of the tunnel are affected by wind, waves, currents, traveling waves etc. The three
types of tunnels are very difficult in underwater localization and underwater or on-water
closure, and their comfort and safety risks during underwater operation are difficult
to predict.
[0006] In order to make the stress on a floating tunnel more reasonable, reduce the impact
of adverse sea conditions during construction period, and be more beneficial to the
control during construction period, the maintenance during operation period and the
replacement of parts, a submerged cable-stayed floating tunnel structure with a cable
system is disclosed. The submerged cable-stayed floating tunnel with a cable system
includes a submerged floating tunnel, shore connection structures, a stay cable anchorage
system, a buoyancy-weight ratio adjustment system, an anti-collision warning system,
an escape system, tunnel subsidiary facilities and so on. The submerged floating tunnel
is connected to the shore connection structures and connected to ground roads via
land slope tunnels. Stay cables are disposed on the submerged floating tunnel and
fixed on cable anchor piers located on both sides of the tunnel to form a stable stress
system. Therefore, it is necessary to propose an installation and construction method,
corresponding to the submerged cable-stayed floating tunnel structure with a cable
system.
SUMMARY OF THE INVENTION
[0007] An object of the present invention is to fill the gap in the prior art and provide
an incremental launching process for a submerged cable-stayed floating tunnel which
is less affected by wind, waves, currents, ship waves and so on, thereby reducing
the risk of offshore construction greatly, and has advantages of high construction
efficiency and short construction period.
[0008] The purpose of the present invention is achieved by providing an incremental launching
process for a submerged cable-stayed floating tunnel, the submerged cable-stayed floating
tunnel including a tunnel body, a launching-side shore connection structure, a receiving-side
shore connection structure, a cable anchorage system and a buoyancy-weight ratio adjustment
system, wherein the tunnel body includes a submerged floating tunnel, a launching-side
land slope tunnel and a receiving-side land slope tunnel; the launching-side shore
connection structure and the receiving-side shore connection structure are respectively
located on a launching-side shore and a receiving-side shore; a waterside end of the
launching-side land slope tunnel and a waterside end of the receiving-side land slope
tunnel are respectively connected to landside ends of the launching-side shore connection
structure and the receiving-side shore connection structure;
the submerged floating tunnel is formed by connecting a plurality of pipe parts; a
head of a first pipe part and a tail of a last pipe part of the submerged floating
tunnel are respectively fixed in an inner cavity of the receiving-side shore connection
structure and an inner cavity of the launching-side shore connection structure ; each
pipe part is divided into an upper tunnel layer, a middle tunnel layer and a lower
tunnel layer by an upper partition and a lower partition, wherein the upper tunnel
layer is a process room, the middle tunnel layer is a tunnel traffic room, and the
lower tunnel layer is a water supply and drainage room;
the launching-side shore connection structure includes a scour protection section,
a starting section, a retaining wall for a portal section, a portal section, a waterside
wall body, a thrust section, a sealing section, a butting section, a pushing section,
a horizontal transportation section and a landside wall body in turn from sea area
to land area, wherein a temporary sealing gate is arranged on a front side face of
the waterside wall body, with a water blocking plug disposed on the temporary sealing
gate; the thrust section is a sealed box structure and has a hoop-type thrust device;
the sealing section is a sealing wall body with a wall hole, with sealing hoops respectively
disposed on a front side face and a rear side face of the sealing section along a
circumference of the wall hole; a water-stop strip is disposed between the wall hole
and an outer surface of the corresponding pipe part; the butting section and the pushing
section are both arranged in a pipe part connecting box which is capable of being
opened and closed; the butting section has a stepped pipe part butting pit formed
in a bottom thereof; carrying airbags are disposed on a bottom of the pushing section
and a positioning section for a hydraulic pushing trolley is located at the rear of
the pushing section; and the horizontal transportation section has a jacking-up beam
disposed on a bottom thereof, which is driven by a jack;
the receiving-side shore connection structure includes a scour protection section,
a receiving section, a retaining wall for a portal section, a portal section, a waterside
wall body, a pipe part stabilizing section, a sealing section, a pipe fixing section,
a drawing and anchor section and a landside wall body in turn from sea area to land
area, the scour protection section, the receiving section, the retaining wall for
a portal section, the portal section, the waterside wall body, the sealing section
and the landside wall body of the receiving-side shore connection structure being
in one-to-one correspondence with the scour protection section, the starting section,
the retaining wall for a portal section, the portal section, the waterside wall body,
the sealing section and the landside wall body of the launching-side shore connection
structure and the corresponding parts having the same structure, wherein the waterside
wall body of the receiving-side shore connection structure has a wall hole and a first
sealing device is disposed along a circumference of the wall hole on a waterside face
of the waterside wall body; the pipe part stabilizing section is a reinforced concrete
box structure in which a hoop-type pipe part stabilizing device is disposed; the sealing
section is a sealing wall with a wall hole and a second sealing device is disposed
along the wall hole on a waterside face of the sealing wall; the pipe fixing section
is a reinforced concrete box structure which is located behind the sealing section,
with a steer sealing gate arranged on a rear end thereof; and the drawing and anchor
section is located between the steer sealing gate of the pipe fixing section and the
landside wall body, and a reinforced concrete abutment pier is disposed on a bottom
of the drawing and anchor section, with a pile foundation disposed under the abutment
pier and a traction device for traction ropes disposed on the abutment pier;
the cable anchorage system includes four cable anchorage piers, a plurality of stay
cables and two temporary cable anchorage piers, wherein the four cable anchorage piers
are respectively disposed on both sides of the tunnel on the launching-side shore
and on the receiving-side shore; each stay cable has a first end and a second end,
the first ends of the plurality of stay cables are anchored at intervals on anchorages
which are disposed on two side faces of the submerged floating tunnel, and the second
ends of the plurality of stay cables are extended from the water to the ground and
then anchored on the cable anchorage piers; and the two temporary cable anchorage
piers are respectively disposed beside the two cable anchorage piers located on the
launching-side shore; and
the buoyancy-weight ratio adjustment system is arranged in the water supply and drainage
room of each pipe part;
the incremental launching process comprising the steps of:
Step 1: prefabricating all the pipe parts and conducting primary outfitting of the
pipe parts in a fabrication yard behind the launching-side land slope tunnel;
Step 2: transporting the first pipe part from the launching-side land slope tunnel
to the horizontal transportation section in the launching-side shore connection structure
via a flat car, and removing the flat car after the jack drives the jacking-up beam
of the horizontal transportation section to jack up the first pipe part;
Step 3: conducting secondary outfitting of the first pipe part in the launching-side
shore connection structure and installing a cone-shaped pushing beam and two traction
ropes on a front end of the first pipe part;
Step 4: inserting the carrying airbag between the first pipe part and the jacking-up
beam and inflating the carrying airbag to make the first pipe part move forward to
the thrust section, so that the head of the first pipe part is located behind the
temporary seal gate and a tail of the first pipe part remains in the butting section
for being connected to a second pipe part; and at the same time, starting the hoop-type
thrust device disposed in the trust section to fix the first pipe part temporarily,
then sealing the trust section;
Step 5: first, transporting the second pipe part to the horizontal transportation
section located in the launching-side shore connection structure; next, removing the
flat car after the jack drives the jacking-up beam of the horizontal transportation
section to jack up the second pipe part; then, conducting secondary outfitting of
the second pipe part; then, inserting the carrying airbag between the second pipe
part and the jacking-up beam, inflating the carrying airbag to make a head of the
second pipe part move forward to the butting section to be connected to the tail of
the first pipe part, and mounting first stay cables on a front end of the second pipe
part; and then setting up sealing walls at two ends of an inner cavity of the second
pipe part, respectively;
Step 6: first, putting the hydraulic pushing trolley in place, closing a seal door
of the pipe part connecting box, filling the pipe part connecting box with water and
adjusting a buoyancy-weight ratio for the first time; then loosing the hoop-type thrust
device so that the first pipe part and the second pipe part are in a floating state;
and then starting the hydraulic pushing trolley to push the first pipe part and the
second pipe part to move forward;
Step 7: at the beginning of pushing the first pipe part and the second pipe part,
pushing the water blocking plug disposed on the temporary sealing gate open via the
pushing beam which is disposed on the front end of the first pipe part, and pulling
the two traction ropes into the receiving-side shore connection structure by a floating
crane and connecting the two traction ropes to the traction device in the drawing
and anchor section;
Step 8: during pushing the first pipe part and the second pipe part, tightening the
two traction ropes by the traction device located in the drawing and anchor section,
and keeping pulling the first pipe part and the second pipe part in front and pushing
the first pipe part and the second pipe part behind until a tail of the second pipe
part remains in the butting section of the launching-side shore connection structure;
Step 9: pulling the first stay cables onto the two temporary cable anchorage piers
located on the launching-side shore;
Step 10: first, starting the hoop-type thrust device disposed in the trust section
to fix the second pipe part temporarily and starting the sealing hoops disposed on
the sealing wall body; then draining the pipe part connecting box, and then opening
the seal door of the pipe part connecting box and removing the hydraulic pushing trolley;
Step 11: connecting and pushing a plurality of the pipe parts in turn, which are from
a third pipe part to the one that follows a mid-span pipe part, by repeating Step
5, Step 6 and Steps 8-10, wherein every time one pipe part is pushed, the stay cables,
which are located on front ends of the pipe parts that have been pushed out of the
launching-side shore connection structure, are pulled onto the two temporary cable
anchorage piers on the launching-side shore in turn; and when the pipe part that follows
the mid-span pipe part is pushed, the first stay cables are pulled from the two temporary
cable anchorage piers to the two cable anchorage piers located on the receiving-side
shore by the floating crane;
Step 12: connecting and pushing the other pipe parts in turn, which are from a pipe
part following the one that is behind the mid-span pipe part to the last pipe part,
by repeating Step 5, Step 6 and Steps 8-10, wherein every time one pipe part is pushed,
the stay cables, from second stay cables located on the third pipe part to stay cables
located on the mid-span pipe part, are pulled onto the two cable anchorage piers located
on the receiving-side shore in turn, and the stay cables, from stay cables located
on the pipe part following the mid-span pipe part to stay cables located on the last
pipe part, are pulled onto the two cable anchorage piers located on the launching-side
shore in turn, until the last pipe part is pushed in place, thereby the tail of the
last pipe part remains in the butting section and the head of the first pipe part
extends into the pipe fixing section of the receiving-side shore connection structure;
and starting the sealing devices disposed in the receiving-side shore connection structure
to seal the head of the first pipe part, and at the same time, starting the hoop-type
thrust device disposed in the launching-side shore connection structure to fix the
tail of the last pipe part temporarily;
Step 13: draining the pipe part connecting box and removing the hydraulic pushing
trolley, then consolidating the tail of the last pipe part in the launching-side shore
connection structure; and at the same time, draining the pipe fixing section of the
receiving-side shore connection structure, removing the pushing beam, the two traction
ropes, and the abutment pier and the traction device located in the drawing and anchor
section, and consolidating the head of the first pipe part in the receiving-side shore
connection structure;
Step 14: performing subsequent facility construction in the submerged cable-stayed
floating tunnel, which includes removal of the sealing walls in each pipe part, road
construction of the submerged floating tunnel, installation and internal decoration
of wind facilities, water facilities and electric facilities in the submerged floating
tunnel; and at the same time, adjusting the buoyancy-weight ratio for the second time;
Step 15: adjusting the buoyancy-weight ratio for the third time by injecting water
into the water supply and drainage rooms of the pipe parts part by part; and
Step 16: adjusting cable force of the stay cables one by one, and then sealing-off
and covering the stay cables.
[0009] In Step 5 of above incremental launching process for a submerged cable-stayed floating
tunnel, the second pipe part and the first pipe part are connected under a dry construction
condition, and the second pipe part and the first pipe part are connected by pipe
joints, joint fasteners, joint filling materials and joint sealing materials.
[0010] In Step 7 and Step 8 of above incremental launching process for a submerged cable-stayed
floating tunnel, the first pipe part and the second pipe part are pushed under a wet
construction condition.
[0011] In Step 13 of above incremental launching process for a submerged cable-stayed floating
tunnel, an outer surface of the head of the first pipe part and an inner surface of
the pipe fixing section of the receiving-side shore connection structure are consolidated
by pouring concrete, and an outer surface of the tail of the last pipe part and an
inner surface of the pipe part connecting box of the launching-side shore connection
structure is consolidated by pouring concrete.
[0012] In above incremental launching process for a submerged cable-stayed floating tunnel,
the buoyancy-weight ratio is adjusted for the first time, the second time and the
third time by injecting water into or pumping water out of the water supply and drainage
room of each pipe part.
[0013] The incremental launching process for a submerged cable-stayed floating tunnel of
the present invention has the following features:
- 1. The pipe parts of the present invention are installed under a dry construction
condition in the launching-side shore connection structure, which is less affected
by wind, waves, currents, ship waves and so on, thereby reducing the risk of offshore
construction greatly;
- 2. Without a floating connection or an underwater pendulum connection, the present
invention reduces the difficulty of construction and avoids the risk of collisions
between the pipe parts, thereby ensuring the structural safety;
- 3. Besides pulling the traction ropes, the present invention has a low frequency of
using construction ships, so the construction has little influence on surface ship
traffic and the seal hoops are greatly reduced.
- 4. The present invention adopts the factory-like connection to connect the pipe parts
in the shore connection structure, so the connection precision is greatly improved,
the water stop effects are greatly enhanced, and the overall quality of the tunnel
is more controllable.
- 5. The present invention is basically carried out under a dry construction condition
in land area, so there is no need to select an installation window period and the
present invention has high construction efficiency and short construction period.
- 6. The present invention basically doesn't need large-scale ship machines, which greatly
shortens the construction period and reduce the costs.
BRIEF DESCRPTION OF THE DRAWINGS
[0014]
FIG. 1 is a plan view of a submerged cable-stayed floating tunnel adapted for an incremental
launching process of the present invention;
FIG. 2 is a longitudinal cut view of the submerged cable-stayed floating tunnel adapted
for the incremental launching process of the present invention;
FIG. 3 is a transverse cut view of the submerged cable-stayed floating tunnel adapted
for the incremental launching process of the present invention;
FIG. 4 is a longitudinal sectional view of a launching-side shore connection structure
of the submerged cable-stayed floating tunnel adapted for the incremental launching
process of the present invention;
FIG. 5 is a longitudinal sectional view of a receiving-side shore connection structure
of the submerged cable-stayed floating tunnel adapted for the incremental launching
process of the present invention;
FIG. 6 is an arrangement view of an incremental launching arrangement used in the
incremental launching process for a submerged cable-stayed floating tunnel of the
present invention;
FIG. 7 is a state view illustrating the incremental launching process for a submerged
cable-stayed floating tunnel of the present invention at Step 5;
FIG. 8 is a state view illustrating the incremental launching process for a submerged
cable-stayed floating tunnel of the present invention at Step 6;
FIG. 9 is a state view illustrating the incremental launching process for a submerged
cable-stayed floating tunnel of the present invention at Step 8; and
FIG. 10 is a plan view illustrating the incremental launching process for a submerged
cable-stayed floating tunnel of the present invention at Step 8.
DETAILED DESCRPTION OF THE PREFERRED EMBODIMENTS
[0015] The present invention will be further described below in combination with the drawings.
[0016] Please refer to Figs. 1-10, a floating tunnel, adapted for an incremental launching
process for a submerged cable-stayed floating tunnel of the present invention, includes
a tunnel body, a launching-side shore connection structure 2, a receiving-side shore
connection structure 2', a cable anchorage system and a buoyancy-weight ratio adjustment
system. The tunnel body includes a submerged floating tunnel 1, a launching-side land
slope tunnel 6 and a receiving-side land slope tunnel 6'. The launching-side shore
connection structure 2 and the receiving-side shore connection structure 2' are located
on a launching-side shore 5 and a receiving-side shore 5', respectively. A waterside
end of the launching-side land slope tunnel 6 and a waterside end of the receiving-side
land slope tunnel 6' are connected to landside ends of the launching-side shore connection
structure 2 and the receiving-side shore connection structure 2', respectively. The
submerged floating tunnel 1 is formed by connecting a plurality of pipe parts 10,
and a head of a first pipe part and a tail of a last pipe part of the submerged floating
tunnel 1 are fixed in an inner cavity of the receiving-side shore connection structure
2 and an inner cavity of the launching-side shore connection structure 2', respectively.
Each pipe part 10 is divided into an upper tunnel layer, a middle tunnel layer and
a lower tunnel layer by an upper partition and a lower partition, and the upper tunnel
layer is a process room, the middle tunnel layer is a tunnel traffic room, and the
lower tunnel layer is a water supply and drainage room.
[0017] From sea area to land area, the launching-side shore connection structure 2, in turn,
includes a scour protection section 21, a starting section 22, a retaining wall for
a portal section 2A, a portal section 23, a waterside wall body 2B, a thrust section
24, a sealing section 25, a butting section 26, a pushing section 27, a horizontal
transportation section 28 and a landside wall body 2C. A temporary sealing gate 231
and corresponding sealing devices are arranged on a front side face of the waterside
wall body 2B, with a water blocking plug disposed on the temporary sealing gate 231.
The thrust section 24 is a sealed box structure in which a hoop-type thrust device
240 is set. The sealing section 25 is a sealing wall body with a wall hole, sealing
hoops are respectively disposed on a front side face and a rear side face of the sealing
wall body along a circumference of the wall hole, and water-stop strips are disposed
between the wall hole and an outer surface of the corresponding pipe part 10. The
butting section 26 and the pushing section 27 are both arranged in a pipe part connecting
box 20 which is capable of being opened and sealed. The butting section 26 has a stepped
pipe part butting pit 260 formed in a bottom thereof. Carrying airbags are placed
on a bottom of the pushing section 27, and a positioning section for a hydraulic pushing
trolley 270 is located at the rear of the pushing section 27. The horizontal transportation
section 28 has a jacking-up beam disposed on a bottom thereof, which may be driven
by a jack. When the pushing operation of all the pipe parts is completed, the tail
of the last pipe part 10 remains in the butting section 26, and concrete is poured
between an outer surface of the tail of the last pipe part 10 and an inner surface
of the pipe part connecting box 20 so that the last pipe part 10 and the launching-side
shore connection structure 2 are consolidated together.
[0018] From sea area to land area, the receiving-side shore connection structure 2', in
turn, includes a scour protection section 21, a receiving section 22', a retaining
wall for a portal section 2A, a portal section 23, a waterside wall body 2B, a pipe
part stabilizing section24', a sealing section 25, a pipe fixing section 26', a drawing
and anchor section 27' and a landside wall body 2C. The scour protection section 21,
the receiving section 22', the retaining wall for a portal section 2A, the portal
section 23, the waterside wall body 2B, the sealing section 25 and the landside wall
body 2C of the receiving-side shore connection structure 2' are in one-to-one correspondence
with the scour protection section 21, the starting section 22, the retaining wall
for a portal section 2A, the portal section 23, the waterside wall body 2B, the sealing
section 25 and the landside wall body 2C of the launching-side shore connection structure
2, that is, the corresponding parts have the same structure and function.
[0019] The waterside wall body 2B of the receiving-side shore connection structure 2' has
a wall hole formed through the waterside wall body 2B. Sealing devices 232 are disposed
along the wall hole on a waterside face of the receiving-side shore connection structure
2', and the sealing devices 232 adopt sealing hoops on which rubber water-stop strips
are disposed. The pipe part stabilizing section 24' is a sealing box structure, with
a manhole formed in a top thereof and an embedded cover disposed in the manhole. Further,
hoop-type pipe part stabilizing devices are disposed in the pipe part stabilizing
section 24' for stable control of postures of the pipe parts 10 after the pipe parts
10 are pushed into the pipe part stabilizing section 24'. The sealing section 25 is
a sealing wall with a wall hole, and on a waterside face of the sealing wall, there
also are sealing devices 232 disposed along the wall hole. Water-stop strips are placed
between the wall hole and an outer surface of the corresponding pipe part 10. The
pipe fixing section 26' is located behind the sealing section 25 and has the same
structure as the pipe part stabilizing section 24', that is, it is also a reinforced
concrete box structure. A steer sealing gate 26A is arranged on a rear end of the
pipe fixing section 26' to form a sealed cabin with the pipe fixing section 26', thereby
preventing seawater from flowing backwards. After the first pipe part 10 is pushed
into the pipe fixing section 26', the sealing device 232 disposed on the waterside
wall body 2B and the sealing device 232 disposed on the sealing section 25 are opened
and the pipe fixing section 26' is drained to achieve a dry construction condition,
and then the concrete, which is located on an outer surface of the head of the first
pipe part 10 located in the pipe fixing section 26', is poured, so that the first
pipe part 10 and the receiving-side shore connection structure 2' are consolidated
together. The drawing and anchor section 27' is located between the steer sealing
gate 26A of the pipe fixing section 26' and the landside wall body 2C. A reinforced
concrete abutment pier is disposed on a bottom of the drawing and anchor section 27',
and a pile foundation is disposed under the abutment pier and a traction device 27A
with high power for traction ropes 12 is disposed on the abutment pier. After the
pipe parts are pushed into place and fixed, the abutment pier and the traction device
27A are removed, and then the head of the first pipe part and the receiving-side land
slope tunnel 6' are connected to each other by cast-in-place reinforced concrete.
[0020] The cable anchorage system includes four cable anchorage piers 4, a plurality of
stay cables 3 and two temporary cable anchorage piers 4A. Two of the cable anchorage
piers 4 are disposed on both sides of the tunnel on the launching-side shore 5 respectively,
and the other two cable anchorage piers 4 are disposed on both sides of the tunnel
on the receiving-side shore 5' respectively. Each stay cable 3 has a first end and
a second end. The first ends of the plurality of stay cables 3 are anchored at intervals
on anchorages 30 which are disposed on two side faces of the submerged floating tunnel
1, and the second ends of the plurality of stay cables 3 are extended from the water
to the ground and then anchored on the cable anchorage piers 4. The two temporary
cable anchorage piers 4A are respectively disposed beside the two cable anchorage
piers 4 which are located on the launching-side shore 5. The two temporary cable anchorage
piers 4A are adopted for temporary anchorage of the stay cables 3 located on the front
half-span pipe parts during the pushing operation. When the pipe parts are pushed
more than halfway, the temporarily anchored stay cables are pulled to the receiving-side
shore 5' by a floating crane to be connected to traction ropes which are prearranged
in underwater steering piers, and then tightened by the cable anchorage piers 4 located
on the receiving-side shore 5' and fixed on the cable anchorage piers 4.
[0021] The buoyancy-weight ratio adjustment system is arranged in the water supply and drainage
room of each pipe part 10.
[0022] The incremental launching process for a submerged cable-stayed floating tunnel of
the present invention includes the steps as follows.
Step 1: prefabricating all the pipe parts and conducting primary outfitting of the
pipe parts in a fabrication yard 100 behind the launching-side land slope tunnel 6;
Step 2: transporting the first pipe part from the launching-side land slope tunnel
6 to the horizontal transportation section 28 in the launching-side shore connection
structure 2 via a flat car, and removing the flat car after the jack drives the jacking-up
beam of the horizontal transportation section 28 to jack up the first pipe part;
Step 3: conducting secondary outfitting of the first pipe part in the launching-side
shore connection structure 2, and installing a cone-shaped pushing beam 11 and two
traction ropes 12 on a front end of the first pipe part;
Step 4: inserting the carrying airbag between the first pipe part and the jacking-up
beam and inflating the carrying airbag to make the first pipe part move forward to
the thrust section 24, so that the head of the first pipe part is located behind the
temporary seal gate 231 and a tail of the first pipe part remains in the butting section
26 for being connected to a second pipe part, and at the same time, starting the hoop-type
thrust device 240 disposed in the trust section 24 to fix the first pipe part temporarily;
Step 5: first, transporting the second pipe part to the horizontal transportation
section 28 located in the launching-side shore connection structure 2; next, removing
the flat car after the jack drives the jacking-up beam of the horizontal transportation
section 28 to jack up the second pipe part; then conducting secondary outfitting of
the second pipe part; then, inserting the carrying airbag between the second pipe
part and the jacking-up beam, inflating the carrying airbag to make a head of the
second pipe part move forward to the butting section 26to be connected to the tail
of the first pipe part, and mounting first stay cables 3 on a front end of the second
pipe part; and then setting up sealing walls at two ends of an inner cavity of the
second pipe part, respectively; wherein the head of the second pipe part and the tail
of the first pipe part are connected by pipe joints, joint fasteners, joint filling
materials and joint sealing materials, and the joint fasteners include internal fasteners
and external fasteners, the internal fasteners are a vertical anchoring type and each
includes a high-strength stainless steel bolt which is mainly used for bearing shear
force, and a nut and a gasket matching the bolt, and the external fasteners include
a plurality of anchor sockets which are arranged on the inner surface of each pipe
part and close to an opening of each pipe part, and steel strands or prestressed steel
bars which are connected between the anchor sockets of every two connected pipe parts
10 by the anchorages, and the external fasteners are mainly used for being tensioned
when the pipe parts 10 are connected to each other and involved in bearing a horizontal
tensile force during tunnel operation period;
Step 6: first, putting the hydraulic pushing trolley 270 in place, closing a seal
door of the pipe part connecting box 20, filling the pipe part connecting box 20 with
water and adjusting a buoyancy-weight ratio for the first time; then loosing the hoop-type
thrust device 240 so that the two pipe parts are in a floating state; and then starting
the hydraulic pushing trolley 270 to push the two pipe parts to move forward;
Step 7: at the beginning of pushing the two pipe parts, pushing the water blocking
plug disposed on the temporary sealing gate 231 open via the pushing beam 11 which
is disposed on the front end of the first pipe part, so as to balance an internal
water pressure and an external water pressure, thereby it is easy to push the temporary
sealing gate 231 open; and then pulling the two traction ropes 12 into the receiving-side
shore connection structure 2' by the floating crane and connecting the two traction
ropes 12 to the traction device 27A in the drawing and anchor section 27';
Step 8: during the pushing operation, tightening the two traction ropes 12 by the
traction device 27A located in the drawing and anchor section 27', and keeping pulling
the first pipe part and the second pipe part in front and pushing the first pipe part
and the second pipe part behind until a tail of the second pipe part remains in the
butting section 26 of the launching-side shore connection structure 2;
Step 9: pulling the first stay cables 3 onto the two temporary cable anchorage piers
4A located on the launching-side shore 5;
Step 10: first, starting the hoop-type thrust device 240 disposed in the trust section
24 to fix the second pipe part temporarily and starting the sealing hoops disposed
on the sealing wall 25; then draining the pipe part connecting box 20, and then opening
the seal door of the pipe part connecting box 20 and removing the hydraulic pushing
trolley 270;
Step 11: connecting and pushing a plurality of the pipe parts in turn, which are from
a third pipe part to the one that follows a mid-span pipe part, by repeating Step
5, Step 6 and Steps 8-10, wherein every time one pipe part is pushed, the stay cables
3, which are located on the front ends of the pipe parts that have been pushed out
of the launching-side shore connection structure 2, are pulled onto the two temporary
cable anchorage piers 4A on the launching-side shore 5 in turn; and when the pipe
part that follows the mid-span pipe part is pushed, the first stay cables 3 are pulled
from the two temporary cable anchorage piers 4A to the cable anchorage piers 4 placed
on the receiving-side shore 5' by the floating crane;
Step 12: connecting and pushing the other pipe parts in turn, which are from a pipe
part following the one that is behind the mid-span pipe part to the last pipe part,
by repeating Step 5, Step 6 and Steps 8-10, wherein every time one pipe part is pushed,
the stay cables 3, from second stay cables 3 located on the third pipe part to stay
cables 3 located on the mid-span pipe part, are pulled onto the two cable anchorage
piers 4 located on the receiving-side shore 5' in turn, and the stay cables, from
stay cables 3 located on the pipe part following the mid-span pipe part to stay cables
3 located on the last pipe part, are pulled onto the two cable anchorage piers 4 located
on the launching-side shore 5 in turn, until the last pipe part is pushed in place,
thereby the tail of the last pipe part remains in the butting section 26 and the head
of the first pipe part extends into the pipe fixing section 26' of the receiving-side
shore connection structure 2'; and starting the sealing devices 232 disposed in the
receiving-side shore connection structure 2' to seal the head of the first pipe part,
and at the same time, starting the hoop-type thrust device 240 disposed in the launching-side
shore connection structure 2 to fix the tail of the last pipe part temporarily;
Step 13:draining the pipe part connecting box 20 and removing the hydraulic pushing
trolley 270, then pouring concrete between the outer surface of the tail of the last
pipe part and the inner surface of the pipe part connecting box 20 of the launching-side
shore connection structure 2 so that the tail of the last pipe part is consolidated
in the launching-side shore connection structure 2; and at the same time, draining
the pipe fixing section 26' of the receiving-side shore connection structure 2' dry,
removing the pushing beam 11, the two traction ropes 12, and the abutment pier and
the traction device 27A located in the drawing and anchor section 27'; and then pouring
concrete between the outer surface of the head of the first pipe part and the inner
surface of the pipe fixing section 26' of the receiving-side shore connection structure
2' so that the head of the first pipe part is consolidated in the receiving-side shore
connection structure 2';
Step 14: performing the subsequent facility construction in the submerged cable-stayed
floating tunnel, which includes removal of the sealing walls in each pipe part 10,
road construction of the submerged floating tunnel 1, installation and internal decoration
of wind facilities, water facilities and electric facilities in the submerged floating
tunnel 1; and at the same time, adjusting the buoyancy-weight ratio for the second
time;
Step 15: adjusting the buoyancy-weight ratio for the third time by injecting water
into or pumping water out of the water supply and drainage rooms of the pipe parts
10 part by part; and
Step 16: adjusting the cable force of the stay cables 3 one by one, and then sealing-off
and covering the stay cables.
[0023] The overall process of the incremental launching process for a submerged cable-stayed
floating tunnel includes: prefabricating all the pipe parts of the tunnel in land,
transporting the pipe parts in the land slope tunnel, connecting the pipe parts in
the shore connection structures, and wet-pushing the pipe parts and pulling and locating
the traction ropes simultaneously after dry-wet transformation.
[0024] Considering the design buoyancy-weight ratio of the pipe parts is equal to 1 during
the pushing operation, in the present invention, the buoyancy-weight ratio is adjusted
to the design buoyancy-weight ratio by water ballasting of the pipe parts. When the
pipe parts are pushed and installed, buoyancy is used to support the weight of the
pipe parts to keep them basically at the design depth in the water. According to Archimede's
floating law, when gravity is equal to buoyancy, in theory, objects in water may stay
anywhere in the water of the same density; moreover, seawater density generally increases
with depth, that is, buoyancy increases with depth, so the sealed pipe parts which
are pushed into water won't float or sink, but they may shake up and down. The shaking
amplitude of the pipe parts is related to currents and waves, and the larger the current
force is, the greater the shaking amplitude is. Therefore, it is necessary to use
the stay cables to restrict the pipe parts and properly decrease the buoyancy-weight
ratio simultaneously, so that the pipe parts are in a downward trend.
[0025] Under the action of horizontal forces generated by currents, waves and so on, the
pipe parts which are pushed into the water will rotate and displace, so the pipe parts
need to be limited. It is different from an incremental launching process for bridges,
there is no support and restriction of temporary piers when a pipe part is pushed
in the water, so the pipe part is easy to deviate from its direction and a large horizontal
bending moment is produced at the portion of the pipe part which enters the water.
Thus, the present invention takes three measures, the first one is to set a starting
section outside the launching-side shore connection structure for stating limit; the
second one is to set the traction ropes on the headmost end of the pipe parts, anchor
the traction ropes in the receiving-side shore connection structure in advance, and
pull the pipe parts in front and push the pipe parts behind during the pushing operation;
and the third one is to use the stay cables to carry horizontal loads and vertical
loads to maintain the pipe parts in a desired direction.
[0026] A dry construction method is used to connect the pipe parts in the present invention,
which is executed in the launching-side shore connection structure. After the pipe
parts are connected, the secondary outfitting is conducted. So the butting section
is arranged in the launching-side shore connection structure, that is, the tail of
the pushed pipe part is exposed under a dry construction condition in the launching-side
shore connection structure 2 for easy connection. For achieving the dry construction
condition, it is necessary to form a seal between the launching-side shore connection
structure and the pushed pipe part, so the sealing section is arranged in the launching-side
shore connection structure, and only the tail of the pipe part is located under the
dry condition. Due to the transformation between the dry condition and the wet condition,
the pushed pipe part will be pushed in a reverse direction under deep water pressure
outside the launching-side shore connection structure. So the pushed pipe part must
be fixed temporarily and the thrust operation starts. The present invention takes
three thrust measures, the first one is to set the thrust section in the launching-side
shore connection structure, which adopts the hoop-type thrust device to provide the
friction force between its hoop and the pipe part; the second one is to pull the pipe
part on the opposite shore with the traction ropes disposed on the front end of the
pipe part; and the third one is to set the cone-shaped beam on the front end of the
pipe part to reduce water pressure.
[0027] In the present, a wet pushing method is used to push the pipe parts, that is, the
pipe parts are pushed when the entire pipe parts suspend in water. In the launching-side
shore connection structure, the butting section and the pushing section are arranged
in the pipe part connecting box and the hydraulic pushing trolley driven by underwater
gears is installed for pushing the pipe parts. Before the pushing operation, the pipe
part connecting box is sealed and filled with water so as to completely immerse the
hydraulic pushing trolley and the connected pipe parts, and then the thrust device
is loosed so that the pipe parts are in a floating state. Since the balance of water
pressure in front of the pipe parts and behind the pipe parts is maintained, the pushing
operation is only affected by water resistance caused by the moving speed of the pipe
parts, that is, it is easy to push the pipe parts. During the pushing operation, the
hydraulic pushing trolley pushes the pipe parts along its track to the butting section,
and at the same time, the traction ropes located on the front end of the pipe parts
are tightened, which means pulling the pipe parts in front and pushing the pipe parts
behind. When the pushing trip for one pipe part ends, the thrust device is started
for temporary fixation and the sealing hoops of the sealing section are started for
seal. Then the pipe part connecting box is drained, and the pipe part connecting box
corresponding to the butting section is opened, so that the tail of the pipe part
is exposed under the dry construction condition, and it starts to execute the loop
of connecting, sealing, injecting and pushing for a next pipe part.
[0028] In the present invention, the temporary sealing gate is arranged outside the waterside
wall body of the launching-side shore connection structure and the water blocking
plug is disposed on the temporary sealing gate which is fastened under deep water
pressure outside the wall body. During the pushing operation, the blocking plug is
opened to balance the internal water pressure and the external water pressure, and
therefore, it is easy to push the temporary sealing gate open. There is no temporary
sealing gate outside the waterside wall body of the receiving-side shore connection
structure, but the steer sealing gate is disposed behind the drawing and anchor section.
After the pipe part enters the steer sealing gate, the pipe part is fixed temporarily
and the concrete is poured around the pipe part. When the two ends of the tunnel and
the corresponding pipe parts are consolidated together, the steel sealing gates located
on the two ends of the tunnel are opened.
[0029] During the implementation of the incremental launching process for a submerged cable-stayed
floating tunnel of the present invention, the buoyancy-weight ratio of the pipe parts
is adjusted in three stages. The buoyancy-weight ratio is adjusted for the first time
after the pipe parts are connected and before the pushing operation begins, and the
first adjustment is mainly to ensure that the submerged floating tunnel is capable
of suspending in water during the pushing operation. The buoyancy-weight ratio is
adjusted for the second time during performing the subsequent construction of the
road and subsidiary facilities in the submerged floating tunnel, and the second adjustment
is mainly to ensure that the stress systems of the submerged floating tunnel meet
the design requirements since the construction of the subsidiary facilities in the
submerged floating tunnel causes an increase of the weight of the tunnel. The buoyancy-weight
ratio is adjusted for the third time after the subsequent construction of the facilities
in the submerged floating tunnel, and it mainly takes into account the load distribution
of the submerged floating tunnel during its operation period.
[0030] Before the pipe part is pushed and installed, the buoyancy-weight ratio is adjusted
to be slightly less than 1 by injecting water into the pipe part, that is, the adjustment
of the buoyancy-weight ratio is mainly achieved by storing water in the water supply
and drainage room of the pipe part. The density of water at the water depth where
the pipe part is located is obtained by sampling and measurement. The density of the
reinforced concrete of the pipe part is obtained by weighing a trial-produced reinforced
concrete block model. The volume of the reinforced concrete of the pipe part is determined
by actual measurement.
[0031] The subsequent road construction in the submerged floating tunnel is carried out
in sections, and at the same time, according to the added weight, water is pumped
out of the corresponding pipe part and the weight of the corresponding pipe part is
reduced in order to ensure that the buoyancy-weight ratio meets the design requirements.
[0032] After the subsequent construction of the facilities in the submerged floating tunnel
is completed, water is injected in sections in order to adjust the buoyancy-weight
ratio to the design value, and at the same time, the cable force of the stay cables
is measured in sections and the stay cables are tightened until the cable tension
reaches to the design value.
[0033] In the process of pushing the pipe parts toward the receiving-side shore connection
structure, it is needed to increase the length of the stay cables properly and maintain
the corresponding tension to hold the positions and postures of the pipe parts. Therefore,
according to the structural design requirements, a certain length of each stay cable
is reserved and placed in an anchor well, and the corresponding length of stay cable
may be released as required. The stay cables are tightened or released by the special
traction device and stress sensors are installed on the stay cables to monitor the
tension stress of the stay cables in real time.
[0034] What are disclosed above are only the preferred embodiments of the present invention,
not a limitation to the invention, and therefore for those skilled in prior art, various
modifications or changes may be made depending on the specification and the drawings
of the present invention without departing from the spirit and scope of the present
invention. All equivalent technical solutions will fall into the scope of the present
invention and be limited by the appended claims.
1. An incremental launching process for a submerged cable-stayed floating tunnel, the
submerged cable-stayed floating tunnel including a tunnel body, a launching-side shore
connection structure, a receiving-side shore connection structure, a cable anchorage
system and a buoyancy-weight ratio adjustment system, wherein the tunnel body includes
a submerged floating tunnel, a launching-side land slope tunnel and a receiving-side
land slope tunnel; the launching-side shore connection structure and the receiving-side
shore connection structure are respectively located on a launching-side shore and
a receiving-side shore; a waterside end of the launching-side land slope tunnel and
a waterside end of the receiving-side land slope tunnel are respectively connected
to landside ends of the launching-side shore connection structure and the receiving-side
shore connection structure;
the submerged floating tunnel is formed by connecting a plurality of pipe parts; a
head of a first pipe part and a tail of a last pipe part of the submerged floating
tunnel are respectively fixed in an inner cavity of the receiving-side shore connection
structure and an inner cavity of the launching-side shore connection structure; each
pipe part is divided into an upper tunnel layer, a middle tunnel layer and a lower
tunnel layer by an upper partition and a lower partition, wherein the upper tunnel
layer is a process room, the middle tunnel layer is a tunnel traffic room, and the
lower tunnel layer is a water supply and drainage room;
the launching-side shore connection structure includes a scour protection section,
a starting section, a retaining wall for a portal section, a portal section, a waterside
wall body, a thrust section, a sealing section, a butting section, a pushing section,
a horizontal transportation section and a landside wall body in turn from sea area
to land area, wherein a temporary sealing gate is arranged on a front side face of
the waterside wall body, with a water blocking plug disposed on the temporary sealing
gate; the thrust section is a sealed box structure and has a hoop-type thrust device;
the sealing section is a sealing wall body with a wall hole, with sealing hoops respectively
disposed on a front side face and a rear side face of the sealing section along a
circumference of the wall hole; a water-stop strip is disposed between the wall hole
and an outer surface of the corresponding pipe part; the butting section and the pushing
section are both arranged in a pipe part connecting box which is capable of being
opened and closed; the butting section has a stepped pipe part butting pit formed
in a bottom thereof; carrying airbags are disposed on a bottom of the pushing section
and a positioning section for a hydraulic pushing trolley is located at the rear of
the pushing section; and the horizontal transportation section has a jacking-up beam
disposed on a bottom thereof, which is driven by a jack;
the receiving-side shore connection structure includes a scour protection section,
a receiving section, a retaining wall for a portal section, a portal section, a waterside
wall body, a pipe part stabilizing section, a sealing section, a pipe fixing section,
a drawing and anchor section and a landside wall body in turn from sea area to land
area, the scour protection section, the receiving section, the retaining wall for
a portal section, the portal section, the waterside wall body, the sealing section
and the landside wall body of the receiving-side shore connection structure being
in one-to-one correspondence with the scour protection section, the starting section,
the retaining wall for a portal section, the portal section, the waterside wall body,
the sealing section and the landside wall body of the launching-side shore connection
structure and the corresponding parts having the same structure, wherein the waterside
wall body of the receiving-side shore connection structure has a wall hole and a first
sealing device is disposed along a circumference of the wall hole on a waterside face
of the waterside wall body; the pipe part stabilizing section is a reinforced concrete
box structure in which a hoop-type pipe part stabilizing device is disposed; the sealing
section is a sealing wall with a wall hole and a second sealing device is disposed
along the wall hole on a waterside face of the sealing wall; the pipe fixing section
is a reinforced concrete box structure which is located behind the sealing section,
with a steer sealing gate arranged on a rear end thereof; and the drawing and anchor
section is located between the steer sealing gate of the pipe fixing section and the
landside wall body, and a reinforced concrete abutment pier is disposed on a bottom
of the drawing and anchor section, with a pile foundation disposed under the abutment
pier and a traction device for traction ropes disposed on the abutment pier;
the cable anchorage system includes four cable anchorage piers, a plurality of stay
cables and two temporary cable anchorage piers, wherein the four cable anchorage piers
are respectively disposed on both sides of the tunnel on the launching-side shore
and on the receiving-side shore; each stay cable has a first end and a second end,
the first ends of the plurality of stay cables are anchored at intervals on anchorages
which are disposed on two side faces of the submerged floating tunnel, and the second
ends of the plurality of stay cables are extended from the water to the ground and
then anchored on the cable anchorage piers; and the two temporary cable anchorage
piers are respectively disposed beside the two cable anchorage piers located on the
launching-side shore; and
the buoyancy-weight ratio adjustment system is arranged in the water supply and drainage
room of each pipe part;
the incremental launching process comprising the steps of:
Step 1: prefabricating all the pipe parts and conducting primary outfitting of the
pipe parts in a fabrication yard behind the launching-side land slope tunnel;
Step 2: transporting the first pipe part from the launching-side land slope tunnel
to the horizontal transportation section in the launching-side shore connection structure
via a flat car, and removing the flat car after the jack drives the jacking-up beam
of the horizontal transportation section to jack up the first pipe part;
Step 3: conducting secondary outfitting of the first pipe part in the launching-side
shore connection structure and installing a cone-shaped pushing beam and two traction
ropes on a front end of the first pipe part;
Step 4: inserting the carrying airbag between the first pipe part and the jacking-up
beam and inflating the carrying airbag to make the first pipe part move forward to
the thrust section, so that the head of the first pipe part is located behind the
temporary seal gate and a tail of the first pipe part remains in the butting section
for being connected to a second pipe part; and at the same time, starting the hoop-type
thrust device disposed in the trust section to fix the first pipe part temporarily,
then sealing the trust section;
Step 5: first, transporting the second pipe part to the horizontal transportation
section located in the launching-side shore connection structure; next, removing the
flat car after the jack drives the jacking-up beam of the horizontal transportation
section to jack up the second pipe part; then, conducting secondary outfitting of
the second pipe part; then, inserting the carrying airbag between the second pipe
part and the jacking-up beam, inflating the carrying airbag to make a head of the
second pipe part move forward to the butting section to be connected to the tail of
the first pipe part, and mounting first stay cables on a front end of the second pipe
part; and then setting up sealing walls at two ends of an inner cavity of the second
pipe part, respectively;
Step 6: first, putting the hydraulic pushing trolley in place, closing a seal door
of the pipe part connecting box, filling the pipe part connecting box with water and
adjusting a buoyancy-weight ratio for the first time; then loosing the hoop-type thrust
device so that the first pipe part and the second pipe part are in a floating state;
and then starting the hydraulic pushing trolley to push the first pipe part and the
second pipe part to move forward;
Step 7: at the beginning of pushing the first pipe part and the second pipe part,
pushing the water blocking plug disposed on the temporary sealing gate open via the
pushing beam which is disposed on the front end of the first pipe part, and pulling
the two traction ropes into the receiving-side shore connection structure by a floating
crane and connecting the two traction ropes to the traction device in the drawing
and anchor section;
Step 8: during pushing the first pipe part and the second pipe part, tightening the
two traction ropes by the traction device located in the drawing and anchor section,
and keeping pulling the first pipe part and the second pipe part in front and pushing
the first pipe part and the second pipe part behind until a tail of the second pipe
part remains in the butting section of the launching-side shore connection structure;
Step 9: pulling the first stay cables onto the two temporary cable anchorage piers
located on the launching-side shore;
Step 10: first, starting the hoop-type thrust device disposed in the trust section
to fix the second pipe part temporarily and starting the sealing hoops disposed on
the sealing wall body; then draining the pipe part connecting box, and then opening
the seal door of the pipe part connecting box and removing the hydraulic pushing trolley;
Step 11: connecting and pushing a plurality of the pipe parts in turn, which are from
a third pipe part to the one that follows a mid-span pipe part, by repeating Step
5,
Step 6 and Steps 8-10, wherein every time one pipe part is pushed, the stay cables,
which are located on front ends of the pipe parts that have been pushed out of the
launching-side shore connection structure, are pulled onto the two temporary cable
anchorage piers on the launching-side shore in turn; and when the pipe part that follows
the mid-span pipe part is pushed, the first stay cables are pulled from the two temporary
cable anchorage piers to the two cable anchorage piers located on the receiving-side
shore by the floating crane;
Step 12: connecting and pushing the other pipe parts in turn, which are from a pipe
part following the one that is behind the mid-span pipe part to the last pipe part,
by repeating Step 5, Step 6 and Steps 8-10, wherein every time one pipe part is pushed,
the stay cables, from second stay cables located on the third pipe part to stay cables
located on the mid-span pipe part, are pulled onto the two cable anchorage piers located
on the receiving-side shore in turn, and the stay cables, from stay cables located
on the pipe part following the mid-span pipe part to stay cables located on the last
pipe part, are pulled onto the two cable anchorage piers located on the launching-side
shore in turn, until the last pipe part is pushed in place, thereby the tail of the
last pipe part remains in the butting section and the head of the first pipe part
extends into the pipe fixing section of the receiving-side shore connection structure;
and starting the sealing devices disposed in the receiving-side shore connection structure
to seal the head of the first pipe part, and at the same time, starting the hoop-type
thrust device disposed in the launching-side shore connection structure to fix the
tail of the last pipe part temporarily;
Step 13: draining the pipe part connecting box and removing the hydraulic pushing
trolley, then consolidating the tail of the last pipe part in the launching-side shore
connection structure; and at the same time, draining the pipe fixing section of the
receiving-side shore connection structure, removing the pushing beam, the two traction
ropes, and the abutment pier and the traction device located in the drawing and anchor
section, and consolidating the head of the first pipe part in the receiving-side shore
connection structure;
Step 14: performing subsequent facility construction in the submerged cable-stayed
floating tunnel, which includes removal of the sealing walls in each pipe part, road
construction of the submerged floating tunnel, installation and internal decoration
of wind facilities, water facilities and electric facilities in the submerged floating
tunnel; and at the same time, adjusting the buoyancy-weight ratio for the second time;
Step 15: adjusting the buoyancy-weight ratio for the third time by injecting water
into the water supply and drainage rooms of the pipe parts part by part; and
Step 16: adjusting cable force of the stay cables one by one, and then sealing-off
and covering the stay cables.
2. The incremental launching process for a submerged cable-stayed floating tunnel as
claimed in claim 1, wherein in Step 5, the second pipe part and the first pipe part
are connected under a dry construction condition, and the second pipe part and the
first pipe part are connected by pipe joints, joint fasteners, joint filling materials
and joint sealing materials.
3. The incremental launching process for a submerged cable-stayed floating tunnel as
claimed in claim 1, wherein in Step 7 and Step 8, the first pipe part and the second
pipe part are pushed under a wet construction condition.
4. The incremental launching process for a submerged cable-stayed floating tunnel as
claimed in claim 1, wherein in Step 13, an outer surface of the head of the first
pipe part and an inner surface of the pipe fixing section of the receiving-side shore
connection structure are consolidated by pouring concrete, and an outer surface of
the tail of the last pipe part and an inner surface of the pipe part connecting box
of the launching-side shore connection structure is consolidated by pouring concrete.
5. The incremental launching process for a submerged cable-stayed floating tunnel as
claimed in claim 1, wherein the buoyancy-weight ratio is adjusted for the first time,
the second time and the third time by injecting water into or pumping water out of
the water supply and drainage room of each pipe part.