TECHNICAL FIELD
[0001] The present disclosure relates to an air conditioning system.
BACKGROUND ART
[0002] There has been known a refrigerant flow path switching device configured to switch,
in an air conditioner including an outdoor unit and a plurality of indoor units, among
refrigerant flow paths between the outdoor unit and the plurality of indoor units,
for individual switching between cooling operation and heating operation at each of
the indoor units (see PATENT LITERATURE 1 or the like).
CITATION LIST
[PATENT LITERATURE]
SUMMARY OF THE INVENTION
[TECHNICAL PROBLEM]
[0004] A pipe length from the outdoor unit to the indoor units via the refrigerant flow
path switching device is set such that a value obtained by adding a predetermined
first value to the pipe length is within a predetermined upper limit value. The first
value is determined in consideration of a pressure loss of a refrigerant pipe in the
refrigerant flow path switching device, and is set to a relatively large constant
value in accordance with a case where the pressure loss is maximum. However, depending
on a capacity of the indoor unit, the pressure loss of the refrigerant pipe becomes
small, and the first value may be made smaller than a constant value. Even in such
a case, when the pipe length is set by using the first value at the constant value,
the pipe length is limited to be shorter than necessary.
[0005] An object of the present disclosure is to provide an air conditioning system capable
of increasing a pipe length from an outdoor unit to an indoor unit.
[SOLUTION TO PROBLEM]
[0006]
- (1) An air conditioning system of the present disclosure includes an outdoor unit,
a plurality of indoor units, and at least one refrigerant flow path switching device
that switches a flow path of a refrigerant between the outdoor unit and the plurality
of indoor units, in which a pipe length that is a sum of lengths of external pipes
from the outdoor unit to the indoor units via the at least one refrigerant flow path
switching device is set such that a value obtained by adding at least a first value
determined in accordance with a sum of capabilities of the indoor units connected
to the at least one refrigerant flow path switching device to the pipe length is equal
to or less than an upper limit value determined in advance.
In the air conditioning system configured as described above, the pipe length, which
is the sum of the lengths of the external pipes from the outdoor unit to the indoor
units, can be obtained by subtracting the first value determined in accordance with
the capabilities of the indoor units from the upper limit value. As a result, by decreasing
the first value as the sum of the capabilities of the indoor units decreases, the
pipe lengths from the outdoor unit to the indoor units can be increased by a decrease
in the first value.
- (2) The air conditioning system preferably includes a plurality of the refrigerant
flow path switching devices connected to each other in series, in which the first
value corresponding to each of the refrigerant flow path switching devices is determined
in accordance with a sum of capabilities of the indoor units respectively connected
to the refrigerant flow path switching device and the refrigerant flow path switching
devices located downstream of the refrigerant flow path switching device, the pipe
length is a maximum pipe length that is a sum of lengths of external pipes from the
outdoor unit to the indoor units connected to the refrigerant flow path switching
device located on a most downstream side, the upper limit value is an upper limit
length of the maximum pipe length, and the maximum pipe length is set such that a
value obtained by adding at least the first value corresponding to each of the plurality
of refrigerant flow path switching devices to the maximum pipe length is equal to
or less than the upper limit length.
With such a configuration, the first value corresponding to each of the refrigerant
flow path switching devices can be made smaller as the sum of the capabilities of
the indoor units connected to the refrigerant flow path switching device and the refrigerant
flow path switching devices located downstream of the refrigerant flow path switching
device becomes smaller. As a result, the maximum pipe length, which is the sum of
the lengths of the external pipes from the outdoor unit to the indoor units connected
to the refrigerant flow path switching device located on the most downstream side,
can be increased by a decrease in the first values.
- (3) The pipe length is preferably set such that a value obtained by further adding
a correction length considering a branch pipe disposed between the outdoor unit and
each of the indoor units to the pipe length is equal to or less than the upper limit
value.
With such a configuration, since the branch pipe is taken into consideration when
the pipe length from the outdoor unit to each of the indoor units is set, the pipe
length can be set to an appropriate value.
- (4) The air conditioning system includes a plurality of the refrigerant flow path
switching devices connected to each other in series, in which the external pipes include
a connecting pipe that connects the refrigerant flow path switching devices adjacent
to each other, and a pipe diameter of the connecting pipe is set in accordance with
a sum of capabilities of the indoor units connected to the refrigerant flow path switching
device located downstream of the connecting pipe.
[0007] Such a configuration allows the pipe diameter of the connecting pipe to be set to
an appropriate value. As a result, it is possible to avoid such an event that oil
cannot be returned during an oil return operation due to the pipe diameters being
excessively thick, or that the pressure loss increases due to the pipe diameters being
excessively thin.
BRIEF DESCRIPTION OF DRAWINGS
[0008]
FIG. 1 is a configuration diagram of an air conditioning system according to an embodiment
of the present disclosure.
FIG. 2 is a refrigerant circuit diagram of the air conditioning system.
FIG. 3 is a perspective view of a refrigerant flow path switching device.
FIG. 4 is a pipe system diagram illustrating an exemplary connection of the refrigerant
flow path switching device in the air conditioning system.
FIG. 5 is a pipe system diagram for describing a pipe length of the air conditioning
system.
FIG. 6 is a table exemplifying a first value corresponding to a sum of capabilities
of a plurality of indoor units.
FIG. 7 is a pipe system diagram illustrating another exemplary connection of the refrigerant
flow path switching device in the air conditioning system.
DETAILED DESCRIPTION
[0009] An air conditioning system of the present disclosure will be described in detail
hereinafter with reference to the accompanying drawings. Note that the present disclosure
is not limited to the following exemplification, but is intended to include all changes
within meanings and a scope of claims and equivalents.
[0010] FIG. 1 is a configuration diagram of an air conditioning system according to an embodiment
of the present disclosure.
[0011] An air conditioning system 100 is installed in a building, a plant, or the like and
achieves air conditioning in an air conditioning target space. The air conditioning
system 100 includes an air conditioner 101 and a refrigerant flow path switching device
130. The air conditioner 101 is configured to execute vapor compression refrigeration
cycle operation to cool or heat the air conditioning target space.
[0012] The air conditioner 101 includes an outdoor unit 110 as a heat source unit and an
indoor unit 120 as a utilization unit. In the air conditioner 101, a plurality of
the indoor units 120 is connected to the single outdoor unit 110 via the refrigerant
flow path switching device 130. In the air conditioner 101, the refrigerant flow path
switching device 130 is configured to freely select cooling operation or heating operation
for each of the indoor units 120.
[Configuration of outdoor unit]
[0013] FIG. 2 is a refrigerant circuit diagram of the air conditioning system.
[0014] The outdoor unit 110 is installed outdoors such as on a roof or a balcony of a building,
or underground.
[0015] The outdoor unit 110 includes a gas-side first shutoff valve 21, a gas-side second
shutoff valve 22, a liquid-side shutoff valve 23, an accumulator 24, a compressor
25, a first flow path switching valve 26, a second flow path switching valve 27, a
third flow path switching valve 28, an outdoor heat exchanger 30, an outdoor fan 33,
a first outdoor expansion valve 34, and a second outdoor expansion valve 35. The outdoor
heat exchanger 30 includes a first heat exchange unit 31 and a second heat exchange
unit 32. The outdoor unit 110 is connected to the refrigerant flow path switching
device 130 via a liquid connection pipe 11, a suction gas connection pipe 12, and
a high and low-pressure gas connection pipe 13.
[Configuration of indoor unit]
[0016] The indoor unit 120 is of a ceiling embedded type, a ceiling pendant type, a floorstanding
type, or a wall mounted type. The air conditioning system 100 according to the present
embodiment exemplarily includes four indoor units 120. The indoor unit 120 includes
an indoor expansion valve 51, an indoor heat exchanger 52, an indoor fan 53, a liquid
tube LP, and a gas tube GP.
[Configuration of refrigerant flow path switching device]
[0017] The refrigerant flow path switching device 130 is provided between the outdoor unit
110 and the plurality of indoor units 120. The refrigerant flow path switching device
130 switches among refrigerant flow paths between the outdoor unit 110 and the plurality
of indoor units 120.
[0018] FIG. 3 is a perspective view of the refrigerant flow path switching device. As illustrated
in FIG. 2 and FIG. 3, the refrigerant flow path switching device 130 includes a casing
131, a control box 132, a plurality of header pipes (refrigerant pipes) 55, 56, and
57, and a plurality of switching units 70. The plurality of header pipes 55, 56 and,
57 includes a first header pipe 55, a second header pipe 56, and a third header pipe
57.
[0019] The refrigerant flow path switching device 130 according to the present embodiment
includes four switching units 70. Each of the switching units 70 is connected with
a single indoor unit 120. The refrigerant flow path switching device 130 according
to the present embodiment can thus be connected with four indoor units 120. The refrigerant
flow path switching device 130 may alternatively include two, three, or five or more
switching units 70, not limited to four switching units 70.
[0020] Each of the plurality of switching units 70 includes a first valve EV1, a second
valve EV2, a first refrigerant tube P1, a third refrigerant tube P3, a fourth refrigerant
tube P4, a utilization gas pipe 61, and a utilization liquid pipe 62. Each of the
switching units 70 switches a flow of the refrigerant by adjusting opening degrees
of the first valve EV1 and the second valve EV2.
[0021] The switching unit 70 includes a plurality of first branch pipes 71 branching from
the first header pipe 55, a plurality of second branch pipes 72 branching from the
second header pipe 56, and a plurality of third branch pipes 73 branching from the
third header pipe 57. The first branch pipe 71 includes the first refrigerant tube
P1, the third refrigerant tube P3, and the utilization gas pipe 61. The second branch
pipe 72 includes the fourth refrigerant tube P4 and the utilization gas pipe 61. The
third branch pipe 73 includes the utilization liquid pipe 62.
[Operation of air conditioning system]
[0022] Description is made hereinafter with reference to FIG. 2 of a case where all the
indoor units 120 in operation in the air conditioning system 100 execute cooling operation
(hereinafter, also referred to as "full cooling operation"), a case where all the
indoor units 120 in operation execute heating operation (hereinafter, also referred
to as "full heating operation"), and a case where some of the indoor units 120 in
operation execute cooling operation and the remaining indoor units 120 execute heating
operation (hereinafter, also referred to as "cooling and heating mixed operation").
(Full cooling operation)
[0023] During full cooling operation, the first valve EV1 in the switching unit 70 is fully
opened. The second valve EV2 is fully opened. In the indoor unit 120 being stopped,
during any one of full cooling operation, full heating operation, and cooling and
heating mixed operation, the first valve EV1 corresponding to this indoor unit 120
has a minimum opening degree, and the second valve EV2 is fully closed.
[0024] When the compressor 25 is driven, a high-pressure gas refrigerant compressed by the
compressor 25 passes through the first flow path switching valve 26, the third flow
path switching valve 28, and the like, and flows into the outdoor heat exchanger 30
to be condensed. The refrigerant condensed in the outdoor heat exchanger 30 passes
through the first and second outdoor expansion valves 34 and 35, the liquid-side shutoff
valve 23, and the like, and flows into the liquid connection pipe 11.
[0025] The refrigerant having flowed into the liquid connection pipe 11 flows in the third
header pipe 57 of the refrigerant flow path switching device 130, passes through the
utilization liquid pipe 62 of each of the switching units 70, and flows into the indoor
unit 120. The refrigerant having flowed into the indoor unit 120 is decompressed at
the indoor expansion valve 51 and is then evaporated in the indoor heat exchanger
52.
[0026] In the indoor unit 120, the refrigerant evaporated in the indoor heat exchanger 52
flows from the gas tube GP into the utilization gas pipe 61, mainly passes through
the second valve EV2, and flows into the second header pipe 56.
[0027] The refrigerant having flowed into the second header pipe 56 passes through the suction
gas connection pipe 12, flows into the outdoor unit 110, and is sucked into the compressor
25.
[0028] The refrigerant having flowed into the utilization gas pipe 61 also passes through
the first valve EV1 and flows into the first header pipe 55. The refrigerant (low-pressure
gas refrigerant) having flowed into the first header pipe 55 passes through the high
and low-pressure gas connection pipe 13, the second flow path switching valve 27,
and the accumulator 24, and is sucked into the compressor 25.
(Regarding full heating operation)
[0029] During full heating operation, the first valve EV1 in the switching unit 70 is fully
opened. The second valve EV2 is fully closed. When the compressor 25 is driven, the
high-pressure gas refrigerant compressed by the compressor 25 passes through the second
flow path switching valve 27 and the like, and flows into the high and low-pressure
gas connection pipe 13. The refrigerant having flowed into the high and low-pressure
gas connection pipe 13 passes through the first header pipe 55 of the refrigerant
flow path switching device 130, the first refrigerant tube P1 of the switching unit
70, and then the first valve EV1, and flows from the utilization gas pipe 61 into
the gas tube GP of the indoor unit 120.
[0030] The refrigerant having flowed into the gas tube GP flows into the indoor heat exchanger
52 of the indoor unit 120 to be condensed. The condensed refrigerant passes through
the indoor expansion valve 51, flows in the liquid tube LP, passes through the utilization
liquid pipe 62 of the switching unit 70, and flows into the third header pipe 57.
[0031] The refrigerant having flowed into the third header pipe 57 flows in the liquid connection
pipe 11, flows into the outdoor unit 110, and is decompressed at the first and second
outdoor expansion valves 34 and 35. The decompressed refrigerant is evaporated while
passing through the outdoor heat exchanger 30, passes through the first flow path
switching valve 26, the third flow path switching valve 28, and the like, and is sucked
into the compressor 25.
(Regarding cooling and heating mixed operation)
[0032] In the switching unit 70 (hereinafter, also referred to as a "cooling switching unit
70") corresponding to the indoor unit 120 (hereinafter, also referred to as a "cooling
indoor unit 120") executing cooling operation among the indoor units 120 in operation,
the first valve EV1 has the minimum opening degree. The second valve EV2 is fully
opened.
[0033] In the switching unit 70 (hereinafter, also referred to as a "heating switching unit
70") corresponding to the indoor unit 120 (hereinafter, also referred to as a "heating
indoor unit 120") executing heating operation among the indoor units 120 in operation,
the first valve EV1 is fully opened. The second valve EV2 is fully closed.
[0034] When the compressor 25 is driven, part of the high-pressure gas refrigerant compressed
by the compressor 25 passes through the second flow path switching valve 27 and the
like, and flows into the high and low-pressure gas connection pipe 13. The remaining
part of the high-pressure gas refrigerant compressed by the compressor 25 passes through
the third flow path switching valve 28, is condensed at the first heat exchange unit
31 of the outdoor heat exchanger 30, passes through the first outdoor expansion valve
34, and flows into the liquid connection pipe 11. The refrigerant having been condensed
at the first heat exchange unit 31 passes through the second outdoor expansion valve
35, is evaporated at the second heat exchange unit 32, passes through the first flow
path switching valve 26, and is sucked into the compressor 25.
[0035] The refrigerant having flowed into the high and low-pressure gas connection pipe
13 flows into the first header pipe 55 of the refrigerant flow path switching device
130, flows in the first refrigerant tube P1, the first valve EV1, and the utilization
gas pipe 61 of the heating switching unit 70, and flows into the gas tube GP.
[0036] The refrigerant having flowed into the gas tube GP is condensed in the indoor heat
exchanger 52 of the heating indoor unit 120. The condensed refrigerant passes through
the utilization liquid pipe 62 of the heating switching unit 70 from the liquid tube
LP, and flows into the third header pipe 57.
[0037] The refrigerant having flowed from the outdoor unit 110 into the liquid connection
pipe 11 also flows into the third header pipe 57. The refrigerant having flowed into
the third header pipe 57 passes through the utilization liquid pipe 62 and the liquid
tube LP of the cooling switching unit 70, and flows into the cooling indoor unit 120.
[0038] The refrigerant having flowed into the cooling indoor unit 120 is decompressed at
the indoor expansion valve 51, and is evaporated in the indoor heat exchanger 52 to
cool the indoor space.
[0039] The evaporated refrigerant flows in the gas tube GP, flows into the utilization gas
pipe 61 of the cooling switching unit 70, passes through the second valve EV2, flows
into the fourth refrigerant tube P4 and the second header pipe 56, and flows in the
suction gas connection pipe 12 to be sucked into the compressor 25.
[Exemplary connection of refrigerant flow path switching device]
[0040] FIG. 4 is a pipe system diagram illustrating an exemplary connection of the refrigerant
flow path switching device in the air conditioning system.
[0041] The air conditioning system 100 according to the present embodiment includes a first
refrigerant flow path switching device group G1 and a second refrigerant flow path
switching device group G2. Each of the first refrigerant flow path switching device
group G1 and the second refrigerant flow path switching device group G2 includes a
plurality of (four in FIG. 4) refrigerant flow path switching devices 130.
[0042] The first refrigerant flow path switching device group G1 includes a refrigerant
flow path switching device 130A, a refrigerant flow path switching device 130B, a
refrigerant flow path switching device 130C, and a refrigerant flow path switching
device 130D connected in series. In each of the adjacent refrigerant flow path switching
devices 130A, 130B, 130B, 130C, 130C, and 130D, the first header pipes 55, the second
header pipes 56, and the third header pipes 57 are connected to each other via first
connecting pipes (external pipes) 141, 142, and 143.
[0043] One end of each of first on-site pipes (external pipes) 151, 152, and 153 is connected
to each of upstream ends of the first header pipe 55, the second header pipe 56, and
the third header pipe 57 of the refrigerant flow path switching device 130A disposed
at a most upstream side. The other end of each of the first on-site pipes 151, 152,
and 153 is connected to the high and low-pressure gas connection pipe 13, the suction
gas connection pipe 12, and the liquid connection pipe 11, which are external pipes
extending from the outdoor unit 110, via first branch pipes (external pipes) 161,
162, and 163. The refrigerant flow path switching devices 130A to 130D are thus connected
in series to the outdoor unit 110.
[0044] Closing pipes 171, 172, and 173 are connected to each of downstream ends of the first
header pipe 55, the second header pipe 56, and the third header pipe 57 of the refrigerant
flow path switching device 130D disposed at a most downstream side.
[0045] The second refrigerant flow path switching device group G2 includes, for example,
a refrigerant flow path switching device 130E, a refrigerant flow path switching device
130F, and a refrigerant flow path switching device 130G connected in series, and a
refrigerant flow path switching device 130H branched downstream of the refrigerant
flow path switching device 130E and connected in parallel with the refrigerant flow
path switching device 130F.
[0046] In each of the refrigerant flow path switching devices 130E and 130F, and 130F and
130G adjacent in one direction, the first header pipes 55, the second header pipes
56, and the third header pipes 57 are connected to each other via second connecting
pipes (external pipes) 144, 145, and 146.
[0047] One end of each of second on-site pipes (external pipes) 154, 155, and 156 is connected
to each of the upstream ends of the first header pipe 55, the second header pipe 56,
and the third header pipe 57 of the refrigerant flow path switching device 130E disposed
at one end in an arrangement direction. The other end of each of the second on-site
pipes 154, 155, and 156 is connected to the high and low-pressure gas connection pipe
13, the suction gas connection pipe 12, and the liquid connection pipe 11 extending
from the outdoor unit 110, via the first branch pipes 161, 162, and 163. The refrigerant
flow path switching devices 130E to 130G are thus connected in series to the outdoor
unit 110.
[0048] One end of each of third on-site pipes (external pipes) 157, 158, and 159 is connected
to each of the upstream ends of the first header pipe 55, the second header pipe 56,
and the third header pipe 57 of the refrigerant flow path switching device 130H disposed
separately from the arrangement direction. The other end of each of the third on-site
pipes 157, 158, and 159 is connected to second branch pipes (external pipes) 164,
165, and 166 provided at a center in a longitudinal direction of the second on-site
pipes 154, 155, and 156 between the refrigerant flow path switching device 130E and
the refrigerant flow path switching device 130F. The refrigerant flow path switching
devices 130E and 130H are thus connected in series to the outdoor unit 110.
[0049] The closing pipes 171, 172, and 173 are connected to each of the downstream ends
of the first header pipe 55, the second header pipe 56, and the third header pipe
57 of each of the refrigerant flow path switching device 130G and the refrigerant
flow path switching device 130H disposed at the most downstream side.
[Setting of pipe length]
(First refrigerant flow path switching device group)
[0050] FIG. 5 is a pipe system diagram for describing a pipe length of the air conditioning
system. The pipe length is a sum of lengths of the external pipes from the outdoor
unit 110 to the indoor unit 120 via the refrigerant flow path switching device 130.
As illustrated in FIG. 4 and FIG. 5, in the refrigerant flow path switching devices
130A to 130D of the first refrigerant flow path switching device group G1 connected
to each other in series, a maximum pipe length L1 of pipe lengths from the outdoor
unit 110 to the indoor units 120 connected to the each of the refrigerant flow path
switching devices 130A to 130D via the high and low-pressure gas connection pipe 13
is a pipe length from the outdoor unit 110 to each of the indoor units 120 connected
to the refrigerant flow path switching device 130D located on the most downstream
side via the high and low-pressure gas connection pipe 13. The maximum pipe length
L1 can be calculated by the following formula (1).

[0051] L11 is a length of the high and low-pressure gas connection pipe 13. L12 is a length
of the first on-site pipe 151. L13 is a length of the first connecting pipe 141.
[0052] In the refrigerant flow path switching devices 130A to 130D connected to each other
in series, a maximum pipe length L2 of pipe lengths from the outdoor unit 110 to the
indoor units 120 connected to the each of the refrigerant flow path switching devices
130A to 130D via the suction gas connection pipe 12 is a pipe length from the outdoor
unit 110 to each of the indoor units 120 connected to the refrigerant flow path switching
device 130D located on the most downstream side via the suction gas connection pipe
12. The maximum pipe length L2 can be calculated by the following formula (2).

[0053] L21 is a length of the suction gas connection pipe 12. L22 is a length of the first
on-site pipe 152. L23 is a length of the first connecting pipe 142.
[0054] In the refrigerant flow path switching devices 130A to 130D connected to each other
in series, a maximum pipe length L3 of pipe lengths from the outdoor unit 110 to the
indoor units 120 connected to the each of the refrigerant flow path switching devices
130A to 130D via the liquid connection pipe 11 is a pipe length from the outdoor unit
110 to each of the indoor units 120 connected to the refrigerant flow path switching
device 130D located on the most downstream side via the liquid connection pipe 11.
The maximum pipe length L3 can be calculated by the following formula (3).

[0055] L31 is a length of the liquid connection pipe 11. L32 is a length of the first on-site
pipe 153. L33 is a length of the first connecting pipe 143.
[0056] Each of the maximum pipe lengths L1, L2, and L3 is set to be equal to or less than
a predetermined upper limit value. At this time, the maximum pipe lengths L1, L2,
and L3 are set so as to satisfy the following formulas (4), (5), and (6), respectively,
in consideration of the first branch pipes 161, 162, and 163, the header pipes 55,
56, and 57 of the refrigerant flow path switching devices 130A to 130D, and the like
disposed between the outdoor unit 110 and the indoor units 120 connected to the refrigerant
flow path switching device 130D.

[0057] J11, J12, and J13 are correction lengths determined in consideration of the first
branch pipes 161, 162, and 163, respectively, disposed between the outdoor unit 110
and the refrigerant flow path switching device 130D. J11, J12, and J13 in the present
embodiment are determined to be constant values (for example, 0.5 m) in consideration
of a pressure loss of each of the first branch pipes 161, 162, and 163, for example.
[0058] Lu is a value defined by a standard or the like, and is an upper limit length (upper
limit value) of a maximum pipe length from the outdoor unit 110 to the indoor unit
120 connected to the refrigerant flow path switching device 130 located on the most
downstream side in the plurality of refrigerant flow path switching devices 130 connected
in series. For example, Lu is 120 m.
[0059] Ka is a common value used as a length of the first header pipe 55, a length of the
second header pipe 56, and a length of the third header pipe 57 in the refrigerant
flow path switching device 130A. Ka is determined in consideration of a pressure loss
of the header pipes 55 to 57. Specifically, Ka is a first value determined in accordance
with a sum of capabilities of the plurality of indoor units 120 connected to the refrigerant
flow path switching device 130A and the refrigerant flow path switching devices 130B,
130C, and 130D located downstream of the refrigerant flow path switching device A.
[0060] Kb is a common value used as a length of the first header pipe 55, a length of the
second header pipe 56, and a length of the third header pipe 57 in the refrigerant
flow path switching device 130B. Kb is determined in consideration of a pressure loss
of the header pipes 55 to 57. Specifically, Kb is a first value determined in accordance
with a sum of capabilities of the plurality of indoor units 120 connected to the refrigerant
flow path switching device 130B and the refrigerant flow path switching devices 130C
and 130D located downstream of the refrigerant flow path switching device B.
[0061] Kc is a common value used as a length of the first header pipe 55, a length of the
second header pipe 56, and a length of the third header pipe 57 in the refrigerant
flow path switching device 130C. Kc is determined in consideration of a pressure loss
of the header pipes 55 to 57. Specifically, Kc is a first value determined in accordance
with a sum of capabilities of the plurality of indoor units 120 connected to the refrigerant
flow path switching device 130C and the refrigerant flow path switching device 130D
located downstream of the refrigerant flow path switching device C.
[0062] Kd is a common value used as a length of the first header pipe 55, a length of the
second header pipe 56, and a length of the third header pipe 57 in the refrigerant
flow path switching device 130D. Kd is determined in consideration of a pressure loss
of the header pipes 55 to 57. Specifically, Kd is a first value determined in accordance
with a sum of capabilities of the plurality of indoor units 120 connected to the refrigerant
flow path switching device 130D.
[0063] Md is a common value used as a length of the first branch pipe 71, a length of the
second branch pipe 72, and a length of the third branch pipe 73 in the refrigerant
flow path switching device 130D. Md is a second value determined to be a constant
value (for example, 4.3 m) in consideration of a pressure loss of the branch pipes
71 to 73.
[0064] FIG. 6 is a table exemplifying the first value corresponding to the sum of the capabilities
of the plurality of indoor units. In FIG. 6, the capacity of the indoor unit 120 is
used as the capability of the indoor unit 120, and the smaller a sum of the capacities
(capabilities) of the indoor units 120, the smaller the first value. The first values
Ka, Kb, Kc, and Kd are determined on the basis of the table in FIG. 6. As the capability
of the indoor unit 120, power consumption of the indoor unit 120 or the like may be
used in addition to the capacity of the indoor unit 120.
[0065] In the present embodiment, in the refrigerant flow path switching devices 130A to
130D of the first refrigerant flow path switching device group G1 connected in series
to each other, the refrigerant flow path switching device located on the downstream
side has a smaller sum of the capacities of the indoor units 120 connected to the
own device and the refrigerant flow path switching device located on the downstream
side. Accordingly, the first values Ka, Kb, Kc, and Kd respectively corresponding
to the refrigerant flow path switching devices 130A to 130D are set to gradually smaller
values in that order.
[0066] For example, when the capacity of each indoor unit 120 connected to the refrigerant
flow path switching devices 130A to 130C is 3.5 kw and the capacity of each indoor
unit 120 connected to the refrigerant flow path switching device 130D is 7.0 kw, the
first values Ka, Kb, Kc, and Kd corresponding to the refrigerant flow path switching
devices 130A to 130D are determined as follows.
[0067] The first value Ka corresponding to the refrigerant flow path switching device 130A
is determined to be a value corresponding to the sum of the capacities of a total
of 16 indoor units 120 connected to the refrigerant flow path switching devices 130A
to 130D. Since 70.0 kw (= 3.5 × 12 + 7.0 × 4), which is the sum of the capacities,
corresponds to "67.4 or more and less than 85.0" in the table in FIG. 6, the first
value Ka is set to 4.3 m.
[0068] The first value Kb corresponding to the refrigerant flow path switching device 130B
is determined to be a value corresponding to the sum of the capacities of a total
of 12 indoor units 120 connected to the refrigerant flow path switching devices 130B
to 130D. Since 56.0 kw (= 3.5 × 8 + 7.0 × 4), which is the sum of the capacities,
corresponds to "47.5 or more and less than 67.4" in the table in FIG. 6, the first
value Kb is set to 2.2 m.
[0069] The first value Kc corresponding to the refrigerant flow path switching device 130C
is determined to be a value corresponding to the sum of the capacities of a total
of 8 indoor units 120 connected to the refrigerant flow path switching devices 130C
and 130D. Since 42.0 kw (= 3.5 × 4 + 7.0 × 4), which is the sum of the capacities,
corresponds to "32.5 or more and less than 47.5" in the table in FIG. 6, the first
value Kc is set to 1.6 m.
[0070] The first value Kd corresponding to the refrigerant flow path switching device 130D
is determined to be a value corresponding to the sum of the capacities of a total
of four indoor units 120 connected to the refrigerant flow path switching device 130D.
Since 28.0 kw (= 7.0 × 4), which is the sum of the capacities, corresponds to "21.0
or more and less than 32.5" in the table in FIG. 6, the first value Kd is set to 0.7
m.
(Second refrigerant flow path switching device group)
[0071] As illustrated in FIG. 4 and FIG. 5, in the refrigerant flow path switching devices
130E to 130G of the second refrigerant flow path switching device group G2 connected
to each other in series, maximum pipe lengths L4, L5, and L6, which are pipe lengths
from the outdoor unit 110 to the indoor units 120 connected to the refrigerant flow
path switching device 130G located on the most downstream side via the high and low-pressure
gas connection pipe 13, the suction gas connection pipe 12, and the liquid connection
pipe 11, respectively, are set by using similar calculation formulas to the maximum
pipe lengths L1, L2, and L3.
[0072] In the refrigerant flow path switching devices 130E and 130H of the second refrigerant
flow path switching device group G2 connected to each other in series, maximum pipe
lengths L7, L8, and L9, which are pipe lengths from the outdoor unit 110 to the indoor
units 120 connected to the refrigerant flow path switching device 130H located on
the most downstream side via the high and low-pressure gas connection pipe 13, the
suction gas connection pipe 12, and the liquid connection pipe 11, respectively, are
set by using similar calculation formulas to the maximum pipe lengths L1, L2, and
L3.
[0073] However, when the maximum pipe lengths L4 to L9 are set, the first value Ke used
as the length of each of the header pipes 55, 56, and 57 of the refrigerant flow path
switching device 130E is determined in accordance with the sum of the capabilities
of the plurality of indoor units 120 connected to the refrigerant flow path switching
device 130E and all the refrigerant flow path switching devices 130F, 130G, and 130H
located downstream of the refrigerant flow path switching device 130E.
[Setting of pipe diameters of connecting pipes]
(First refrigerant flow path switching device group)
[0074] As shown in FIG. 4 and FIG. 5, in the first refrigerant flow path switching device
group G1, pipe diameters of the first connecting pipes 141, 142, and 143 connecting
the refrigerant flow path switching devices 130A to 130D to each other in series are
set in accordance with the sum of the capabilities of the plurality of indoor units
120 connected to the refrigerant flow path switching devices 130 located downstream
of the first connecting pipes 141, 142, and 143.
[0075] Specifically, pipe diameters d11, d12, and d13 of the first connecting pipes 141,
142, and 143 connecting the adjacent refrigerant flow path switching devices 130A
and 130B to each other are set in accordance with the sum of the capabilities of the
plurality of indoor units 120 connected to the refrigerant flow path switching devices
130B, 130C, and 130D located downstream of the first connecting pipes 141, 142, and
143.
[0076] Pipe diameters d14, d15, and d16 of the first connecting pipes 141, 142, and 143
connecting the adjacent refrigerant flow path switching devices 130B and 130C to each
other are set in accordance with the sum of the capabilities of the plurality of indoor
units 120 connected to the refrigerant flow path switching devices 130C and 130D located
downstream of the first connecting pipes 141, 142, and 143.
[0077] Pipe diameters d17, d18, and d19 of the first connecting pipes 141, 142, and 143
connecting the adjacent refrigerant flow path switching devices 130C and 130D to each
other are set in accordance with the sum of the capabilities of the plurality of indoor
units 120 connected to the refrigerant flow path switching device 130D located downstream
of the first connecting pipes 141, 142, and 143.
[0078] In the present embodiment, when the pipe diameters d11 to d13, d14 to d16, and d17
to d19 are determined, for example, the capacity of the indoor unit 120 is used as
the capability of the indoor unit 120. The pipe diameters d11 to d13, d14 to d16,
and d17 to d19 are set to smaller values as the sum of the capacities (capabilities)
of the indoor units 120 decreases. As the capability of the indoor unit 120, power
consumption of the indoor unit 120 or the like may be used in addition to the capacity
of the indoor unit 120.
[0079] In the refrigerant flow path switching devices 130A to 130D connected in series to
each other, the refrigerant flow path switching device located on the downstream side
has a smaller sum of the capacities of the indoor units 120 connected to the own device
and the refrigerant flow path switching device located on the downstream side. Therefore,
the pipe diameters d11 to d13 are set to smaller values than the pipe diameters d14
to d16, and the pipe diameters d14 to d16 are set to smaller values than the pipe
diameters d17 to d19.
(Second refrigerant flow path switching device group)
[0080] In the second refrigerant flow path switching device group G2, the pipe diameters
d21 to d23 and d24 to d26 of the second connecting pipe 144, 145, and 146 connecting
the refrigerant flow path switching devices 130E to 130G to each other in series are
set by a similar method to the pipe diameters d11 to d13, d14 to d16, and d17 to d19.
[Operation and effects of embodiment]
[0081] In the air conditioning system 1 according to the present embodiment, the maximum
pipe lengths L1 to L3 corresponding to the plurality of refrigerant flow path switching
devices 130A to 130D connected to each other in series can be obtained by subtracting
the first values Ka to Kd and the like from the value of the upper limit length Lu
by formulas (4) to (6). The first values Ka, Kb, Kc, and Kd are determined in accordance
with the sum of the capacities of the indoor units 120 connected to the corresponding
refrigerant flow path switching devices 130A, 130B, 130C, and 130D and the refrigerant
flow path switching devices 130B to 130D, 130C and 130D, and 130D located downstream
of the refrigerant flow path switching devices 130A, 130B, 130C, and 130D. Therefore,
since the first values Ka, Kb, Kc, and Kd are determined as more appropriate pipe
lengths, it is possible to increase the maximum pipe lengths L1 to L3 as compared
with a case where the first values are set as fixed values and the capacities of the
indoor units connected downstream are set to an allowable value at a maximum.
[0082] The maximum pipe lengths L4 to L6 corresponding to the plurality of refrigerant flow
path switching devices 130E to 130G connected to each other in series and the maximum
pipe lengths L7 to L9 corresponding to the plurality of refrigerant flow path switching
devices 130E and 130H connected to each other in series can also be increased similarly
to the maximum pipe lengths L1 to L3.
[0083] The maximum pipe lengths L1 to L3 corresponding to the plurality of refrigerant flow
path switching devices 130A to 130D connected to each other in series are set such
that a value obtained by further adding correction lengths J11 to J13 considering
the pressure loss of the first branch pipes 161 to 163 to the maximum pipe lengths
L1 to L3 is equal to or less than the upper limit length Lu, as shown in formulas
(4) to (6). As a result, the maximum pipe lengths L1 to L3 can be set to appropriate
values.
[0084] The maximum pipe lengths L4 to L6 corresponding to the plurality of refrigerant flow
path switching devices 130E to 130G connected to each other in series and the maximum
pipe lengths L7 to L9 corresponding to the plurality of refrigerant flow path switching
devices 130E and 130H connected to each other in series can also be set to appropriate
values similarly to the maximum pipe lengths L1 to L3.
[0085] In the plurality of refrigerant flow path switching devices 130A to 130D connected
to each other in series, the pipe diameters d11 to d13, d14 to d16, and d17 to d19
of the first connecting pipes 141 to 143 connecting the adjacent refrigerant flow
path switching devices 130 to each other are set in accordance with the sum of the
capabilities of the indoor units 120 connected to the refrigerant flow path switching
devices 130 located downstream of the first connecting pipes 141 to 143. Thus, the
pipe diameters d11 to d13, d14 to d16, and d17 to d19 of the first connecting pipe
141 to 143 can be set to appropriate values. As a result, it is possible to avoid
such an event that oil cannot be returned during an oil return operation due to the
pipe diameters d11 to d13, d14 to d16, and d17 to d19 being excessively thick, or
that the pressure loss increases due to the pipe diameters d11 to d13, d14 to d16,
and d17 to d19 being excessively thin.
[0086] As for pipe diameters d21 to d23 and d24 to d26 of the second connecting pipe 144
to 146, similarly to the pipe diameters d11 to d13 and the like of the first connecting
pipe 141 to 143, it is possible to avoid such an event that the oil cannot be returned
or the pressure loss increases during the oil return operation.
[Another exemplary connection of refrigerant flow path switching device]
[0087] FIG. 7 is a pipe system diagram illustrating another exemplary connection of the
refrigerant flow path switching device in the air conditioning system.
[0088] In FIG. 7, the air conditioning system 100 includes one refrigerant flow path switching
device 130 (hereinafter, referred to as a refrigerant flow path switching device 130I)
connected to the outdoor unit 110.
[0089] One end of each of fourth on-site pipes (external pipes) 181, 182, and 183 is connected
to each of upstream ends of the first header pipe 55, the second header pipe 56, and
the third header pipe 57 of the refrigerant flow path switching device 130I. The other
end of each of the fourth on-site pipe 181, 182, and 183 is directly connected to
the high and low-pressure gas connection pipe 13, the suction gas connection pipe
12, and the liquid connection pipe 11 extending from the outdoor unit 110. The closing
pipes 171, 172, and 173 are connected to each of downstream ends of the first header
pipe 55, the second header pipe 56, and the third header pipe 57 of the refrigerant
flow path switching device 130I.
[0090] A pipe length L 110 from the outdoor unit 110 to each indoor unit 120 connected to
the refrigerant flow path switching device 130I via the high and low-pressure gas
connection pipe 13 can be calculated by the following formula (7).

[0091] L11 is a length of the high and low-pressure gas connection pipe 13. L111 is a length
of the fourth on-site pipe 181.
[0092] A pipe length L120 from the outdoor unit 110 to each indoor unit 120 connected to
the refrigerant flow path switching device 130I via the suction gas connection pipe
12 can be calculated by the following formula (8).

[0093] L21 is a length of the suction gas connection pipe 12. L121 is a length of the fourth
on-site pipe 182.
[0094] A pipe length L130 from the outdoor unit 110 to each indoor unit 120 connected to
the refrigerant flow path switching device 130I via the liquid connection pipe 11
can be calculated by the following formula (9).

[0095] L31 is a length of the liquid connection pipe 11. L131 is a length of the fourth
on-site pipe 183.
[0096] Each of the maximum pipe lengths L110, L120, and L130 is set to be equal to or less
than the upper limit length Lu. At this time, the pipe lengths L110, L120, and L130
are set so as to satisfy the following formulas (10), (11), and (12), respectively,
in consideration of the header pipes 55, 56, and 57 of the refrigerant flow path switching
device 130I.

[0097] Ki is a common value used as a length of the first header pipe 55, a length of the
second header pipe 56, and a length of the third header pipe 57 in the refrigerant
flow path switching device 130I. Ki is determined in consideration of a pressure loss
of the header pipes 55 to 57. Specifically, Ki is a first value determined in accordance
with a sum of capabilities of the plurality of indoor units 120 connected to the refrigerant
flow path switching device 130I.
[0098] Mi is a common value used as a length of the first branch pipe 71, a length of the
second branch pipe 72, and a length of the third branch pipe 73 in the refrigerant
flow path switching device 130I. Mi is a second value determined to be a constant
value (for example, 4.3 m) in consideration of a pressure loss of the branch pipes
71 to 73.
[0099] The first value Ki is determined on the basis of the table in FIG. 6. For example,
when the capacity of each indoor unit 120 connected to the refrigerant flow path switching
device 130I is 3.5 kw, the first value Ki is set to a value corresponding to the sum
of the capacities of a total of four indoor units 120. Since 14.0 kw (= 3.5 × 4),
which is the sum of the capacities, corresponds to "less than 21.0" in the table in
FIG. 6, the first value Ki is set to 0.4 m.
[0100] In the air conditioning system 1 in FIG. 7, the pipe lengths L110, L120, and L130
corresponding to the refrigerant flow path switching device 130I can be obtained by
subtracting the first value Ki or the like from the value of the upper limit length
Lu by formulas (10) to (12). As a result, the smaller the sum of the capacities of
the indoor units 120 connected to the refrigerant flow path switching device 130I,
the smaller the first value Ki. Therefore, the pipe lengths L110, L120, and L130 can
be increased by a decrease in the first value Ki.
[Other modifications]
[0101] The present disclosure is not limited to the above-described embodiment, and various
modifications may be made within the scope of the claims.
[0102] For example, the air conditioning system 100 in FIG. 4 includes the two refrigerant
flow path switching device groups G1 and G2, but may include three or more refrigerant
flow path switching device groups.
[0103] In the pipe system in FIG. 4 and FIG. 5, the maximum pipe length is set such that
the value obtained by adding the first value, the second value, and the correction
length of the branch pipes 161 to 166 to the maximum pipe length is equal to or less
than the upper limit value. However, the maximum pipe length may be set such that
a value obtained by adding at least the first value to the maximum pipe length is
equal to or less than the upper limit value. Similarly, in the pipe system in FIG.
7, the pipe length is set such that the value obtained by adding the first value and
the second value to the pipe length is equal to or less than the upper limit value.
However, the pipe length may be set such that a value obtained by adding at least
the first value to the pipe length is equal to or less than the upper limit value.
[0104] In the pipe system in FIG. 4 and FIG. 5, the first value corresponding to the refrigerant
pipes (header pipe 55 to 57) of the refrigerant flow path switching device 130 is
determined in accordance with the sum of the capabilities of the indoor units 120
connected to all the refrigerant flow path switching devices 130 located downstream
of the refrigerant flow path switching device 130. However, the first value may be
determined in accordance with the sum of the capabilities of the indoor units 120
connected to some of the refrigerant flow path switching devices 130 located downstream
of the refrigerant flow path switching device.
REFERENCE SIGNS LIST
[0105]
1 air conditioning system
11 liquid connection pipe (external pipe)
12 suction gas connection pipe (external pipe)
13 high and low-pressure gas connection pipe (external pipe)
110 outdoor unit
120 indoor unit
130 refrigerant flow path switching device
141 to 143 first connecting pipe (external pipe, connecting pipe)
144 to 146 second connecting pipe (external pipe, connecting pipe)
151 to 153 first on-site pipe (external pipe)
154 to 156 second on-site pipe (external pipe)
157 to 159 third on-site pipe (external pipe)
161 to 163 first branch pipe (external pipe, branch pipe)
164 to 166 second branch pipe (external pipe, branch pipe)
181 to 183 fourth on-site pipe (external pipe)
d11 to d19, d21 to d26 pipe diameter
111 to J13, J21 to J23 correction length
Ka to Ki, Ke' first value
L1 to L9 maximum pipe length
L110, L120, L130 pipe length
Lu upper limit length (upper limit value)