TECHNICAL FIELD
[0001] The present invention relates to a construction system for building homes and the
like wherein the elements involved in the system exhibit a high degree of industrialization,
which allows obtaining benefits in terms of time frame, sustainability, safety, and
labor integration.
[0002] The invention also relates to a method of construction based on the system.
[0003] As a guideline, the system of the invention, previously industrialized elements involved
in the system entail a value of the order of 64.8% of the total budget of the construction,
with the subsequent cost reduction therein.
BACKGROUND OF THE INVENTION
[0004] As is known, when constructing buildings, the expected time frames are usually very
long, where delays due to unforeseen circumstances are relatively frequent, very negatively
affecting both building times and construction costs.
[0005] In order to avoid these problems, modular homes are known which, although drastically
reduce the building times as well as the costs associated therewith, are very specific
structures that are, accordingly, not very versatile.
DESCRIPTION OF THE INVENTION
[0006] The construction system that is recommended solves the aforementioned problems in
a completely satisfactory manner, based on a simple but effective solution.
[0007] To that end, and more specifically, the system of the invention involves a series
of industrialized elements which allow drastically reducing construction times, with
the consequent and beneficial repercussion that this entails.
[0008] More specifically, the elements involved in the construction system are the following:
- Prefabricated columns.
- Prestressed beams.
- Precast slabs.
- Prefabricated walls.
- Prefabricated façades.
- Roof parapets.
- PVC joinery.
- Glass panels.
- Plasterboards on profiles.
- Installations.
- Home electrical panel.
- Metal baseboard.
- Coping.
- Chimneys.
- Prefabricated bathrooms.
- Covering for wet areas.
- Vinyl flooring.
- Prefabricated balconies.
[0009] The prefabricated columns are obtained in reinforced concrete of variable cross section
connected to footing by means of an injected steel casing. The columns have a smooth
finish and are painted in the color of choice.
[0010] The prestressed beams constitute prefabricated T-shape type prestressed concrete
elements, with connections and support apparatus with columns included. Like the columns,
they have a smooth finish and are painted in the color of choice.
[0011] The precast slabs consist of 25+5 precast top slabs with lightened polystyrene filler
blocks, formed by a prefabricated reinforced concrete plate, top slab tensile reinforcements
and ties. They are characterized by quick placement and concreting.
[0012] In terms of prefabricated walls, they will be self-supporting, have a variable thickness
with B500S steel reinforcement and a smooth finish, and they will be painted in the
color of choice. This type of wall is placed both in garages as containment, as well
as in stairwells and communication centers.
[0013] In turn, the prefabricated façades will be made up of an outer bearing wall with
a 5 cm thick visible concrete finish, a continuous rigid XPS insulation in the intermediate
layer, and a 15 cm inner structure layer of concrete with inner plasterboard paneling
on profiles and rock wool.
[0014] The roof parapets consist of concrete walls prefabricated for parapets, whereby brick
placement is spared and a greater structural stability is obtained.
[0015] The PVC joinery is made as a 76 mm deep PVC window with 5 chambers.
[0016] The glass panels have a double glazing formed by a colorless glass panel having a
thickness according to the project and a second glass panel having a thickness according
to the project and the dehydrated air chamber has a variable thickness with double
perimeter sealing and aluminum separator profile.
[0017] In terms of the plasterboards, they allow obtaining a 15 mm thick inner paneling.
[0018] With respect to the installations, the prefabricated walls internally include the
installations of plumbing and raceway system.
[0019] The home electrical panels are partially assembled in factory with the entire switchgear
provided only for connecting the points. It is supplied in a ready-for-placement plasterboard
structure.
[0020] As mentioned above, another one of the prefabricated constructive elements is the
metal baseboard, which will be hung on the metal profile acting as a slate sheet finishing
profile in urbanization.
[0021] The use of metal copings with concealed mechanical fixing system has been envisaged
in urbanization and parapets. The system circumvents silicone seals by having waterproof
neoprene strips under the attachment, making the coping completely water-tight, avoiding
maintenance of any type.
[0022] In turn, the chimneys are completely assembled from factory with a concealed structure
for a quick and waste-free assembly. An inner metal fitting structure intended for
that purpose is made.
[0023] In terms of the bathrooms, they will also be prefabricated, with an enveloping system
of concealed metal structure and direct plasterboards with insulation to be left prepared
on site so as to not open until delivery, leaving the installation points to be connected.
[0024] The covering for wet areas consists of a composite system received with high moisture-resistant
glue for placement in kitchen and shower stall fronts. A cleaner, completely water-tight
finish that does not generate tiling waste is achieved. This covering can have the
desired design or drawing because a photograph is submitted and printed to the desired
size.
[0025] A system for setting up a compression layer by means of directly polishing the finish
to place the vinyl flooring on top has also been envisaged. This flooring is changed
slat by slat without having to lift long wythes. With this mixed system, the implementation
of mortar screed is spared, avoiding a large amount of waste.
[0026] Lastly, the involvement of prefabricated balconies is envisaged in the construction
system, said balconies having metal fittings completely finished in factory including
the outdoor wooden flooring with a water collection tray and connected by means of
mechanical anchoring to the metal structure of the top slab.
[0027] Based on this structure, the construction method starts with setting up different
on-site auxiliary installations and resources for the workers.
[0028] After the corresponding phase of moving the earth, the foundation and containment
are set up by means of using the prefabricated concrete walls described above, which
significantly reduces operating times.
[0029] Next, the underground sewage network is made by making the corresponding trenches
and making bases and beddings for assembling the pipes and accessories associated
therewith.
[0030] In terms of the below-ground structure, the prefabricated columns and beams described
above are set up, such that once they are placed and before supporting horizontal
elements thereon, a gravel paving process is performed to subsequently make the floor
slab.
[0031] Top slabs, on which the corresponding compression layer is applied, are obtained
in a quick and simple manner from the precast slabs described above.
[0032] In terms of making the stairs, this is done while climbing up the structure. It is
made up of a prefabricated concrete box in which the stairs are supported on brackets
by simply supporting them on top of one another.
[0033] As mentioned above, the façades are formed in a quick and simple manner by means
of mechanical anchoring systems based on the prefabricated façades envisaged in the
system, including therein the PVC joinery as well as the glass panels described above,
thereby obtaining a fully finished and water-tight façade.
[0034] After placing the walls, the top slabs will be placed and the compression layer made,
with the described operation being repeated until the desired height of the building
is obtained.
[0035] In a subsequent phase, the prefabricated bathrooms are installed, and inner partitioning
and installation connection are set out, all of which taking a much shorter operating
time as a result of the prefabricated nature of most of the elements involved in the
system.
[0036] Following the construction process set forth in the description, once reaching the
last top slab, the roof must be tackled as soon as possible so as to make the building
completely water-tight, with there being two different types of roofs to be obtained;
trafficable and non-trafficable roofs.
[0037] In parallel, and in the cases in which it is envisaged, the prefabricated chimneys
will be installed in this phase.
[0038] In parallel, vertical coverings will be applied, false ceilings obtained, and surfaces
painted.
[0039] Once this phase has ended, the wood joinery and metal fittings will be installed,
to lastly proceed with the laying out of flooring.
[0040] Therefore, and as mentioned above, the construction time frames, as well as the waste
generated during construction, are significantly reduced, increasing safety, sustainability,
and labor integration.
DESCRIPTION OF THE DRAWINGS
[0041] As a complement to the description that will be provided herein, and for the purpose
of helping to make the features of the invention more readily understandable, according
to a preferred practical exemplary embodiment thereof, said description is accompanied
by a set of drawings constituting an integral part thereof in which, by way of illustration
and not limitation, the following is represented:
Figure 1 shows a perspective view of one of the columns involved in a construction
system carried out according to the object of the present invention.
Figure 2 shows a perspective view of a prestressed beam involved in the construction
system of the invention.
Figure 3 shows a perspective view of a precast slab involved in the construction system
of the invention.
Figure 4 shows a perspective view of a prefabricated wall involved in the construction
system of the invention.
Figure 5 shows a perspective view of a prefabricated façade involved in the construction
system of the invention.
Figure 6 shows a perspective view of a roof parapet involved in the construction system
of the invention.
Figure 7 shows a perspective view of a detail of the PVC joinery involved in the construction
system of the invention.
Figure 8 shows a perspective view of the glass panels involved in the construction
system of the invention.
Figure 9 shows a detail of the plumbing and raceway system installations included
in factory inside the prefabricated walls.
Figure 10 shows a perspective view of the prefabricated home electrical panel involved
in the construction system of the invention.
Figure 11 shows a perspective view of a metal coping involved in the construction
system of the invention.
Figure 12 shows a perspective view of a prefabricated chimney involved in the construction
system of the invention.
Figure 13 shows a perspective view of a prefabricated bathroom involved in the construction
system of the invention.
Figure 14 shows a perspective view of a prefabricated balcony involved in the construction
system of the invention.
PREFERRED EMBODIMENT OF THE INVENTION
[0042] In view of the mentioned figures, it can be seen how the following elements are involved
in the construction system of the invention:
- Prefabricated columns (1).
- Prestressed beams (2).
- Precast slabs (3).
- Prefabricated walls (4).
- Prefabricated façades (5).
- Roof parapets (6).
- PVC joinery (7).
- Glass panels (8).
- Plasterboards.
- Installations.
- Home electrical panel (9).
- Metal baseboard.
- Coping (10).
- Chimneys (11).
- Prefabricated bathrooms (12).
- Covering for wet areas.
- Vinyl flooring.
- Prefabricated balconies (13).
[0043] The prefabricated columns (1) are obtained in reinforced concrete of variable cross
section connected to footing by means of an injected steel casing. The columns have
a smooth finish and are painted in the color of choice.
[0044] The prestressed beams (2) constitute prefabricated T-shape type prestressed concrete
elements, with connections and support apparatus with columns (2') included. Like
the columns, they have a smooth finish and are painted in the color of choice.
[0045] The precast slabs (3) consist of 25+5 precast top slabs with lightened polystyrene
filler blocks (3'), formed by a prefabricated reinforced concrete plate, top slab
tensile reinforcements, and ties. They are characterized by quick placement and concreting.
[0046] In terms of the prefabricated walls (4), they will be self-supporting, have a variable
thickness with B500S steel reinforcement and a smooth finish, and they will be painted
in the color of choice. This type of wall is placed both in garages as containment,
as well as in stairwells and communication centers.
[0047] In turn, the prefabricated façades (5) will be made up of an outer bearing wall with
a 5 cm thick visible concrete finish, a continuous rigid outer XPS insulation, and
a 15 cm inner structure layer of concrete with inner plasterboard paneling.
[0048] The roof parapets (6) consist of concrete walls prefabricated for parapets, whereby
brick placement is spared and a greater structural stability is obtained.
[0049] The PVC joinery (7) is obtained as a 76 mm deep PVC window with 5 chambers.
[0050] The glass panels (8) have a double glazing formed by a colorless glass panel having
a thickness according to the project and a second glass panel having a thickness according
to the project and the dehydrated air chamber has a variable thickness with double
perimeter sealing and aluminum separator profile.
[0051] In terms of the plasterboards, not depicted in the figures as they are conventional,
said plasterboards allow obtaining a 15 mm thick inner plasterboard paneling.
[0052] With respect to the installations, as shown in Figure 9, the prefabricated walls
(4) internally include the installations of plumbing and raceway system (14).
[0053] In turn, the home electrical panels (9) are partially assembled in factory with the
entire switchgear provided only for connecting the points. It is supplied in a ready-for-placement
plasterboard structure.
[0054] As mentioned above, another one of the prefabricated constructive elements is the
metal baseboard, which will be hung on the metal profile acting as a slate sheet finishing
profile in urbanization.
[0055] The use of metal copings (10), like the one shown in Figure 11, with concealed mechanical
fixing system, has been envisaged in urbanization and parapets. The system circumvents
silicone seals by having waterproof neoprene strips under the attachment, making the
coping completely water-tight, avoiding maintenance of any type.
[0056] In turn, the chimneys (11) are completely assembled from factory with a concealed
structure for a quick and waste-free assembly. An inner metal fitting structure intended
for that purpose is made.
[0057] In terms of the bathrooms (12), and as can be seen in Figure 13, they will also be
prefabricated, with an enveloping system of concealed metal structure and direct plasterboards
with insulation to be left prepared on site so as not to open until delivery, leaving
the installation points to be connected.
[0058] The covering for wet areas consists of a composite system received with high moisture-resistant
glue for placement in kitchen and shower stall fronts. A cleaner, completely water-tight
finish that does not generate tiling waste is achieved. This covering can have the
desired design or drawing because a photograph is submitted and printed to size.
[0059] A system for setting up a compression layer by means of directly polishing the finish
to place the vinyl flooring on top has also been envisaged. This flooring is changed
slat by slat without having to lift long wythes. With this mixed system, the implementation
of mortar screed is spared, avoiding a large amount of waste.
[0060] Lastly, the involvement of prefabricated balconies (13) is envisaged in the construction
system, said balconies having metal fittings completely finished in factory including
the outdoor wooden flooring with a water collection tray and connected by means of
mechanical anchoring to the metal structure of the top slab.
[0061] In terms of the construction process, for on-site set up, auxiliary installations
and resources will be provided for the workers. To avoid blocking public roads or
interfering with construction works, a space within the plot of land has been chosen.
The free spaces between blocks and the urbanization area are thereby reserved for
the interior circulation of vehicles and for stockpiling, in the future shared interior
urbanization area of the houses.
[0062] The stockpiling area is distributed in two accessible spaces, together with an area
intended as a rebar workshop. It has been determined that these locations do not obstruct
works and crane access areas.
[0063] The installation of construction offices provided with water, light, telephone connection,
as well as IT and auxiliary resources, is considered necessary for proper construction
planning and execution.
[0064] Furthermore, to prevent impacts that may be generated in the surroundings during
the operative phase of these installations, the following preventive measures must
be applied:
[0065] Temporarily fencing the construction areas to be occupied, putting up signs to indicate
same and the transit roads, so as not to affect lands not related to the construction.
[0066] The engines of the machinery and loading vehicles will be regulated so that they
comply with the legislation in force in terms of the emission of gases to the atmosphere.
Likewise, effective mufflers approved by the competent organizations will be provided
and the machinery shall comply with Directives 86/622/EEC and 95/27/EC on the limitations
of noise emitted by the public work machinery at all times.
[0067] Periodic watering of discharge accesses and areas to prevent the emission of particles
and dust.
[0068] Services in terms of the needs for water, light, and telephone connections will be
from nearby points. Furthermore, and for movement around the construction site, there
will be a mobile telephone phone system for an uninterrupted faultless communication.
[0069] The availability of electric power and particularly water, required for the operation
of the installations, will be assured either by providing the required services or
by installing generators and a potable water tank of sufficient capacity.
[0070] There will also be a fully equipped first-aid kit. Occasional or emergency care will
be provided through the different public and/or private medical services existing
in the area.
[0071] The selected units or sheds, as well as the access path, will be conditioned for
setting up the following general services.
- Office
- Canteen
- Warehouse
- Dressing rooms
- Toilets
[0072] The worker installations, toilets, dressing rooms, canteens, and first-aid kit, as
well as offices, will be modular prefabricated ones and transported to the construction
site in a truck in modules measuring 6.00x2.40 m. If space requirements exceed availability
in the plot of land, the sheds will be placed vertically. These modules do not require
any foundation where there are placed, such they are raised on concrete supports and/or
rough brick masonry, allowing multiple combinations in the arrangement thereof.
[0073] The services required, as well as the suitable lighting and heating, will be provided
in all of them taking into account, in any case, their temporary character.
[0074] The technical-administrative office will have a series of work places, with a work
place being prepared for the construction management. In all cases, air conditioning
and heating will be provided.
[0075] The dressing rooms and toilets will be provided with lockers and sinks, toilet pans,
and showers, respectively. Likewise, electric heaters will be provided in the toilets.
In the canteen, in addition to the suitable tables and chairs, food heating elements
will be provided.
[0076] The first-aid kit or treatment room will have the elements required to perform first
aid, there being hospitals and health centers in the area for serious cases.
[0077] Once the installation of all the spaces has ended, construction works will be set
out. Once construction works have started, all the other envisaged installations will
be assembled.
[0078] In terms of the auxiliary installations, a compressed air installation will be established
while construction is going on as an auxiliary element for operations such as concrete
vibration, fretting, demolitions, cleaning, etc.
[0079] An electric power installation will also be set up for supplying the electric power
necessary for shed installation and site installations which will come from the area's
mains connection.
[0080] In each structure site, in order to prevent possible current losses and to prevent
a "critical" site from shutting down, a 150 kVA generator, sufficient for those activities
which, in the event of unforeseen circumstances, can be performed by taking power
supply from the existing installations, such as exhaustions, use of welding equipment,
vibration generators, etc., will be provided.
[0081] Both the medium-voltage line and the low-voltage line will be installed and operated
according to the rules and regulations in force and those others established for this
case.
[0082] The lines will generally be laid overhead, with said lines being able to be laid
underground in the cases in which it is required either due to the characteristics
of the terrain or to special situations, such as parallelisms, crossings, etc.
[0083] There will be provided in the different sites and installations motor control centers
or power and lighting distribution panels which will be suitably protected both mechanically
and electrically according to the type of service they must provide, i.e., fixed,
semi-fixed, and mobile.
[0084] Independently of the protection against accidental direct contacts inherent to the
laid overhead or underground lines in each case, suitable protections against overvoltages,
short-circuits, overcurrent, etc., will be installed and they will be completed with
other defect countercurrents and grounding meshes, so as to ensure maximum worker
safety and service continuity at all times.
[0085] For supplying water in the area of the installations, water will suitably be drawn
from the area's water mains, with a pressure group being provided in each one to ensure
a suitable pressure at the points of use.
[0086] A mobile telephony network will be provided to allow communications between the different
areas of the construction site, as well as between the sites and main installations.
[0087] An indoor telephone exchange having the capacity for several extensions and simultaneous
connections will be installed. This unit will be installed in the main office, from
where all the external cabling will branch out to different areas of the installations,
and will be installed with battery equipment automatically connecting the accumulators
when the mains voltage fails, thereby allowing service continuity.
[0088] For laying the overhead telephone lines, "urban self-supported"-type cable or simply
"plastic urban" cable will generally be used, as the case may be. These cables are
made of a copper conductor with PVC insulation and forming telephone pairs. The telephone
apparatus will be of the "table-top" or "wall-mounted" type, and will be installed
directly or inside soundproof cabins, as the case may be.
[0089] There will also be water mains with suitably located outlets, said water mains will
be installed in the area of the offices and general warehouses, as well as electromechanical
and rebar workshops as means for extinguishing fires.
[0090] This water mains will be complemented with the corresponding manual extinguisher
equipment located in visible and easily accessible places. These manual extinguishers
may be "pressurized water", "chemical foam", "dry powder," or "carbon dioxide" extinguishers,
depending on whether they are intended for extinguishing solid fuel fires that should
not be affected by liquid foam, non-delicate solid fuels, combustible gases or flammable
products and electrical equipment.
[0091] Likewise, lightning protection and storm proximity detection, consisting of lightning
arresters and acoustic alarms, will be provided.
[0092] An electromechanical workshop with a work place for the workshop manager, a small
storage room, and a separate exit for the electrical workshop, dressing rooms and
toilets and the workshop itself, have also been envisaged next to the general installations.
[0093] A rebar workshop and a collection point which will help the operators in waste separation
have also been envisaged.
[0094] The industrialized construction system reduces the need to perform works at height
to a minimum due to its complete façade closure system.
[0095] Nevertheless, when the heights do not exceed 3-4 m, standardized fixed scaffolding
with wheels will be used so as not to damage the flooring.
[0096] The movements of earth include clearing a 15 cm thick layer off the terrain and forming
the void for making the basement and foundation. All earth moving works will be performed
with mechanical means and excess earth will be brought to an authorized landfill.
[0097] In terms of the foundation and containment phase, prefabricated concrete walls will
be used therein, such that the ground containment system is formed by the basement
wall or the semi-prefabricated reinforced concrete containment wall made up of two
parallel, 6 cm HA-25 concrete slabs and B-500-S steel therein.
[0098] The thickness of the wall is 30 cm and the height according to project plans, with
vertical chamfered joints every 2.40 m or 1.20 m.
[0099] The phases of making the reinforced concrete containment walls are related to the
following:
- 1) Excavating the grounds for the foundation: continuous or by foundation trenches
(two-sided or single-sided walls).
- 2) Pouring blinding concrete on the support base of the wall
- 3) Calculating the footing of the wall and making same in the conventional way such
that the metal feet or protruding rebars of the wall are introduced in the prefabricated
sandwich.
- 4) Placing the prefabricated wall. The resistant steel of the wall elevation is incorporated
in the prefabricated wall, so it is not necessary to place any rebar during construction,
only filler concrete.
- 5) Pouring concrete into the wall.
[0100] Each panel is assembled independently from the rest, where 4 wooden wedges and a
so-called double-effect post are necessary. No formwork is necessary and only one
post per panel is required.
[0101] To assure that those walls are completely water-tight, they will be made with a PVC
strip between different concreted parts.
[0102] The time it takes to make a conventional 6 m tall and 15 m long wall is 3 days since
it involves the use of an over-scaffolding for making the second height of the wall.
This wall system allows a 3 m high and 20 m long wall to be completed in a single
day.
[0103] In terms of the foundation, this will be superficial, by means of insulated HA-25
reinforced concrete footings with steel casings for prefabricated columns.
[0104] In terms of the underground sewage network, for the installation of the tubes in
the trench, several reference points are first fixed by means of stakes, nails, or
any other method. Based on these points, the shaft of the pipe is placed at the bottom
of the trench. It may also be suitable to set the pipe out directly at the bottom
of the trench. After this, the trench is made, paying attention to the slopes. This
will be made by means of a backhoe, transporting excess earth to a landfill with a
three-axle truck.
[0105] If the presence of water is detected during emptying, a fishbone-type drainage network
will be made.
[0106] Catch basins, dividers, or wells will be made on a blinding concrete bed.
[0107] The entire drainage system will be supplied by the same manufacturer who has developed
all the elements. The watertightness thereof is thereby assured.
[0108] Finally, before making the floor slab, cleaning will be performed while inspecting
with cameras so that any blockage can be dealt with in a quick and simple manner.
[0109] Once the foundation has moved forward, placement of the prefabricated columns starts.
[0110] With the drainage system already made and the foundation finished, the gravel paving
process begins. This process is extremely important and requires good manual compaction
thereof to be performed. This is because the final floor slab will be arranged on
this support base.
[0111] Since it does not require any posts, the system allows making the floor slab "in
one go" with fewer problems; furthermore, it will allow starting works in the basement
immediately without waiting for the time periods needed for the top slabs, the floor
slab base, and the finishing layer to set, as well as for posts to be removed.
[0112] Once the verticality of the vertical elements is ensured, prefabricated T-shaped
beams will be placed.
[0113] The top slabs chosen for the project are joist slabs and pre-cast slabs with lightened
polystyrene filler blocks.
[0114] This top slab is placed in a quick and simple manner because it is allowed to fall
on the supports at the ends and is ready for the placement of the rebar.
[0115] The compression layer for this top slab is envisaged with a thickness of 5 cm and
is made without polishing unlike the top slabs for housing.
[0116] Having top slabs with prefabricated elements, joist slabs, or pre-cast slabs allows
vertical construction to be performed, moving forward with the upper floors, and allowing
gradually finishing the garage as posts are not needed.
[0117] This allows the floor slab of the garage to be made in a single phase.
[0118] The stairs are made while climbing up the structure. It is made up of a prefabricated
concrete box in which the stairs are supported on brackets by simply supporting them
on top of one another.
[0119] It is a quick process which assures that the workers will be safe on site since they
do not have to walk on platforms.
[0120] The handrail is placed as the stair is made and lastly it is painted before delivery.
The complete safety of the stair is therefore assured.
[0121] In terms of the above-ground structure, the structural system is based on load-bearing
walls (where the top slabs and semi-load bearing walls rest, supporting the weight
thereof and furthermore performing transverse bracing functions and other functions
completing the structural scheme as a whole.
[0122] Said walls will be installed naturally, being supported on one another and using
mechanical anchoring systems for this purpose.
[0123] Some walls are intended for separating houses or interior spaces and other walls
furthermore constitute the façade in line with their structural function.
[0124] The walls contain:
- Incorporated laminated gypsum board.
- Façade insulation.
- Installations built into walls.
- Installed doors and windows (PCV joinery).
- Glass panels.
[0125] The advantage of this system is that the façade elements and party walls, i.e., the
entire structure and enclosure of the construction, can be made in factory, regardless
of the weather condition.
[0126] This allows an orderly, clean, and quick construction.
[0127] In this sense, fully finished façade walls will be placed, party walls will be placed
between houses, and lastly the top slab will be placed on the walls.
[0128] The walls are attached by means of mechanical systems, dispensing with liquid elements
which make the construction thereof slower and messier, with the attachment being
an attachment that reduces waste and speeds up the process.
[0129] The construction is carried out with tower cranes which allow said construction to
be performed without having to occupy roads as a result of requiring mobile cranes.
[0130] After placing the walls, the top slabs are placed and the compression layer which,
in this case is semi-polished, is made without requiring screed mortar.
[0131] This is carried out so on and so forth, floor by floor, until the structure is completed.
[0132] Once the ceiling panels of the houses are placed and the compression layer concreted,
certain activities such as the setting out of partitioning, inner partitioning (that
did not come together with the walls) and the connection of installations can then
be performed, with the rest of the activities also being carried out.
[0133] In terms of the roofs, two different roofs can be obtained, i.e., trafficable roofs
and non-trafficable roofs.
[0134] The sheet considered for both roofs is of a state-of-the-art, synthetic, non-adherent
TPO type.
[0135] It is placed with heaters or automated machines which, depending on the room temperature
and the degree of humidity, apply the suitable temperature on the waterproofing overlaps.
The reason is to prevent degradation due to overheating and to ensure that it does
not lack heat for an optimal welding.
[0136] In the case of a non-trafficable roof (except for maintenance activities), the order
of the non-trafficable roof is as follows:
- 1. Slopes
- 2. Geotextile
- 3. Waterproofing sheet
- 4. Geotextile
- 5. 14 cm XPS
- 6. Geotextile
- 7. 5 cm gravel
[0137] The order of the trafficable roof is as follows:
- 1. Slopes
- 2. Geotextile
- 3. Waterproofing
- 4. Geotextile
- 5. Mortar protective layer
- 6. Flooring
[0138] The synthetic TPO sheet system used has the particularity that there is placed at
the lower part of the parapets a distribution bar which causes strains to be distributed
without creating localized stresses on the sheets, which could be a problem in the
future.
[0139] In terms of the divisions, they may be below or above ground depending on the area
in which they are located.
[0140] If they are below-ground, one of the premises of the industrialized system is the
elimination of the large format with gypsum, which usually causes a lot of cracking
problems during construction. Thus, a 20 cm exposed concrete block is proposed in
the sectorization areas and a 10 cm block in the storage room divisions. This block
is placed like the exposed brick and has a very good finish.
[0141] In the case of above-ground divisions, it must be indicated that 30% of the partitioning
are made in factory, since the entire facade paneling, as well as the housing divisions
that are made up of a structural wall, already have the laminated gypsum board installed
in factory.
[0142] The laminated gypsum board partitioning work is started by the officer who sets out
the site, beginning with the assembly of the supporting structure, with the placement
of the horizontal lower and upper channels, as appropriate, to then proceed with the
vertical pillars placed every 40 or 60 cm and inserted into these channels. The door
pre-frames will also be placed therewith.
[0143] From this point on, in the case of partitions, the first plate will be screwed on
one of the faces thereof followed by the second plate in a staggered manner.
[0144] The installers will pass all the raceway systems and lines that will be housed therein,
and once this is done this end will be closed on the other face with the assembly
of the two corresponding plates. Finally, with an adhered tape covering the joint
and a special paste, the joints will be sealed and all the nuts and bolts covered.
[0145] In the case of stairs, vertical sandwich panels which provide a cleaner finish than
the conventional rough brick with painted gypsum, will be used.
[0146] For the assembly of this panel that has been described, a metal fitting substructure,
which will be assembled in factory and must simply be inserted during the structural
phase through the opening intended as the air well, is required.
[0147] The sandwich panel base is then placed so that the panels serving as a support when
erecting the installations can be placed.
[0148] Once all the installations are in place, the closure panels with their registers
are placed in compliance with the regulation.
[0149] In parallel, a vertical enclosure of the open stairwell formed by a sandwich panel
35 mm thick and 1100 mm wide has been envisaged, formed by two smooth galvanized steel
sheet walls with an external thickness of 0.5 mm and an internal thickness of 0.5
mm, and an insulating polyurethane core having a mean density 40 kg/m
3, with a concealed fastening system.
[0150] With respect to the vertical coverings, they are divided into below-ground and above-ground
coverings.
[0151] In the case of below-ground coverings, the uncovered, exposed block solution provides
a better termination by eliminating works implying the same element.
[0152] In the case of above-ground coverings, a paneling system for showers and kitchens
with a gluing treatment and a composite-like sheet that is completely waterproof and
offers the best performance is chosen. This finish will be placed at the end of the
work as if it were the furniture, so that it will be used for the first time when
the owner moves in.
[0153] The operation is as follows:
Placement of the composite paneling covering:
- 1. Cleaning the plasterboard support
- 2. Applying a special glue according to the manufacturer's indications
- 3. Placing the already measured and previously machined panel
- 4. Placing finishing elements at the ends and corners
- 5. Sealing joints between the shower plate and corners.
[0154] The false ceilings both in homes and in common areas are 13 mm plasterboards with
insulation in bathrooms, kitchens, and areas required by the project.
[0155] The following types of false ceiling will be placed:
- For homes: laminated gypsum board false ceiling and vinyl drop ceiling
- For common areas: smooth false ceiling with riser, soundproof acoustic false ceiling,
continuous false plaster ceiling.
[0156] As a condition for its assembly, all the installations running through the interior
thereof must have been carried out so as to avoid subsequent breakages that may affect
the construction process, and the laminated gypsum paneling and partitions must have
been made.
[0157] This is made prior to the flooring so as to prevent the flooring from being damaged
as a result of the movement of the scaffolding, even if they have wheels, and of the
materials and tools possibly falling.
[0158] In terms of the construction process, in the continuous false ceiling, the steps
to be followed will be similar to the laminated gypsum partitions and paneling, since
the same systems are used, but in a horizontal position.
[0159] The envisaged heights will be marked on the walls with laser levels. The perimeter
profiles will then be placed. After that, the main and secondary profiles will be
placed. The boards will be screwed and the joints sealed as explained above. Finally,
the curtain rods will be installed.
[0160] In terms of the painting process, it is the last task to be performed because it
cannot be carried out in advance due to its fragility. Nevertheless, works can be
organized so that they can be carried out in two stages, in the first stage, sanding
and elimination of imperfections can be performed, followed by the application of
a coat of primer with diluted plastic, plastification, and general mechanical sanding.
[0161] Wooden doors will be supplied in a duly identified manner in accordance with the
carpentry reports to facilitate their placement and subsequent assembly. They will
be distributed by floors and, in turn, by houses. The frames will be assembled with
fittings for putting up the doors.
[0162] Finally, the leaves will be placed and the installation of the closure mechanisms
will come to an end. Given the final finish of these doors (lacquered), they must
be duly protected, since they will be difficult to repair in the event of an impact
and would have to be replaced. They will be assembled prior to the flooring.
[0163] With respect to cabinets, they will be acquired from a workshop since they are modular
elements, such that there is only a need to place them in their final position on
site.
[0164] In terms of flooring, polished concrete will be used if it is below-ground. Compared
to ceramic flooring, this finish is durable and requires minimal maintenance, and
it is impeccable as it is made without any posts.
[0165] Polished concrete will be made when making the bottom slab and will be used to start
works on exposed block.
[0166] If the flooring is above-ground, the use of vinyl flooring coupled by clipping has
been envisaged.
[0167] In terms of the chimneys, and as mentioned above, they are prefabricated elements
that are assembled on site. This chimney has been developed with a system for anchoring
to the top slab in those of small dimensions and embedded in those of larger dimensions
to finish off the waterproofing against its base without having to make brick parapets.
[0168] In turn, the outer baseboards will be detachable metal baseboards hanging from an
element adhered to the wall and held in the lower portion thereof to prevent movement.
This hanging baseboard allows absorbing small tolerances that are generated during
construction, providing a completely flat finish.
[0169] In parallel, the use of metal copings without silicone seals in joints, copings mechanically
fixed to the wall by an attachment element under the joint between parts and with
a waterproof element preventing the sealing thereof, has been envisaged.
[0170] With respect to projecting balconies, they constitute another industrialized element
that arrives on site ready for assembly at the right time.
[0171] They are balconies made with a metal structure with an attachment element acting
as a holding structure embedded in the top slab and mechanically fixed to the completely
finished 3D balcony including flooring, handrail, false ceiling, and water collection
system. This allows adapting the design of the balcony to the architect's design for
this development and any others that may arise. It is a standardized type of construction
solution.
[0172] As a general rule and as explained, the installations must be adapted to other processes,
such as partitioning, ceilings, flooring, etc.
[0173] In the garage, and since the system of the present invention does not have any posts,
the entry of the ceiling networks and the trays thereof can be done immediately after
the concreting of the lower floor compression layer, and it is necessary to set out
the partitions and make the floor slab to work in optimal conditions.
[0174] In the houses, as the different enclosures are constructed, the piping, trays, and
raceway systems, particularly the installations that will be embedded in the enclosures
in factory and in the laminated gypsum partitions and paneling, will be gradually
installed.
[0175] As indicated above, the installations are incorporated in the prefabricated walls
and then connected and complemented with the rest of the installation made
"in situ".
[0176] The false ceilings will be made once all the installations running through the interior
thereof have been made.
[0177] After the ceilings, the terminal elements (grating, light fixture, detectors, etc.)
can be installed. Finally, upon the conclusion of painting works, the mechanisms and
their decorative components will be assembled, with the connection boxes being previously
installed.
[0178] In terms of the prefabricated bathrooms, they are assembled in line with the structure
before placing the ceiling slab thereof.
[0179] In turn, the electrical panel comes with a plasterboard structure which is placed
in the wall, leaving the element fully finished.
1. A construction system,
characterized in that it involves the following prefabricated elements:
• Prefabricated columns (1)
• Prestressed beams (2)
• Precast slabs (3)
• Prefabricated walls (4) with plumbing and raceway systems (14)
• Prefabricated façades (5)
• Roof parapets (6)
• PVC joinery (7)
• Glass panels (8)
• Plasterboards
• Home electrical panel (9)
• Metal baseboard
• Coping (10)
• Chimneys (11)
• Prefabricated bathrooms (12)
• Covering for wet areas
• Vinyl flooring
• Prefabricated balconies (13)
2. The construction system according to claim 1, characterized in that the prefabricated columns (1) are obtained in reinforced concrete of variable cross
section connected to footing by means of an injected steel casing, having a smooth
finish and a paint coat.
3. The construction system according to claim 1, characterized in that the prestressed beams (2) are made as prefabricated T-shape type prestressed concrete
elements, with connections and support apparatus with columns (2') included, having
a smooth finish and a paint coat.
4. The construction system according to claim 1, characterized in that the precast slabs (3) are made as top slabs with lightened polystyrene filler blocks
(3'), formed by a prefabricated reinforced concrete plate, top slab tensile reinforcements,
and ties.
5. The construction system according to claim 1, characterized in that the prefabricated walls (4) are self-supporting, have a variable thickness with B500S
steel reinforcement and a smooth finish and paint.
6. The construction system according to claim 1, characterized in that the prefabricated façades (5) are made up of an outer bearing wall with a 5 cm thick
visible concrete finish, a continuous rigid outer XPS insulation, and a 15 cm inner
structure layer of concrete with inner plasterboard paneling.
7. The construction system according to claim 1, characterized in that the roof parapets (6) are made as concrete walls prefabricated for parapets.
8. The construction system according to claim 1, characterized in that the PVC joinery (7) is made as 76 mm deep PVC windows with 5 chambers.
9. The construction system according to claim 1, characterized in that the glass panels (8) have a double glazing formed by a colorless glass panels and
an intermediate dehydrated air chamber with double perimeter sealing and aluminum
separator profile.
10. The construction system according to claim 1, characterized in that the plasterboards are 15 mm thick.
11. The construction system according to claim 1, characterized in that the home electrical panels (9) are partially assembled in factory with the entire
switchgear provided only for connecting the points, incorporating a plasterboard structure
for direct placement.
12. The construction system according to claim 1, characterized in that the metal baseboard is hung on a metal profile.
13. The construction system according to claim 1, characterized in that the metal copings (10) include a concealed mechanical fixing system.
14. The construction system according to claim 1, characterized in that the prefabricated chimneys (11) include a concealed structure for a quick and waste-free
assembly by means of an inner metal fitting structure.
15. The construction system according to claim 1, characterized in that the prefabricated bathrooms (12) include an enveloping system of concealed metal
structure and direct plasterboards with insulation to be left prepared on site, with
installation points to be connected.
16. The construction system according to claim 1, characterized in that the covering for wet areas consists of a composite system received with high moisture-resistant
glue for kitchen and shower stall fronts.
17. The construction system according to claim 1, characterized in that the prefabricated balconies (13) have metal fittings completely finished in factory
including the outdoor wooden flooring with a water collection tray and means for mechanical
connection to the metal structure of the top slab.
18. A method for putting the system according to claim 1 into practice,
characterized in that the following operative phases are established therein:
a) Setting up on-site auxiliary installations and resources for the workers
b) Moving earth
c) Setting up the foundation and containment by means of using prefabricated concrete
walls (4)
d) Making the underground sewage network
e) Setting up prefabricated columns (1), prestressed beams (2), gravel paving, and
setting up the floor slab
f) Installing the top slabs from the precast slabs (3) and obtaining a polished compression
layer
g) Making stairs
h) Forming façades by means of mechanical anchoring systems from the prefabricated
façades (5), PVC joinery (7), and glass panels (8)
i) Repeating steps f, g, and h until the desired height of the building is obtained
j) Setting out inner partitioning and installation connection
k) Installing roofs
l) Applying vertical coverings, and obtaining false ceilings, and painting surfaces
m) Installing the wood joinery
n) Laying out flooring