[0001] The present disclosure relates to improvements in managing vertical movement in modular
construction.
BACKGROUND
[0002] Modular buildings comprise prefabricated building sections or modules that may be
manufactured off-site and transported to a construction site. On-site, the modules
may be assembled to form part or all of a building structure. These modules may be
assembled in any suitable manner to yield a robust and safe building. Typically, in
order to increase the height of a building such modules may be stacked on top of each
other.
[0003] The effect of vertical forces over time causes all buildings to experience shortening
of their vertical elements such as walls and columns. This effect is particularly
noticeable in taller buildings as the magnitude of vertical deflection increases with
height. As a result, the stacking of modules can yield an increase in the magnitude
of vertical deflection experienced by a modular building.
[0004] The embodiments described below are provided by way of example only and are not limiting
of implementations which solve any or all of the disadvantages of managing vertical
movement in modular construction.
[0005] The examples described herein are not limited to examples which solve problems mentioned
in this background section.
SUMMARY
[0006] Examples of preferred aspects and embodiments of the invention are as set out in
the accompanying independent and dependent claims.
[0007] This Summary is provided to introduce a selection of concepts in a simplified form
that are further described below in the Detailed Description. This Summary is not
intended to identify key features or essential features of the claimed subject matter,
nor is it intended to be used to limit the scope of the claimed subject matter.
[0008] A first aspect of the disclosed technology comprises a method for limiting visible
damage such as cracking within 3D modules through the control of vertical, flexural
and racking deflections. The method comprises determining an individual axial force
for each of a plurality of column elements that are stacked to form a column, wherein:
each of the plurality of column elements links a lower storey to an adjacent upper
storey of a modular building such that the column traverses a plurality of storeys
of the modular building, each of the plurality of column elements has a cross-sectional
area, the axial force of a column element in any given storey is the sum of the loads
entering the column element from all of the storeys above in that column, and each
storey comprises a plurality of column elements of different columns; determining
an individual Force-Area Ratio (FAR) for each of the plurality of column elements
based on the determined axial force for each of the plurality of column elements divided
by the cross-sectional area of each of the plurality of column elements; determining
a cumulative FAR for each of the plurality of column elements, each cumulative FAR
respectively comprising the sum total of each of the determined individual FARs for
each of the plurality of column elements summed successively from the column element
at the base of the column to the column element at the top of the column; and adjusting
the determined individual FAR of at least one column element to adjust the cumulative
FAR of the at least one column element within a specified target range of the cumulative
FARs of the other column elements of the storey that the at least one column element
occupies.
[0009] In this way, FARs across storeys are balanced within a specified target range thereby
maintaining the level of the storeys. This allows vertical, flexural and racking deflections
in a modular building to be controlled, thereby limiting damage such a cracking.
[0010] In some preferred example embodiments, adjusting at least one determined individual
FAR of at least one column element comprises adjusting the nominal storey-to-storey
height of the modular building by one or more of: adding a first shim of a specified
size to at least one of the plurality of column elements; adjusting a thickness of
at least one tie-plate; and adjusting a length of at least one of the plurality of
column element to adjust the cross-sectional area of the at least one column element.
In this way, determined individual FARs of given column elements can be manipulated
in order to subsequently adjust the cumulative FARs of the given column elements.
[0011] In some preferred example embodiments, the method comprises adjusting the cumulative
FAR of the at least one column element to within a FAR tolerance range of the average
cumulative FAR of the storey that the at least one column element occupies. In this
way, the cumulative FARs as summed successively up each storey lie within a FAR tolerance
range.
[0012] In some preferred example embodiments, the FAR tolerance range of the average cumulative
FAR of the storey that the at least one column occupies is up to 25 per cent of a
permitted deformation available to the at least one column element. In this way, the
FAR contribution to the permitted deformation of the column element is limited.
[0013] In some preferred example embodiments, the method comprises adjusting for poor tolerances
of length of the plurality of column elements by using a second shim. In this way,
poor tolerances in length of column elements can be compensated, contributing to maintaining
level across storeys.
[0014] In some preferred example embodiments, the method comprises offsetting deflections
experienced in an upper cluster of co-located column elements by sandwiching at least
one tie-plate between lower cluster of co-located column elements and the upper cluster
of co-located column elements, wherein the lower cluster of co-located column elements
comprises a plurality of columns elements occupying a first storey, the upper cluster
of co-located column elements comprises a plurality of column elements occupying a
second storey immediately above the first storey and the lower cluster of co-located
column elements and the upper cluster of co-located column elements are substantially
aligned. In this way, forces arising from residual column shortening can be redistributed.
[0015] In some preferred example embodiments, the method comprises offsetting variable vertical
displacements between at least one core element of the modular building and at least
one of the plurality of column elements by using a compliant element, wherein: the
at least one core element comprises a fixed structure within the modular building
and the compliant element is arranged substantially perpendicular to the axis of the
variable vertical displacements and is configured to: adjoin the at least one core
element and at least one of the plurality of column elements; transfer lateral forces
that are applied to the modular building along its length via axial forces in the
compliant element; deform plastically in flexure to offset variable vertical displacements
as a result of a differential vertical movement between the core element and the at
least one of the plurality of column elements; and deform elastically to offset variable
vertical displacements as a result of at least one of lateral or vertical forces applied
to the building. In this way, variable vertical displacements between core elements
and column elements can be offset during construction and thereafter.
[0016] In some preferred example embodiments, the compliant element is configured to deform
elastically within a predetermined range. In this way, small variable vertical displacements
that occur after stacking of modules can be offset.
[0017] In some preferred example embodiments, adjoining the at least one core element and
at least one of the plurality of column elements comprises affixing a first end of
the compliant element to the one of the at least one tie-plates and affixing a second
end of the compliant element to a plate affixed to the at least one core element,
wherein the first end and the second end of the compliant element are substantially
opposite. In this way, variable vertical displacements experienced between the core
element and the column elements are able to be offset.
[0018] In some preferred example embodiments, the compliant element is any of one of a bar,
a sectional profile or a plate.
[0019] In some preferred example embodiments, the compliant element is manufactured of metal.
[0020] In some preferred example embodiments, the method comprises compensating for elastic
shortening of at least one column element by attaching at least one headed stud to
a structure that moves with the uppermost surface of at least one column element in
the at least one column, wherein the headed stud is configured to move within a ceiling
rail from a first position to a second position independently of the uppermost surface
of the at least one column element by traversing an opening in the ceiling rail. In
this way, elastic shortening of column elements can be compensated by allowing a ceiling
rail to move independently of the ceiling of the column element.
[0021] In some preferred example embodiments, the magnitude of the movement of the ceiling
rail is within a predetermined range of movement to accommodate the effects of column
axial shortening, structural flexure under in-service loads and cumulative manufacturing
tolerances.
[0022] In some preferred example embodiments, the diameter of the opening of the ceiling
rail exceeds that of the shaft of the headed stud and is less than that of the diameter
of the headed stud. In this way, the stud can traverse the opening of the ceiling
rail.
[0023] In some preferred example embodiments, the stiffness of the ceiling rail enables
the ceiling rail to deflect within a predetermined threshold level for a specified
span of the ceiling rail. In this way, the relative stiffness of the ceiling rail
allows the ceiling rail to deflect only within a specified range across its span.
[0024] It will also be apparent to anyone of ordinary skill in the art, that some of the
preferred features indicated above as preferable in the context of one of the aspects
of the disclosed technology indicated may replace one or more preferred features of
other ones of the preferred aspects of the disclosed technology. Such apparent combinations
are not explicitly listed above under each such possible additional aspect for the
sake of conciseness.
[0025] Other examples will become apparent from the following detailed description, which,
when taken in conjunction with the drawings, illustrate by way of example the principles
of the disclosed technology.
BRIEF DESCRIPTION OF THE DRAWINGS
[0026]
FIG. 1 illustrates an isometric cut-away of an exemplary building with column elements;
FIG. 2 is a table illustrating how the maximised individual Force-Area Ratio is obtained
at every storey in the building of FIG. 1;
FIG. 3 is a table showing the effects of using a reduced number of column elements
of different sizes on the cumulative Force-Area Ratios within a given storey of the
building of FIG. 1;
FIG. 4 is a table showing the balanced Force-Area Ratios for column element adjusted
to obtain a balanced Force-Area Ratio within a given storey of the building of FIG.
1;
FIG. 5A illustrates the isometric cut-away of the exemplary building of FIG.1 with
the addition of shims on given column elements and provides an expanded view illustrating
the addition of a shim on a given column element;
FIG. 5B is table showing the effects on individual and cumulative FARs as a result
of adding shims to given column elements;
FIG. 6A is a table illustrating the average cumulative FARs across storeys for an
exemplary unshimmed building;
FIG. 6B is a table illustrating the average cumulative FARs across storeys for an
exemplary shimmed building;
FIG. 7 is table showing the sum total of all of the cross-sectional areas of each
of the buildings represented in the tables of FIGs. 2, 3, 4 and 5B;
FIG. 8 is a simplified flow diagram of an exemplary method for limiting damage in
3D modules;
FIG. 9A is a simplified angular view diagram of a tie-plate in use with a cluster
of column elements;
FIG. 9B is a simplified frontal view diagram of a tie-plate in use with a cluster
of column elements;
FIG. 10 is an exemplary diagram of a compliant element in use with a core element
and a cluster of column elements;
FIG. 11A illustrates a schematic section through a column element; and
FIG. 11B shows an expanded schematic section of the ceiling of the column element
as depicted in FIG. 11A.
[0027] The accompanying drawings illustrate various examples. The skilled person will appreciate
that the illustrated element boundaries (e.g., boxes, groups of boxes, or other shapes)
in the drawings represent one example of the boundaries. It may be that in some examples,
one element may be designed as multiple elements or that multiple elements may be
designed as one element. Common reference numerals are used throughout the figures,
where appropriate, to indicate similar features.
DETAILED DESCRIPTION
[0028] The following description is made for the purpose of illustrating the general principles
of the present technology and is not meant to limit the inventive concepts claimed
herein. As will be apparent to anyone of ordinary skill in the art, one or more or
all of the particular features described herein in the context of one embodiment are
also present in some other embodiment(s) and/or can be used in combination with other
described features in various possible combinations and permutations in some other
embodiment(s).
[0029] This disclosure relates to a method for managing vertical movement in modular buildings.
In particular, but not exclusively, it relates to maintaining level of storeys within
modular buildings and offsetting any further effects of differential vertical movement.
[0030] The following description is presented by way of example to enable a person skilled
in the art to make and use the invention. The present invention is not limited to
the embodiments described herein and various modifications to the disclosed embodiments
will be apparent to those skilled in the art.
[0031] Modular construction is typically a form of construction in which building components,
which may be alternatively referred to as modules, are manufactured off-site before
being assembled on-site. Social, political, economic, environmental and financial
factors mean that modular construction is becoming more common as there is need to
quickly and consistently construct good quality buildings, whilst minimising waste
and pollution.
[0032] All buildings experience axial shortening of their vertical elements over time. Differential
axial shortening may alternatively be referred to as differential shortening or shortening.
It is appreciated that whilst columns are specifically discussed hereafter, that the
methods described may be applicable to any suitable vertical element of a module in
a modular building.
[0033] The axial shortening of a column can be described by:

[0034] Columns in a modular building can shorten by different amounts. This leads to differential
axial shortening, which can be described by:

[0035] Various factors influence differential axial shortening; as such, there are numerous
ways that differential axial shortening may be corrected or compensated for in a building.
[0036] In conventional concrete frame construction, the effects of differential axial shortening
may be corrected during construction as each storey of the building is constructed
and levelled sequentially. Surveys are performed at every column position in every
storey to identify differential shortening, which is then corrected for at higher
storeys as construction progresses. Such surveys are time-consuming and prone to human
error.
[0037] In contrast, the objective of modular construction is to minimise the amount of work
that is to be completed on site. In order to minimise the effects of shortening in
a modular building, vertical elements in a modular building therefore may be manufactured
to nominally the same length. As some tolerances in the lengths of these elements
may remain, there is still a need to survey and check the level of storeys and vertical
elements at approximately every five storeys.
[0038] Differential axial shortening in conventional concrete frame building can occur as
additional storeys are added. This may cause lower storeys to become out-of-level.
This can be corrected for by the application of screed. Any shortening occurring after
the application of screed is corrected for by the fitting of finishes and elements
such as internal walls to correspond to the deflected shape of the building. Such
finishes are only used to correct for shortening that occurs at a late stage of construction.
[0039] In contrast, in modular construction, finishes are applied early in the modular construction
process, so cannot be used in the same corrective manner as conventional construction.
Further, the differential shortening as a result of stacking can cause module finishes
to be damaged, which results in unsightly finishes.
[0040] Foundation settlement is also problematic for modular construction. Foundation settlement
occurs under load and over time. In conventional construction, differential vertical
movement as a result of foundation settlement can be corrected as construction progresses
as such construction is typically quite a lengthy process. In contrast, foundation
settlement is problematic for modular construction due to the typical sequence it
follows. It is usual to build the core or fixed elements of the building prior to
assembly of the modules. The core may be concrete such that it is subject to shortening
as a result of shrinkage, creep and self-weight. The majority of shortening that is
experienced by the core is prior to installation of the modules. As the modules are
stacked, the modules experience shortening which results in a differential vertical
movement between the core and the module.
[0041] Similar issues may arise when a modular building is instead constructed atop a transfer
slab. Modules may not align with vertical elements beneath the transfer slab, thereby
experiencing flexural deflections of slab, resulting in differential vertical deflections
between adjacent columns in the module. As the modules are stacked, there is a corresponding
increase in the differential vertical deflections as the load entering the columns
from above increases. This effect is particularly pronounced if the transfer slab
is constructed from concrete as it will also undergo creep.
[0042] Due to the numerous contributory factors and associated problems with differential
axial shortening and differential vertical movements, it is desirable to find means
to minimise differential axial shortening in modular buildings. One such method relates
to the maintaining the Force-Area Ratio within given storeys of a modular building.
[0043] With reference to equation (1), the height of a given column and the elastic modulus
are generally constant. As such, it follows that:

[0044] Columns may be comprised of stacked column elements. Each column element may occupy
a given storey, alternatively referred to as levels or floors. As such, a column may
traverse multiple storeys of a building. Each storey may include a plurality of column
elements from different columns.
[0045] Differential axial shortening can cause the column elements and subsequently, the
storeys they occupy, to become out-of-level as the column elements of different columns
are compressed along their axes at different rates. If the Force-Area Ratio (FAR)
is kept constant for every column element in the building, then each column shortens
by the same amount. As a result, all of the storeys in the building remain level as
all of the columns move vertically downwards by the same margin.
[0046] In practice, keeping the FAR constant is challenging due to the complex and often
interdependent relationships between various factors. Firstly, the axial force experienced
by a column varies with the height of the building. The axial force in a column is
the sum of all of the individual forces entering the column from above. By way of
example, a column element occupying a lower storey will experience a greater axial
force than a column element occupying an upper storey. As a result, the lower column
element requires a higher cross-sectional area than the upper column, thereby changing
the FAR.
[0047] Balancing FAR for all of the column elements within a given storey is further complicated
as the axial force experienced by a column element varies based on its position within
the storey. For example, a column element of a fully internal column may experience
twice the load of a perimeter mid-side column element in the same storey. The perimeter
mid-side column element may experience twice the load of a corner column element in
the same storey. Further, perimeter column elements may be subject to additional loads
due to the need to support external features such as cladding and balconies.
[0048] Further additional superimposed dead and live loads are problematic for maintaining
the constancy of FAR within storeys as they can be unpredictable. Modular buildings
tend to be more sensitive to variations in live loads than concrete or steel-framed
buildings. Modular buildings can typically tolerate a lower dead load to live load
ratio than so-called conventional buildings. As such, the level of the floorplates
forming at least part of the floors of storeys of modular buildings tends to depart
from level more than a counterpart concrete framed building. It is therefore desirable
for the initial level of the floorplate in a modular building to be better than that
of a concrete framed building.
[0049] FAR may further be affected by alternative load paths. In modular construction, an
alternative load path may see the transfer of the load into upper beams, through wall
studs, into lower beams and back into the column. As such, the construction and plan
of the building and the amount of axial force on a column element has a large effect
on the proportion of the load that alternative load paths can tolerate.
[0050] It would be desirable to provide an improved method for managing vertical movement
in modular construction, such that a survey is not required at every storey during
construction of the modular building. As the vertical displacement experienced by
a column element is proportional to its FAR, maintaining the constancy of the FARs
of column elements within the same storey provides a means of managing vertical movement.
[0051] FIG. 1 of the accompanying drawings shows an isometric cut-away of an exemplary building.
The diagram shows the top ten storeys of the exemplary building. Each storey is labelled
sequentially, starting with the top storey denoted as 'TOP', the penultimate storey
as (-1) etc. The building extends to a reference storey, denoted as (-9). In other
examples, it is appreciated that any storey other than the top storey could be the
reference storey. It is appreciated that the building could be constructed of any
suitable number of storeys and be of any suitable height.
[0052] In FIG. 1, three columns are visible, a corner column (1), a mid-side column (2),
and a fully internal column (3). The columns traverse all ten of the storeys shown.
Whilst in the depiction shown the columns only traverse the upper ten storeys, it
is appreciated that in other examples the columns may traverse the whole length of
the building, or any other number of storeys of the building.
[0053] The columns shown are formed by the stacking of column elements on top of each other.
Each module has an uppermost surface, alternatively referred to as a ceiling, a lowermost
surface, alternatively referred to as a floor, and lateral surfaces, alternatively
referred to as walls. In this example, each individual column element occupies a single
given storey.
[0054] In FIG. 1, ten column elements are stacked to respectively form each of the three
columns (1, 2, 3). Three column elements from each of the different columns (1, 2,
3) occupy each given storey. By way of example, storey -1 is occupied by the column
elements of each of the corner (1), mid-side (2) and internal (3) columns.
[0055] The individual axial forces experienced by each column element are shown at the corresponding
location they are experienced on building 100. The individual axial forces may describe
the loads added from the individual module floors and ceilings.
[0056] FIG. 2 is a table corresponding to the exemplary building in FIG. 1. The table is
split into three sections, each indicating respective columns (1), (2) and (3). Each
row in the table corresponds to each storey of the building in FIG. 1.
[0057] Each of the sections of the table are split into four columns. The first column describes
the cumulative axial force experienced by a given column element within a storey.
The cumulative axial force is calculated by sequentially summing the individual axial
forces experienced by the column element from the top storey down to storey (-9).
[0058] The second column describes the cross-sectional area of the given column element.
[0059] The third column describes the individual Force-Area Ratio of the given column element.
The individual FAR is calculated using the cumulative axial force and the cross-sectional
area of the column.
[0060] The fourth column describes the cumulative FAR experienced by the given column element.
The cumulative FAR is calculated by sequentially summing the individual FARs from
the lowest storey (-9) to the top storey (TOP).
[0061] For ease of discussion, the maximum permitted value of FAR in the following examples
is 100, wherein the limit is related to the capacity of the column.
[0062] In FIG. 2, the cross-sectional areas of the column elements of the building in FIG.
1 have been adjusted in order to yield the maximum individual FAR for each given column
element. FIG. 2 shows the optimal design for maintaining FAR within storeys, as the
achieving the maximum individual FAR at each column element within a given storey
results in the cumulative FAR being maintained across the storey. As the vertical
displacement of each column element is proportional to its individual FAR, if the
cumulative FAR summed up the building is the same for all columns across each storey
and has this condition at every storey, then each storey will maintain level assuming
that the base of each column element in a given storey lies in the same horizontal
plane.
[0063] Whilst FIG. 2 highlights the optimal design for maintaining FAR, in practice, it
is unrealistic, impractical and expensive. In FIG. 2, by way of example, a total of
twenty different cross-sectional areas are required in order to maintain the FARs
within given storeys. In practice, the number of column sizes may be significantly
higher. As such, it is therefore disadvantageous to use such a design in order to
manage vertical displacement.
[0064] FIG. 3 is a table showing the effects of using a reduced number of column elements
of different sizes on the cumulative Force-Area Ratios within a given storey of the
building of FIG. 1. The arrangement of the table in FIG. 3 is the same as that of
FIG. 2. In this example, as in practice, there is a limit on the number of different
sizes of column element that are available. In this example, there are eight different
cross-sectional areas of column element available, in contrast to the twenty available
in the optimally designed building of FIG. 2.
[0065] Referring more specifically to the cross-sectional area columns in FIG. 3, it can
be seen that the smallest cross-sectional area available is 5, the largest being 40,
increasing in increments of 5. The smallest-sized cross-sectional area that achieves
a FAR of ≤ 100 has been selected for each given column element, as can be seen in
the individual FAR columns of each section.
[0066] Comparing columns 1, 2 and 3 of FIG. 3 shows that the cumulative FARs for a given
storey vary. By way of example, consider the top storey where the cumulative FAR for
the corner column (1) is 700, for the mid-side column (2) is 803 and for the internal
column (3) is 890. This yields a difference of 190 for the cumulative FARs for the
top storey.
[0067] Consider that a difference of 100 for cumulative FARs typically represents a 3mm
shortening of a fully loaded steel column. A difference of 190 as depicted in the
top storey of the building in FIG. 3 may result in a difference in shortening of columns
1 and 3 by approximately 5.7mm. Such a difference in shortening may be the entire
deflection allowance of the module, such there is no margin allowing for additional
deflection, resulting in modules that would deform to such an extent that finishes
would crack, and remedial work would be required. It would therefore be beneficial
to introduce improved and alternative means for maintaining FAR within a given storey.
[0068] FIG. 4 is a table showing matching individual Force-Area Ratios wherein the column
elements of the building of FIG. 1 have been adjusted to obtain matching individual
FARs across a given storey. The arrangement of the table in FIG. 4 is the same as
that of FIGs. 2 and 3. The cross-sectional areas of the column elements of the mid-side
column (2) are adjusted to give individual FARs that are equal to the individual FARs
of the corresponding column element in the corner column (1). The cross-sectional
areas of the column elements of internal column (3) are also adjusted to match the
individual FARs of the corresponding column elements of the corner column (1). By
way of example, the individual FAR of the corner column element in the top storey
is 20. The individual FARs of mid-side and internal column elements are also 20, as
the cross-sectional areas of the mid-side and internal columns have been adjusted
in order to achieve this correspondence across the top storey. This can be seen in
each of the remaining storeys in FIG. 4.
[0069] It is noted that for both of the buildings described by FIGs. 3 and 4, a limited
number of cross-sectional areas are available. In FIG. 3, cross-sectional areas of
column elements are selected to achieve an individual FAR as close to the maximum
as possible. In contrast, in FIG. 4, the cross-sectional areas are selected from an
even more limited pallet of cross-sectional areas, but the selection ensures that
the sum of the individual FARs up the columns is similar across storeys. This achieves
a much more consistent range of cumulative FARs across storeys. The effects of adjusting
cross-sectional area of column element in terms of volume of material used will be
discussed in greater detail later with respect to FIG. 7.
[0070] FIG. 5A illustrates the isometric cut-away of the exemplary building of FIG. 1 with
the addition of shims on given column elements and provides an expanded view of the
addition of a shim on a given column element. A shim may be of any suitable material
or shape to effectively adjust the FAR without the need to adjust the cross-sectional
areas of the columns themselves. A shim is typically applied to the underside of a
module. As such, the shim may additionally be in contact with the uppermost surface
of the stacked lower adjacent module. Alternatively, a shim may be in contact with
a tie-plate, which will be discussed in greater detail later.
[0071] Whilst the building in FIG. 5A is the same building as shown in FIG. 1 and is arranged
in the same manner, shims have been added to given column elements. FIG. 5A provides
a simplified expanded view 500 of the addition of a shim 502 to column element 504a
occupying storey -1 for column (2), where the shim is sandwiched between the upper
column element 504a at storey -1 and the lower column element 504b occupying storey
-2.
[0072] FIG. 5B is table showing the effects on individual and cumulative FARs as a result
of adding shims to given column elements as in FIG. 5A. The arrangement of the table
in FIG. 5B is the same as that of FIGs. 2, 3 and 4 with the exception of the individual
FAR columns. The boxed column elements are the column elements that have been fitted
with a shim. As the shim is intended to maintain level in a building, the shim reduces
the individual FAR. As such, in the boxed columns in the individual FAR column of
FIG. 5B, the individual FAR without a shim is shown and the effect of the shim reduction
is subtracted to obtain the shimmed individual FAR. The cumulative axial forces, cross-sectional
areas and individual FARs without the shims are the same as those depicted in FIG.
3, such that FIG. 5B depicts a shimmed version of the building of FIG. 3.
[0073] Adding a shim will reduce the effective axial shortening of a column element at a
given level as individual FAR is proportional to axial displacement. The adjustment
to FAR value used in figure 5B is related to shim thickness as follows:

and

[0074] Where a shim is used, it is to give the same effect as column shortening (or lengthening).
Equation (5) is re-arranged to give the FAR adjustment resulting from a given shim
thickness:

[0075] The FAR adjustment is subtracted from the normally calculated FAR for any given column
element whenever a shim is deployed to that column element.
[0076] By way of example, assume that an individual FAR of 100 represents a 3mm displacement.
It follows that a cumulative FAR of 1000 represents an axial displacement of 30mm.
The axial displacement of the top of an upper column element relative to the top of
a vertically adjacent lower column element is proportional to the individual FAR of
the upper column element. The addition of a shim between the upper and lower column
elements in the stack reduces that axial displacement of the top of the upper column
relative to the top of the lower column element. As axial displacement is proportional
to FAR, the reduction in the relative axial displacement as a result of adding the
shim is equivalent to reducing the FAR.
[0077] A 1mm shim may reduce the individual FAR of a column element by 33. Specifically,
and by way of example, the individual FAR of the top column element of the mid-side
column 2 in FIG. 5B is 40 without the addition of a shim. With the addition of a 1mm
shim the individual FAR is reduced by 33 to 7.
[0078] Additional 1mm shims have been added to the -1 and -6 column elements of the mid-side
column. This has an impact on the cumulative FARs experienced within a given storey
as it reduces the individual FARs of each of these column elements. This effect can
be seen with reference to FIGs. 3 and 5B, in which FIG. 5B is the shimmed version
of FIG. 3. By way of example, the cumulative FAR of the top storey column element
of the mid-side column in FIG. 3 is 803. In the shimmed version of FIG. 5B, this cumulative
FAR has been reduced to 704
[0079] Reading the cumulative FARs across storeys in FIG. 5B, it is shown that the cumulative
FARs can sit within a range of 19. This maximum range can be seen in storey -2. It
is therefore possible to keep the adjustment of the cumulative FAR across a storey
within a range that is approximately half of the thickness of a shim by varying the
location of the shims. As an example, to maintain storey level within 1mm, a shim
of 2mm could be used.
[0080] The benefits of adjusting the individual FARs of given column elements can be explained
by averaging the cumulative FARs of all the column elements within a given storey
and determining the percentage difference for each of the cumulative FARs for each
of the column elements within a given storey.
[0081] FIG. 6A is a table illustrating the average cumulative FARs across storeys for the
exemplary un-shimmed building as described in FIG. 3. The absolute difference between
the average cumulative FAR for a given storey and the cumulative FARs for each of
the column elements within a given storey is shown for each of columns 1, 2 and 3.
[0082] FIG. 6B is a table illustrating the absolute difference between the average cumulative
FAR for a given storey and the cumulative FARs for each of the column elements within
a given storey for the exemplary shimmed building as described in FIG. 5B. FIG. 6B
is arranged in the same manner as FIG. 6A.
[0083] The objective of equalising cumulative FARs at each storey is to maintain level across
each storey such that module finishes are not damaged when a module is placed. The
damage limit for a given module may be defined in terms of the differential level
between adjacent columns in a given module. The damage limit also needs to allow for
module deformations arising from other tolerances and adjustments made during installation.
It is reasonable for the FAR contribution to permitted deformation to use up 25% of
the total available. As an example, if the maximum differential level between adjacent
columns is 6mm, then the FAR contribution should be 1.5mm. Putting this value into
equation (6) gives a FAR value, in this case the tolerance range within which the
cumulative FARs at each storey should lie.
[0084] By way of example, the cumulative FARs of all of the column elements in the top storey
in the non-shimmed building of FIG. 3 and as depicted in FIG. 6A yield an average
cumulative FAR of 798. The cumulative FAR of the top storey of column 1 is within
a range of 98 of the average cumulative FAR across the storey. The cumulative FAR
of the top storey of column 2 is within a range of -5 of the average cumulative FAR
across the storey. The cumulative FAR of the top storey of column 3 is within a range
of -92 of the average cumulative FAR across the storey.
[0085] In contrast, and with reference to FIG. 6B, averaging the cumulative FARs of all
of the column elements in the top storey in the shimmed building as depicted in FIG.
5A gives an average cumulative FAR of 699.The cumulative FAR of the top storey of
column 1 is within a range of -1 of the average cumulative FAR across the storey.
The cumulative FAR of the top storey of column 2 is within a range of -5 of the average
cumulative FAR across the storey. The cumulative FAR of the top storey of column 3
is within a range of 7 of the average cumulative FAR across the storey.
[0086] Comparing the absolute differences of the adjusted building to the non-adjusted building
shows that the cumulative FAR within a given storey can be maintained to within a
much tighter tolerance than in the non-adjusted building.
[0087] The use of shims is also beneficial in terms of efficiency. The sum of the cross-sectional
areas of the column elements in a column is directly proportional to the amount of
material that is used to form the column. The amount of material used to form a column
provides a measure of efficiency.
[0088] FIG. 7 is table showing the sum total of all of the cross-sectional areas of each
of the buildings as described by the tables depicted in FIGs. 2, 3, 4 and 5B. The
first column shows the building to which it relates. The sum totalled cross-sectional
areas for each of the columns is shown. The sum total of all of the columns in a given
building is shown in the final column.
[0089] For the shimmed building of FIG. 5B, the sum total of the cross-sectional areas of
all of the column elements is 445. This is the same as the limited column size building
depicted in FIG. 3. The sum total of all of the cross-sectional areas of all of the
column elements of FIG. 4 is 525. In contrast, in the optimal building design as in
FIG. 2, the sum total is 385.
[0090] There is an 18% reduction in material required to construct the shimmed building
in FIG. 5B in comparison to the equivalently level non-shimmed building of FIG 4.
This shows that with the addition of a limited number of shims, it is possible to
balance cumulative FARs within a given storey to within a tight tolerance. This assists
in maintaining the level of a given storey by minimising the amount differential shortening
that each of the column elements within a given storey undergoes, such that they shorten
at substantially the same rate.
[0091] It is noted that whilst in terms of amount of material used, the building in FIG.
2 may be considered to be the most efficient, in practice it is unrealistic and impractical
due to the number of different cross-sectional areas required. It is therefore beneficial
to combine shims with column elements with varying cross-sectional areas in order
to manage variable vertical displacement.
[0092] Imbalances in FAR within a given storey can result in damage to the modules including
visible cracks and hairline fractures due to vertical, flexural and racking deflections.
Based on the preceding examples, there is a need to provide a method of maintaining
cumulative FARs within given storeys of buildings in an efficient and practical manner
in order to limit damage to the modules.
[0093] FIG. 8 provides a flow-chart depicting an exemplary method 800 for limiting damage
within 3D modules of a building. The method comprises determining an individual axial
force for each of a plurality of column elements that are stacked to form a column
(block 810). The column element may be a module of the modular building such that
it occupies a given storey in the modular building. Each of the plurality of column
elements has a defined cross-sectional area and links a lower storey to an adjacent
upper storey of a modular building such that the column traverses a plurality of storeys
of the modular building. The column may traverse the entire height of the building
from the ground storey to the top floor. Alternatively, it is appreciated that the
column may span from a first reference storey to the top storey, where the reference
storey may be any storey below the top storey including the ground storey.
[0094] Column elements may be stacked to form a plurality of columns such that each storey
includes a plurality of column elements from different columns.
[0095] The individual axial force of a column element in any given storey may be determined
by calculating the sum of the loads entering the column element from all of the storeys
above.
[0096] A cumulative axial force for each of the plurality of column elements may be determined
(block 820). Each cumulative axial force of each of the plurality of column elements
may comprise the sum total of each of the determined individual axial forces summed
successively from the column element at the top of the column to a column element
at a reference storey.
[0097] An individual Force-Area Ratio for each of the plurality of column elements is determined
(block 830). The individual FAR is based on the determined cumulative axial force
for each of the plurality of column elements divided by the cross-sectional area of
each of the plurality of column elements.
[0098] A cumulative FAR for each of the plurality of column elements is determined (block
840). Each of the cumulative FARs for each of the plurality of column elements respectively
comprises the sum total of each of the determined individual FARs for each of the
plurality of column elements summed successively from the column element at the base
of the column to the column element at the top of the column.
[0099] An average cumulative FAR for each storey of the modular building is determined (block
850). The average cumulative FAR is based on the determined cumulative FARs of all
of the plurality of column elements that occupy a given storey. The determined individual
FAR of at least one column element is adjusted (block 860). The determined individual
FAR is adjusted to adjust the cumulative FAR of the at least one column element to
within a specified target range of the average cumulative FAR of the storey that the
at least one column element occupies. The objective of equalising cumulative FARs
up the column at each storey is to maintain level across each storey such that module
finishes are not damaged when a module is placed. The damage limit for a given module
may be defined in terms of the differential level between adjacent columns on that
module. This limit also needs to allow for module deformations arising from other
tolerances and adjustments made during installation. It is reasonable for the FAR
contribution to permitted deformation to use up 25% of the total available.
[0100] The determined individual FAR may be adjusted by varying the cross-sectional area
of the column element which may be achieved by adjusting the length of a column element.
Alternatively, or additionally, the individual FAR may be adjusted with the addition
of a shim. Alternatively, or additionally, the individual FAR may be adjusted by the
addition of a tie-plate, positioned on the underside of a column element. The tie-plate
may be of any suitable shape provided that it is larger or equal in size to the base
of the column element. The tie-plate may be of any suitable material provided that
it can withstand the loads entering it from above.
[0101] The adjustment of the individual FAR allows the cumulative FAR to be adjusted in
order to maintain the cumulative FARs across column elements within a given storey
to within an acceptable range, thereby limiting damage experienced by the 3D modules.
[0102] The exemplary method 800 provides a practical and realistic method for installation
of a modular building. The method 800 minimises the amount of material required whilst
being realistic and affordable in practice. The method 800 provides a means for balancing
FAR within given storeys within a specified target range. This more efficiently and
easily maintains level within storey.
[0103] The method 800 may also limit the need to perform level surveys at every storey.
In the examples in which the cumulative FARs are adjusted through the addition of
shims, the shims adjust cumulative FARs and do not accommodate for poor tolerances
in column length. It is appreciated that other shims, referred to as tolerance shims,
may be used in addition to the FAR shims. The tolerance shims may be used to correct
for poor tolerances in the length of column elements. As the method 800 maintains
the cumulative FAR across all columns within a given storey, it is appreciated that
any variations in level in the storey may be attributed to poor tolerances. As modular
construction tends to be highly accurate and consistent, the repeatability in length
accuracy of column elements across a given storey is expected to be ≤ 0.5mm. Survey
equipment currently can only reliably detect accuracy within ±2mm such that surveys
for tolerance shims are only required at approximately every fifth storey. It is therefore
noted that method 800 as described above reduces costs and minimises the risk of introducing
human errors as fewer level surveys are required.
[0104] Whilst the method in FIG. 8 is based on the exemplary building of FIG. 1, it is appreciated
that the methods and techniques are applicable to other modular building constructions
with varying heights, varying storey heights, varying numbers of storeys and varying
axial force accumulations down the columns. The methods are applicable provided that
dead loads can be accurately estimated in advance, which is a typical feature of modular
construction. The estimations provide a representation of the dead loads post-construction.
The estimation of the dead loads in advance means that the methods as described above
are applicable as dead loads post-construction are predictable and non-changing.
[0105] Referring back to FIGs. 6A and 6B, it is shown that the cumulative FARs of column
elements within a given storey can be adjusted to within a specified target range
of the average cumulative FAR of the storey. Whilst this is beneficial to minimise
the differential axial shortening, the FARs within a given storey are not perfectly
equal. By way of example in FIG. 5B, the cumulative FARs of the column elements in
the top storey are 700, 904 and 692 respectively. The range of these values is minimised
by the method 800 described above but in practice, it is not possible to perfectly
balance these ratios. As such, the adjusted building may experience some differential
column shortening, which will hereinafter be referred to as residual column shortening.
It is desirable to redistribute the forces arising from the residual column shortening.
[0106] FIG. 9A shows a simplified example of a tie-plate in use with a cluster of column
elements, arranged to redistribute the forces arising from residual column shortening.
The arrangement 900 in FIG. 9A is comprised of a lower cluster of co-located column
elements 902, an upper cluster of co-located column elements 904 and a tie-plate 906
sandwiched between the lower cluster 902 and upper cluster 904. The residual column
shortening may arise as a result of variations in the length of at least one column
element in the upper cluster 904 and lower cluster 902 of column elements. Alternatively,
or additionally, the residual column shortening may arise due to the variation in
the load entering at least one of the column elements in the upper 904 and lower cluster
902 of column elements.
[0107] The lower cluster 902 of column elements is comprised of a plurality of column elements
that occupy a first storey of a modular building. The upper cluster 904 of column
elements is comprised of a plurality of column elements that occupy a second storey
of the modular building that is immediately above the first storey. In other words,
the upper cluster 904 is stacked on top of the lower cluster 902 such that each of
the column elements in the lower 902 and upper 904 clusters are substantially vertically
aligned; for example, lower column element 902a is directly below upper column element
904a.
[0108] The column elements within the lower cluster 902 are co-located. The co-location
describes column elements that are immediately adjacent to each other. The distance
between the column elements may be up to 10cm. The column elements may be spaced apart
at substantially regular intervals.
[0109] Whilst four column elements in each cluster are depicted in FIG. 9A, it is appreciated
that each cluster of column elements may comprise any number of column elements, provided
there are more than two column elements in each cluster. The cluster of column elements
may be positioned in any suitable arrangement according to the description above.
[0110] The tie-plate 906 is shown sandwiched between the lower cluster 902 and the upper
cluster 904 of columns. The tie-plate is arranged such that, in use, it is in contact
with all of the column elements in the respective lower cluster 902 and the upper
cluster 904 of columns. The tie-plate 906 has a predetermined length (L). The tie-plate
906 may comprise a sheet of any suitable material such as a fibre composite, steel
or any other suitable metal.
[0111] FIG. 9B shows a frontal view of the tie-plate arrangement of FIG. 9A. The tie-plate
is configured to offset axial displacements in the upper cluster 904 of columns that
arises as a result of the residual column shortening. The tie-plate may be manufactured
to be of a specified thickness (t) to offset the deflections.
[0112] The balancing force available at each tie-plate may be described by:

[0113] The yield stress, length (L) and thickness of equation (6) are those of the tie-plate;
the length and thickness are depicted in FIG. 9B. The column spacing (S) is depicted
in FIG. 9B and describes the relative distance between each of the column elements
in a given column cluster (e.g. the distance between column elements 902a and 902b).
[0114] In FIG. 9B, the result of the residual column shortening can be seen. Column 908
is formed from column elements 902a and 904a. Neighbouring column 910 is formed from
column elements 802b and 804b Column 908 has shortened more than column 910. The tie-plate
is sandwiched between the column elements stacked to form columns 908 and 910 to offset
the differences as a result of this residual column shortening, provided that the
balancing force of the tie-plate exceeds that of the load of the cluster of the column
elements. As this gives little leeway for additional deflections, in practice, a balancing
force that exceeds the load of the cluster of column elements by at least 10% is adequate.
In preferred examples, the balancing force exceeds the loads of the cluster of column
elements by 20%.
[0115] In modular construction, column shortening under load can result in additional challenges.
Typically, in modular construction, core elements, alternatively known as fixed structures,
which may include walls, stairwells and lift shafts, are constructed first. The modules
may be assembled in the correct position relative to these fixed structures.
[0116] As described above, column elements are stacked to form columns. As the column elements
are stacked, the load increases such that the column elements undergo shortening under
load. This may cause the column elements to move downwards relative to the core element.
[0117] Lateral forces in the plane of the module roof of each of the column elements need
to be transferred to the core element. Transferring these forces using a rigid connection
is problematic due to the differential vertical movement experienced by the column
elements and the core element. Use of such a connection would be likely cause damage
to the building as either or both of the column elements moves downwards relative
to the wall.
[0118] Mechanical systems such as a bracket with slotted holes or a dowel running in a hole
may be employed. However, such systems increase the amount of work required to be
undertaken on site as, during installation, they must be carefully aligned. This also
increases the risk of human error. Further, such systems may be prone to generating
noise as they slide that may be transmitted into the modular building. It is therefore
desirable to provide an alternative method for transferring horizontal loads from
a column element to a core element.
[0119] An example of a compliant element in use with a core element and a cluster of column
elements is shown in FIG. 10. A cluster 1002 of column elements 1002a, 1002b adjacent
to a shear wall 1004 is illustrated.
[0120] In FIG. 10, only a single storey of the modular building is shown. Whilst it is not
visible in FIG. 10 it is appreciated that column elements 1002a, 1002b may form a
part of a stack of different columns. It is appreciated that column elements 1002a,
1002b may be stacked atop lower column elements. Further additional column elements
may be stacked above the depicted column elements 1002a, 1002b. Further, whilst only
two column elements and one core element are shown, it is appreciated that any suitable
number of column elements and core elements can be used to construct a modular building
providing it is structurally sound.
[0121] If additional column elements are stacked atop either of column elements 1002a, 1002b,
they may move downwards relative to the shear wall 1004. As described above, this
differential vertical movement makes it challenging to easily and efficiently transfer
lateral forces from the column elements into the core wall.
[0122] FIG. 10 shows compliant elements 1006a and 1006b in use with respective column elements
1002a and 1002b and the core wall 1004. Whilst the compliant elements 1006a and 1006b
are depicted as round bars, it is appreciated that the compliant elements may alternatively
comprise other sectional profiles or plates. The compliant elements 1006a, 1006b are
substantially perpendicular to the plane of differential vertical movement.
[0123] Tie-plate 1008 is positioned atop the cluster 1002 of column elements. Referring
specifically to the arrangement of compliant element 1006a for ease of discussion,
plate 1010a is affixed to the shear wall 1004. One end of the compliant element 1006a
is affixed to the plate 1010a. A substantially opposite end of the compliant element
1006a is attached to the tie-plate 1008. It is noted that compliant element 1006b,
column element 1002b and wall plate 1010b are arranged in the same manner with the
compliant element 1006b attached to the tie-plate 1008 at a location corresponding
to column element 1002b.
[0124] It is appreciated that whilst in the example in FIG. 10 the compliant elements 1006a
and 1006b are respectively attached to the wall plates 1010a and 1010b and the tie-plate
1008, the compliant elements 1006a, 1006b may be directly affixed to the column element
1002a and 1002b respectively instead of to the tie-plate 1008. The compliant elements
1006a and 1006b may be directly affixed to the shear wall 1004 instead of to the respective
wall plates 1010a and 910b. It is appreciated that any suitable combination of these
affixing arrangements may be adopted.
[0125] Compliant element 1006a is configured to transfer lateral forces applied to the column
elements along its length via axial forces. The compliant element 1006a is attached
to the wall plate 1010a which is affixed to the core element 1004. The compliant element
1006a therefore provides a direct load path out of the column element 1002a into the
core element 1004. The proportions of the compliant element 1006a are selected such
that it does not buckle as a result of the axial forces arising in the compliant element
1006a.
[0126] In an example, column elements may be stacked atop column element 1002a. As described
above, this may result in column element 1002a moving downwards relative to the shear
wall 1004. This differential vertical movement arises due to column shortening under
load as the column elements are stacked as the load entering column element 1002a
increases. It is therefore a one-time event such that no further differential vertical
movement between the core element 1004 and the column element 1002a is expected after
the column elements have been stacked and the building has been occupied as no significant
further change in load is expected.
[0127] The compliant element 1006a is configured to deform plastically to offset the one-time
variable vertical displacement between the core element 1004 and column element 1002a.
The variable vertical displacement experienced may typically be up to 30mm. Due to
the relative magnitude of this displacement, the compliant element 1006a is configured
to yield in vertical bending. The deformation of the compliant element 1006a operates
within its plastic range as it is one-time yielding, corresponding to the one-off
differential vertical displacement event as a result of stacking column elements.
[0128] The compliant element is configured to deform within its elastic range to offset
variable vertical displacements that may occur after the column elements have been
stacked. These displacements tend to be much smaller in magnitude than the one-time
differential vertical displacements under load and may be up to 5mm. These smaller
displacements may be as the result of lateral forces applied to the modular building
such as wind. The elastic deformations of the compliant elements are sufficiently
small in magnitude so as not to cause premature failure of the connection under the
effects of fatigue. As described above, the compliant elements 1006a,1006b can transfer
the lateral forces experienced by the building along its length via axial forces and
into the shear wall 1004.
[0129] It is appreciated that the compliant element may be of any suitable size, shape and
material provided that its plastic and elastic ranges can withstand the variable vertical
displacements that occur during construction and thereafter such that the compliant
element is not compromised. The compliant element therefore is not prone to failure
or generating noise.
[0130] Vertical oriented elements other than column elements may also be susceptible to
damage as they undergo elastic shortening. As previously described, each module has
an uppermost surface, alternatively referred to as a ceiling, a lowermost surface,
alternatively referred to as a floor, and vertical surfaces, which may be referred
to as walls . Walls typically have internal vertical elements which are attached to
floor structure at the bottom and ceiling structure at the top. In some examples of
modular construction, the ceiling structure comprises horizontal beams which are supported
by the column elements. A rigid connection between the ceiling and the frame means
that as the column elements undergo elastic shortening, the ceiling moves downwards
into the tops of the walls of the module. This increases the risk of damaging both
or either of the ceiling and walls and other vertical elements.
[0131] FIG. 11A illustrates a schematic section through a column element. A floor frame
1104 and ceiling frame 1106 are connected by a column 1102. The column element 1102
is substantially perpendicular to both the floor frame 1104 and the ceiling frame
1106. The column element 1102 provides additional support to ceiling frame 1106. It
is appreciated that the ceiling frame 1106 may be further supported by additional
walls that are not visible in FIG. 11A.
[0132] The underside of a ceiling board 1114 is in contact with the top of wall 1110 and
internal wall 1112. The upper surface of the ceiling board 1114 is in contact with
the headed stud 1116 and the ceiling rail 1118. The ceiling board 1114 lies substantially
in the horizontal plane. The ceiling board 1114 forms the visible ceiling of the module.
The arrangement of the ceiling rail 1118 and the ceiling board 1114 is discussed in
greater detail later with respect to FIG. 11B.
[0133] In some examples of modular construction, height tolerances may exist between the
floor frame 1104 and the ceiling frame 1106. The difference may result in an effective
change in the floor to ceiling dimensions.
[0134] A floor assembly 1108 is supported off the floor frame 1104. The upper surface of
the floor assembly 1108 may vary from nominal due to tolerance variation of components
used in the floor assembly 1108. This may increase the risk of the wall 1110 and the
internal wall 1112 being higher or lower than the nominal position of the wall tops.
The poor tolerance of the floor system as depicted by 1104 and 1108 increases the
risk of compromising the structure of the wall element via the accumulation of gaps
as it allows the distance between the tops of the wall 1110 and internal wall 1112
and the ceiling board 1114 to vary.
[0135] Any shortening of column element 1102 as a result of axial load can further or alternatively
vary the distance between the ceiling board 1114 and the wall 1110 and internal wall
1112. Differential deflections of the floor frame 1104 and of the ceiling frame 1106
may also result in a dimensional variation between the ceiling board 1114 and the
wall 1110 and the internal wall 1112.
[0136] In order to minimise damage or to prevent gaps forming between the wall 1110, and
or the internal wall 1112, and the ceiling board 1114, it is desirable for the ceiling
board 1114 of the column element to be able to move independently of the ceiling frame
1106.
[0137] FIG. 11B depicts an enlarged view of a schematic section through the ceiling arrangement
of FIG. 11A. As described earlier, the upper surface of ceiling board 1114 is attached
to the ceiling frame 1106. Although not visible in FIG. 11B, it is appreciated that
the underside of the ceiling board 1114 may be in contact with the tops of walls as
depicted in FIG. 11A.
[0138] A ceiling rail 1118 is affixed to the upper surface of the ceiling board 1114. A
headed stud 1116 traverses an opening in the ceiling rail 1118 and is attached to
the underside of the ceiling frame 1106. The diameter of the opening of the ceiling
rail 1118 exceeds that of the shaft of the stud 1116. Additionally, the diameter of
the opening of the ceiling rail 1118 is less than that of the head of the stud 1116.
[0139] The ceiling rail 1118 is configured to move independently of the ceiling frame 1106.
The ceiling rail 1118 may move vertically along the length of the shaft of the stud
1116 between the head of the stud 1116 and the ceiling frame 1106. This permits the
ceiling rail to move only within a distance range dictated by the length of the stud.
In a preferred example, the maximum permitted independent movement of the ceiling
rail 1118 is 12mm. The independent movement of the ceiling rail is able to accommodate
the effects of column axial shortening, structural flexure under in-service loads
and cumulative manufacturing tolerances. This is beneficial as it limits excessive
sagging of the ceiling board 1114 and limits the ceiling board 1114 either diverging
from or pushing into the tops of walls and/or wall boards.
[0140] The ceiling rail 1118 assembly may be able to accommodate up to 12mm of deflections,
with 7mm attributable to tolerances. As such, the ceiling rail 1118 is configured
to enable the ceiling board 1114 to deflect within a specified threshold. This allows
the ceiling board 1114 to remain in contact with the tops of walls and/or wall boards
that are different heights, provided the difference in height is within the threshold
deflection range of the ceiling board 1114. In a preferred example, the stiffness
of the ceiling rail 1118 is selected to enable the ceiling board 1114 to deflect by
10mm under self-weight when the ceiling board 1114 spans 2m. This relative stiffness
provides sufficient support to maintain the contact between the ceiling rail 1118
and the ceiling board 1114 whilst enabling the ceiling board 1114 to deflect within
an allowable range.
[0141] As described above, the ceiling rail 1118 is affixed to the ceiling board 1114. As
a result, the ceiling board 1114 can also move independently of the ceiling frame
1106 along the length of the stud 1116. The ceiling rail 1118 assembly may be able
to accommodate up to 12mm of deflections, with 7mm attributable to tolerances.
[0142] The independent movement minimises the risk of gaps forming between the tops of walls,
wall boards and the ceiling board 1114 due to factors including but not limited to
column shortening, tolerances, and differential frame flexures. Correspondingly, this
also reduces the risk of damage to the column element.
[0143] Any reference to 'an' item refers to one or more of those items. The term 'comprising'
is used herein to mean including the method blocks or elements identified, but that
such blocks or elements do not comprise an exclusive list and an apparatus may contain
additional blocks or elements and a method may contain additional operations or elements.
Furthermore, the blocks, elements and operations are themselves not impliedly closed.
[0144] The steps of the methods described herein may be carried out in any suitable order,
or simultaneously where appropriate. The arrows between boxes in the figures show
one example sequence of method steps but are not intended to exclude other sequences
or the performance of multiple steps in parallel. Additionally, individual blocks
may be deleted from any of the methods without departing from the spirit and scope
of the subject matter described herein. Aspects of any of the examples described above
may be combined with aspects of any of the other examples described to form further
examples without losing the effect sought. Where elements of the figures are shown
connected by arrows, it will be appreciated that these arrows show just one example
flow of communications (including data and control messages) between elements. The
flow between elements may be in either direction or in both directions.
[0145] Where the description has explicitly disclosed in isolation some individual features,
any apparent combination of two or more such features is considered also to be disclosed,
to the extent that such features or combinations are apparent and capable of being
carried out based on the present specification as a whole in the light of the common
general knowledge of a person skilled in the art, irrespective of whether such features
or combinations of features solve any problems disclosed herein. In view of the foregoing
description it will be evident to a person skilled in the art that various modifications
may be made within the scope of the invention.