CROSS REFERENCE TO RELATED APPLICATIONS
TECHNICAL FIELD
[0002] The present disclosure relates to the technical field of central heating, in particular
to a pipe network heat storage system based on series connection of a supply main
pipe and a return main pipe in a heating network and a control method thereof.
BACKGROUND
[0003] As an important way of efficient and clean utilization of energy in power and heat
industries, cogeneration of heat and power has become an important method for the
development of thermal power generation in the world, and has been included in key
energy-saving projects and becomes a main way of clean heating in China. In recent
years, the rapid development of new energy power generation has brought severe power
peak regulation requirements to the thermal power generation. However, the operation
way of conventional cogeneration units based on heat and power, in which the electricity
is determined by the heat, has severely restricted the flexible adjustment of thermal
power, resulting in a serious conflict between heat supply and power peak regulation.
[0004] At present, the conventional solution for the low efficiency of the cogeneration
heating system is to increase thermal energy storage equipment(s). The excess heat
can be stored through the heat storage technique when the load of the cogeneration
unit is high, and the heat can be supplied to external device(s) through heat storage
device(s) when the power peak regulation is difficult, thereby replenishing the insufficient
heating capacity of the cogeneration unit caused by the reduced power generation load
and improving the power peak regulation ability of the cogeneration unit. However,
this greatly increases the construction investment cost for enterprises.
[0005] The existing patent "Balance Adjustment Method and Heating System for Heat Storage
and Release in Heat and Hydraulic Network" (Application No.:
CN202110294128.3) discloses that a heating pipe network can be used to store heat, and the huge heating
pipe network is a natural heat storage equipment. If the heating pipe network is used
for heat storage to increase the peak regulation capacity of the cogeneration unit,
huge construction investment costs can be saved with a significant economic benefit.
However, when the number of heat stations in the heating system is too large using
the technology of the existing patent, it shall need to add a large number of heating
network water bypasses, valves and other related facilities, which also increases
the construction investment cost to a certain extent, and at the same time, the control
becomes complicated which makes the precise heating be difficult.
SUMMARY
[0006] Embodiments of the present disclosure provide a pipe network heat storage system
based on series connection of a supply main pipe and a return main pipe in a heating
network and a control method thereof.
[0007] Detailed technical solutions are as follows:
A first aspect of the present disclosure provides a pipe network heat storage system
based on series connection of a supply main pipe and a return main pipe in a heating
network. The pipe network heat storage system comprises a heat supply pipe network
including a heating network initial station, heat station(s), a circulating water
pump, a primary network water return pipe and a primary network water supply pipe,
in which the heating network initial station is communicated with a primary network
of the heat station(s) through the primary network water return pipe and the primary
network water supply pipe, the number of the heat station(s) is n which is not less
than 1, the heating network water is driven by the circulating water pump to flow
among the heating network initial station, the heat station(s), the primary network
water return pipe and the primary network water supply pipe; wherein,
a heating network water bypass is installed between the primary network water supply
pipe and the primary network water return pipe, an adjustment component is arranged
on the heating network water bypass for adjusting the flowrate and pressure of the
heating network water in the heating network water bypass, the adjustment component
comprises a first temperature-pressure-flowrate measuring instrument, a pressure relief
device and a first regulating valve which are arranged on the heating network water
bypass in sequence along the water flow direction, and a pressure measuring instrument
is provided at an upstream position in the water flow direction of the primary network
water return pipe, in which the upstream position is at the connection position between
the heating network water bypass and the primary network water return pipe;
a water outlet regulating valve for adjusting the water supply flowrate of the heating
network water is arranged on a water outlet of the heating network initial station,
and a water inlet regulating valve for adjusting the water return flowrate of the
heating network water is arranged on a water inlet of the heating network initial
station;
when the heat supply pipe network is storing heat, the heating network initial station
is used to increase the heat supply and increase the water supply temperature and/or
water supply flowrate of the heating network water; and when the heat supply pipe
network is releasing heat, the heating network initial station is used to reduce the
heat supply and reduce the water supply temperature and/or water supply flowrate of
the heating network water;
the first regulating valve is used to be in a normally closed state to make the flowrate
of the heating network water in the heating network water bypass be zero when the
heat supply pipe network is not storing or not releasing heat, the first regulating
valve can be adjustably open to make the flowrate of the heating network water in
the heating network water bypass be gradually increased while storing heat, and the
first regulating valve can be adjustably closed to make the flowrate of the heating
network water in the heating network water bypass be gradually decreased while releasing
heat; and,
the pressure relief device is used to reduce the pressure of the heating network water
in the heating network water bypass to match with the pressure measured by the pressure
measuring instrument, and then the heating network water can be returned to the primary
network water return pipe.
[0008] In some embodiments, a second regulating valve and a second temperature-pressure-flowrate
measuring instrument are arranged on a water inlet pipe connecting the heat station(s)
with the primary network water supply pipe, and a third regulating valve and a temperature-pressure
measuring instrument are arranged on a water outlet pipe connecting the heat station(s)
with the primary network water return pipe;
when the heat supply pipe network is storing heat and the water supply temperature
of the heating network water is increased by the heating network initial station,
the second regulating valve and the third regulating valve are used to be adjustably
closed in order to reduce the flowrate of the heating network water entering the heat
station(s) and increase the flowrate of the heating network water entering the heating
network water bypass; and, when the heat supply pipe network is releasing heat and
the water supply temperature of the heating network water is decreased by the heating
network initial station, the second regulating valve and the third regulating valve
are used to be adjustably open in order to increase the flowrate of the heating network
water entering the heat station(s) and reduce the flowrate of the heating network
water entering the heating network water bypass.
[0009] In some embodiments, the pipe network heat storage system further comprises a water
replenishing component including a primary network water replenishing pipe, a water
replenishing pump, a fourth regulating valve and a third temperature-pressure-flowrate
measuring instrument, in which the third temperature-pressure-flowrate measuring instrument,
the water replenishing pump and the fourth regulating valve are arranged on the primary
network water replenishing pipe in sequence along the water flow direction, and the
primary network water replenishingpipe is connected to the primary network water return
pipe;
a fourth temperature-pressure-flowrate measuring instrument is provided at an upstream
position in the water flow direction of the primary network water return pipe, in
which the upstream position is at the connection position between the primary network
make-up water pipe and the primary network water return pipe; and, the fourth regulating
valve is operated to be open when the pressure of the primary network water return
pipe measured by the fourth temperature-pressure-flowrate measuring instrument is
lower than the setting pressure, and the fourth regulating valve is operated to be
closed when the pressure of the primary network water return pipe measured by fourth
temperature-pressure-flowrate measuring instrument is not lower than the setting pressure;
and,
a fifth temperature-pressure-flowrate measuring instrument is provided at a water
outlet of the heating network initial station.
[0010] In some embodiments, the heating network water bypass is arranged at the j
th heat station, in which 1≤j≤n, and the pressure measuring instrument is arranged on
the primary network water return pipe connecting to the j
th heat station.
[0011] In some embodiments, the heating network water bypass is arranged at the j
th heat station, and number j represented in the j
th heat station can be calculated as follows:
the maximum heating network water flowrate Gr of the heat supply pipe network can be determined according to the design flowrate
G0 (unit: t/h) of the circulating water pump: Gr = G0;
the minimum storage heat Qmin (unit: GJ) required by the heat supply pipe network can be determined according to
the heat storage required by the cogeneration unit for power peak regulation;
the minimum heating network water flowrate

(unit: t/h, 1≤i≤n) required by each heat station during the heating period can be
determined according to the maximum heating load Wi (unit: GJ/h, 1≤i≤n) required by each heat station during the heating period and the maximum temperature
difference between the heating network water supply temperature and water return temperature
of the heat supply pipe network, and the water supply temperature and the water return
temperature can be respectively indicated as T01 ( unit: °C) and T02 (unit: °C):


;
the maximum heating network water flowrate Gs of the heat supply pipe network used for heat storage in the heating period can determined
according to the minimum heating network water flowrate

required by each heat station during the heating period and the maximum heating network
water flowrate Gr of the heat supply pipe network:

;
the maximum value Amax of number j can be determined according to the design head H0 (unit: m) of the circulating water pump and the resistance loss of different pipe
sections used to connect the heat supply pipe network with each heat station during
the heating period;
the minimum value B min of number j can be determined according to the minimum heat storage required by the
heat supply pipe network; and,
the final value of number j can be determined according to the following relationship:
when Bmin ≥ Amax, the final value of number j is Amax; and,
when B min < Amax, the final value of number j is Amax if the heat dissipation loss rate and water leakage loss rate of the heat power pipe
network can be ignored, and the final value of number j is Bmin if the heat dissipation loss rate and water leakage loss rate of the heat supply
pipe network can not be ignored.
[0012] In some embodiments, the maximum value A
max of number j can be determined according to the design head H
0 (unit: m) of the circulating water pump and the resistance loss of different pipe
sections used to connect the heat supply pipe network with each heat station during
the heating period, and the maximum value A
max can be calculated as follows:
calculating the heating network water flowrate

in different pipe sections connecting each heat station by the following equations:

calculating the resistance loss Rx (unit: Palm) in different pipe sections connecting each heat station by the following
equation:

and calculating the total pressure drop of the heat supply pipe network during the
heating period by the following equations:

and, then the design head H0 of the circulating water pump is compared with the total pressure drop of the heat
supply pipe network during the heating period, and the maximum value Amax of number j can be determined according to the relationship: 10×H0≥0.002×Pz;
in which: the design head H0 of the circulating water pump is a known parameter; K (unit: m) is the equivalent
absolute roughness of the heat supply pipe network; ϕ (unit: %) is the local resistance
equivalent length percentage of the heat supply pipe network; Li (unit: m, 1≤i≤n) is the length of each pipe section connecting each heat station
to the heat supply pipe network; Di (unit: m, 1≤i≤n) is the diameter of each pipe section connecting each heat station
to the heat supply pipe network; and, ρ (unit: kg/m3) is the density of the heating network water.
[0013] In some embodiments, the minimum value B
min of number j can be determined according to the minimum heat storage required by the
heat supply pipe network, and the minimum value B
min can be calculated as follows:
calculating the design heat storage of the heat supply pipe network by the following
equation:

and, the minimum value B min of number j can be determined according to the relationship Qe≥Qmin; in which: ρ (unit: kg/m3) is the density of the heat supply network water; and, C (unit: J/(kg · °C)) is specific
heat capacity of the heat supply network water.
[0014] A second aspect of the present disclosure provides a pipe network heat storage control
method based on series connection of a supply main pipe and a return main pipe in
a heating network. The control method uses any one of the aforementioned pipe network
heat storage system and comprises the following steps:
when the heat supply pipe network is not storing or not releasing heat, the first
regulating valve is used to be in a normally closed state to make the flowrate of
the heating network water in the heating network water bypass be zero, the heating
network water from the heating network initial station is transported to the heat
station(s) through the primary network water supply pipe, and then the heating network
water is returned to the heating network initial station through the primary network
water return pipe in a continuous cycle;
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station is increased and the water supply temperature and/or water
supply flowrate of the heating network water is increased, the first regulating valve
can be adjustably open to make the flowrate of the heating network water in the heating
network water bypass be gradually increased; and, the pressure relief device is used
to reduce the pressure of the heating network water in the heating network water bypass
to match with the pressure measured by the pressure measuring instrument, and then
the heating network water can be returned to the heating network initial station through
the primary network water return pipe; and,
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station is decreased and the water supply temperature and/or water
supply flowrate of the heating network water is decreased, the first regulating valve
can be adjustably closed to make the flowrate of the heating network water in the
heating network water bypass be gradually decreased.
[0015] In some embodiments, the second regulating valve and the second temperature-pressure-flowrate
measuring instrument are arranged on a water inlet pipe connecting the heat station(s)
with the primary network water supply pipe, and the third regulating valve and the
temperature-pressure measuring instrument are arranged on a water outlet pipe connecting
the heat station(s) with the primary network water return pipe;
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station is increased and the water supply temperature of the heating
network water is increased, the second regulating valve and the third regulating valve
are used to be adjustably closed in order to reduce the flowrate of the heating network
water entering the heat station(s) and increase the flowrate of the heating network
water entering the heating network water bypass; and,
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station is decreased and the water supply temperature of the heating
network water is decreased, the second regulating valve and the third regulating valve
are used to be adjustably open in order to increase the flowrate of the heating network
water entering the heat station(s) and reduce the flowrate of the heating network
water entering the heating network water bypass.
[0016] In some embodiments, the control method further comprises a water replenishing step:
the pipe network heat storage system comprises the water replenishing component including
the primary network water replenishing pipe, the water replenishing pump, the fourth
regulating valve and the third temperature-pressure-flowrate measuring instrument,
in which the third temperature-pressure-flowrate measuring instrument, the water replenishing
pump and the fourth regulating valve are arranged on the primary network water replenishing
pipe in sequence along the water flow direction, the primary network water replenishing
pipe is connected to the primary network water return pipe, and the fourth temperature-pressure-flowrate
measuring instrument is provided at an upstream position in the water flow direction
of the primary network water return pipe, in which the upstream position is at the
connection position between the primary network water replenishing pipe and the primary
network water return pipe; and
according to a pressure value measured by the fourth temperature-pressure-flowrate
measuring instrument, the fourth regulating valve is operated to be open when the
pressure of the primary network water return pipe is lower than the setting pressure,
and the water replenishing pump replenishes water to the primary network water return
pipe; and, the fourth regulating valve is operated to be closed when the pressure
of the primary network water return pipe is not lower than the setting pressure, and
the water replenishing pump stops replenishing water .
[0017] The present disclosure achieves the following beneficial effects:
the present disclosure provides a pipe network heat storage system and a control method
thereof, which utilizes the heating network water bypass connecting the primary network
water supply pipe with the primary network return water pipe to change the flowrate
and temperature of heating network water through the heat station at an appropriate
time, thereby realizing the function of storing heat by using the pipe network. For
the heating system of the cogeneration unit, the heat storage capacity of the existing
huge heating pipe network can be made full use to increase the peak regulation capacity
of the cogeneration unit and can also save the huge investment cost of new energy
storage devices. At the same time, in the heat storage process, through the heating
network water bypass, part of the heating network water can be directly returned to
the primary network water return pipe without passing through the heat station(s),
which reduces the pressure loss of the heating system and effectively saves the power
consumption of the circulating water pump; and, in the heat storage and release process,
by adjusting the heating network water flowrate in the heating network water bypass,
the heating network water flowrate required by each heat station can be ensured, which
fully exerts the heat storage capacity of the existing heating pipe network and also
effectively guarantees the heating requirement of each heat station.
BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The accompanying drawings described here are provided for further understanding of
the present disclosure, and constitute a part of the present disclosure. The exemplary
embodiments of the present disclosure and illustrations thereof are intended to explain
the present disclosure, but do not constitute inappropriate limitations to the present
disclosure. In the drawings:
FIG. 1 is a schematic diagram of a pipe network heat storage system provided in embodiments
of the invention according to an embodiment of the present disclosure;
Reference numerals:
[0019] 1 - heating network initial station; 11- fourth temperature-pressure-flowrate measuring
instrument; 12 - fifth temperature-pressure-flowrate measuring instrument; 13 - water
outlet regulating valve; 14 - water inlet regulating valve; 2- heat station(s); 21
- second regulating valve; 22 - third regulating valve; 23 - second temperature-pressure-flowrate
measuring instrument; 24 - temperature-pressure measuring instrument; 3 - circulating
water pump;4 - primary network water return pipe; 41 - pressure measuring instrument;
5 - primary network water supply pipe; 6 - heating network water bypass; 61 - first
temperature-pressure-flowrate measuring instrument; 62 - first regulating valve; 63
- pressure relief device; 7 - primary network water replenishing pipe; 71 - water
replenishing pump; 72 - fourth regulating valve; 73 - third temperature-pressure-flowrate
measuring instrument.
DETAILED DESCRIPTION
[0020] To make the objectives, technical solutions, and advantages of the present disclosure
clearer, the present disclosure is described below with reference to the accompanying
drawings and embodiments. It should be understood that the embodiments described herein
are merely used to explain the present disclosure, rather than to limit the present
disclosure. All other embodiments obtained by those of ordinary skill in the art based
on the embodiments of the present disclosure without creative efforts should fall
within the protection scope of the present disclosure.
[0021] Apparently, the accompanying drawings in the following description show merely some
embodiments of the present disclosure, and a person of ordinary skill in the art may
apply the present disclosure to other similar scenarios according to these drawings
without creative efforts. In addition, it can also be appreciated that, although it
may take enduring and complex efforts to achieve such a development process, for those
of ordinary skill in the art related to the present disclosure, some changes such
as design, manufacturing or production made based on the technical content in the
present disclosure are merely regular technical means, and should not be construed
as insufficiency of the present disclosure.
[0022] The "embodiment" mentioned in the present disclosure means that a specific feature,
structure, or characteristic described in combination with the embodiment may be included
in at least one embodiment of the present disclosure. The phrase appearing in different
parts of the specification does not necessarily refer to the same embodiment or an
independent or alternative embodiment exclusive of other embodiments. It may be explicitly
or implicitly appreciated by those of ordinary skill in the art that the embodiment
described herein may be combined with other embodiments as long as no conflict occurs.
[0023] Unless otherwise defined, the technical or scientific terms used in the present disclosure
are as they are usually understood by those of ordinary skill in the art to which
the present disclosure pertains. The terms "one", "a", "the" and similar words are
not meant to be limiting, and may represent a singular form or a plural form. The
terms "include", "contain", "have" and any other variants in the present disclosure
mean to cover the non-exclusive inclusion, for example, a process, method, system,
product, or device that includes a series of steps or modules (units) is not necessarily
limited to those steps or units which are clearly listed, but may include other steps
or units which are not expressly listed or inherent to such a process, method, system,
product, or device. The term "multiple" in the present disclosure means two or more.
The term "and/or" describes associations between associated objects, and it indicates
three types of relationships. For example, "A and/or B" may indicate that A exists
alone, A and B coexist, or B exists alone. The character "/" generally indicates that
the associated objects are in an "or" relationship.
[0024] The terms "center", "upper", "lower", "left", "right", "vertical", "horizontal",
"inner", "outer" and so on in the present disclosure are intended to indicate orientation
or positional relationship shown in the accompanying drawings, which is only for describing
the present disclosure and simplifying the description, rather than indicating or
implying the device or element with a specific orientation, a specific construction
or a specific operation, and therefore should not be construed as limiting the present
disclosure. The terms "first", "second", "third" and so on in the present disclosure
are intended to distinguish between similar objects but do not necessarily indicate
a specific order of the objects.
[0025] The terms "installed", "communicated", "interconnected", "coupled" and similar words
in the present disclosure are not restricted to physical or mechanical connections,
but may include electrical connections, whether direct or indirect. The terms should
be understood in a broad sense, unless otherwise expressly specified and limited,
for example, it may be a fixed connection or a detachable connection, or integral
connection; can be mechanical connection, can also be electrical connection; can be
directly connected, can also be indirectly connected through an intermediate medium,
can be internal communication between two elements. For those of ordinary skill in
the art, the specific meanings of the above terms in the present invention can be
understood in specific situations.
[0026] Referring to FIG. 1, an embodiment of the present disclosure provides a pipe network
heat storage system based on series connection of a supply main pipe and a return
main pipe in a heating network. The pipe network heat storage system comprises a heat
supply pipe network where the heating network water flows. The heat supply pipe network
includes a heating network initial station 1, heat station(s) 2, a circulating water
pump 3, a primary network water return pipe 4 and a primary network water supply pipe
5, in which the heating network initial station 1 is communicated with a primary network
of the heat station(s) 2 through the primary network water return pipe 4 and the primary
network water supply pipe 5. The number of the heat station(s) 2 is n which is not
less than 1. The heating network water is driven by the circulating water pump 3 to
flow among the heating network initial station 1, the heat station(s) 2, the primary
network water return pipe 4 and the primary network water supply pipe 5.
[0027] Specifically, the heating network initial station 1 is used to provide heat, and
the circulating water pump 3 is used to drive the heating network water to flow in
the heating network. The primary network water supply pipe 5 is connected with the
heating network initial station 1 and a water inlet of the heat station(s) 2, and
the high-pressure and high-temperature heating network water can be transported to
the heat station(s) 2 through the primary network water supply pipe 5. The primary
network return pipe 4 is connected with a water outlet of the heat station(s) 2 and
the heating network initial station 1, and the cooled and depressurized heating network
water can be transported back to the heating network initial station 1 through the
primary network return pipe 4. The heating network water can be pressured and driven
to enter the heating network initial station 1 by the circulating water pump 3, and
then can be heated and transported back to the heat station(s) 2 for circulation.
[0028] For a cogeneration heating system, the huge heat supply pipe network is used as a
natural heat storage equipment. While the heat storage capacity of heat supply pipe
network is achieved by increasing the water supply temperature of the heating network
initial station 1, since the total heat output by the heating network initial station
1 is increased by the increasing the water supply temperature, the heating network
water output by the heating network initial station 1 can only pass through the heat
station(s) 2 for heat exchange and then can be returned to the heating network initial
station 1. After the excess heat supplied by the heating network initial station 1
enters the heat station(s) 2, most of the heat is absorbed by the heat station(s)
2 and then supplied to outside, instead of being stored in heat supply pipe network,
which causes the excessive heat supply of the heat station(s) 2 resulting in energy
waste.
[0029] Thus, in one preferred embodiment, a heating network water bypass 6 is installed
between the primary network water supply pipe 5 and the primary network water return
pipe 4. An adjustment component is arranged on the heating network water bypass 6
for adjusting the flowrate and pressure of the heating network water in the heating
network water bypass 6. By setting the heating network water bypass 6, the excess
heat output by the heating network initial station 1 is no longer transferred to the
heat station(s) 2, instead to be transferred to the primary network water return pipe
4 through the heating network water bypass 6, so as to realize that the excess heat
output by the heating network initial station 1 can be stored in the primary network
water supply pipe 5 and the primary network return water pipe 4, which well exerts
a heat storage capacity of heat supply pipe network.
[0030] Specifically, the adjustment component comprises a first temperature-pressure-flowrate
measuring instrument 61, a pressure relief device 63 and a first regulating valve
62 which are arranged on the heating network water bypass 6 in sequence along the
water flow direction. The first temperature-pressure-flowrate measuring instrument
61 is used to measure the temperature, pressure and flowrate of the heating network
water flowing into the heating network water bypass 6, thus the heat of the heating
network water passing through the heating network water bypass 6 can be calculated.
The first regulating valve 62 is used to adjust the flowrate of the heating network
water in the heating network water bypass 6. The first regulating valve 62 is used
to be in a normally closed state to make the flowrate of the heating network water
in the heating network water bypass 6 be zero when the heat supply pipe network is
not storing or not releasing heat, the first regulating valve 62 can be adjustably
open to make the flowrate of the heating network water in the heating network water
bypass 6 be gradually increased while storing heat, and the first regulating valve
62 can be adjustably closed to make the flowrate of the heating network water in the
heating network water bypass 6 be gradually decreased while releasing heat. The control
method of an opening degree of the first regulating valve 62 is as follows: the heat
passing through the heating network water bypass 6 is equal to a value which is a
heat difference between the heat supplied by the heating network initial station 1
and the heat flowing into each heat station 2. The opening degree of the first regulating
valve 62 can be adjusted according to the required heat passing through the heating
network water bypass 6. The heat supplied by the heating network initial station 1
and the heat required by each heat station 2 are both known parameters. While storing
heat, the opening degree of the first regulating valve 62 can be increased so as to
increase the flowrate of the heating network water flowing through the heating network
water bypass 6. When the flowrate of the heating network water in the heating network
water bypass 6 is needed as a maximum set value, the first regulating valve 62 can
be fully opened. While releasing heat, the opening degree of the first regulating
valve 62 can be reduced. If the heat stored in heat supply pipe network is needed
to be completely released, the opening degree of the first regulating valve 62 can
be adjusted to a minimum opening degree, and the first regulating valve 62 can be
completely closed, so that the flowrate of the heating network water in the heating
network water bypass 6 can be reduced until to be zero. If there is no need to completely
release the heat stored in heat supply pipe network, the opening degree of the first
regulating valve 62 can be appropriately reduced so as to reduce the flowrate of the
heating network water in the heating network water bypass 6 to a set value.
[0031] In one preferred embodiment, a pressure measuring instrument 41 is provided at an
upstream position in the water flow direction of the primary network water return
pipe 4, in which the upstream position is at the connection position between the heating
network water bypass 6 and the primary network water return pipe 4. The pressure measuring
instrument 41 is used to measure the pressure of the heating network water in the
primary network water return pipe 4. The pressure relief device 63 is used to reduce
the pressure of the heating network water in the heating network water bypass 6, thus
the pressure of the high-temperature and high-pressure heating network water can be
decreased to match with the pressure measured by the pressure measuring instrument
41, so that the heating network water can be smoothly returned to the primary network
water return pipe 4 and then can be returned to the heating network initial station
1. The pressure relief device 63 includes a throttle pressure reducing valve, an ejector
pressure reducer and so on.
[0032] In any one of the aforementioned embodiments, a pipe network heat storage control
method comprises the following steps:
when the heat supply pipe network is not storing or not releasing heat, the first
regulating valve 62 is used to be in a normally closed state to make the flowrate
of the heating network water in the heating network water bypass 6 be zero, the heating
network water from the heating network initial station 1 is transported to the heat
station(s) 2 through the primary network water supply pipe 5, and then the heating
network water is returned to the heating network initial station 1 through the primary
network water return pipe 4 in a continuous cycle;
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station 1 is increased, which can achieved by increasing the water
supply temperature of the heating network water, increasing the water supply flowrate
of the heating network water, or both; the first regulating valve 62 can be adjustably
open to make the flowrate of the heating network water in the heating network water
bypass 6 be gradually increased; and, specifically, if the heat supply of the heating
network initial station 1 is increased only by increasing the water supply temperature
of the heating network water, it is necessary to reduce the flowrate of the heating
network water entering the heat station(s) 2 and increase the flowrate of the heating
network water flowing through the heating network water bypass 6; if the heat supply
of the heating network initial station 1 is increased only by increasing the water
supply flowrate of the heating network water, it is unnecessary to change the flowrate
of the heating network water entering the heat station(s) 2, and the increased water
supply flowrate of the heating network water can be returned to the heating network
initial station 1 through the heating network water bypass 6; and, if the water supply
temperature and water supply flowrate of the heating network water are both increased,
it is necessary to reduce the flowrate of the heating network water entering the heat
station(s) 2 and increase the flowrate of the heating network water flowing through
the heating network water bypass 6;
the heating network water flowing through the heating network water bypass 6 is the
water with a high temperature and a high pressure; and, the pressure relief device
63 is used to reduce the pressure of the heating network water in the heating network
water bypass 6 to match with the pressure measured by the pressure measuring instrument
41, and then the heating network water can be returned to the heating network initial
station 1 through the primary network water return pipe 4; and,
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station 1 is decreased, which can achieved by reducing the water supply
temperature of the heating network water, reducing the water supply flowrate of the
heating network, or both; the first regulating valve 62 can be adjustably closed to
make the flowrate of the heating network water in the heating network water bypass
6 be gradually decreased; and, specifically, if the heat supply of the heating network
initial station 1 is decreased only by reducing the water supply temperature of the
heating network water, it is necessary to increase the flowrate of the heating network
water entering the heat station(s) 2 and reduce the flowrate of the heating network
water flowing through the heating network water bypass 6, and the opening degree of
the first regulation valve 62 can be gradually decreased; if the heat supply of the
heating network initial station 1 is decreased only by decreasing the water supply
flowrate of the heating network water, it is unnecessary to change the flowrate of
the heating network water entering the heat station(s) 2, the flowrate of the heating
network water flowing through the heating network water bypass 6 can be gradually
decreased, and the opening degree of the first regulating valve 62 can be gradually
decreased; and, if the water supply temperature and water supply flowrate of the heating
network water are both decreased, it is necessary to increase the flowrate of the
heating network water entering the heat station(s) 2 and reduce the flowrate of the
heating network water flowing through the heating network water bypass 6, and the
opening degree of the first regulating valve 62 can be gradually reduced.
[0033] Heat storage in heat supply pipe network means that when the cogeneration unit needs
to reduce its output capacity in the power grid peak regulation process, the output
capacity can be reduced by increasing the heating extraction steam flowrate of the
cogeneration unit. The excess heat generated by the increased extraction steam flowrate
of the cogeneration unit is stored by the pipe network heating system. Due to the
increased extraction steam flowrate of the cogeneration unit, the heat supply of the
heating network initial station 1 can be increased. If the hearing network water bypass
6 is not provided, the excess heat will be transported the to outside from the heat
station(s) 2, resulting in waste.
[0034] As an example, the heat supply of the heating network initial station 1 is increased
only by increasing the water supply temperature of the heating network water. In this
embodiment, when heat storage is required in the pipe network heating system, the
first regulating valve 62 is controlled to be adjustably open, thus part of the heating
network water in the primary network water supply pipe 5 does not flow into the heat
station(s) 2 and can be directly returned to the primary network water return pipe
4 through the heating network water bypass 6, and the other part of the heating network
water continues to flow through the heat station(s) 2. The water flowrate of the heating
network water flowing through the heating network water bypass 6 can be determined
by the heat value difference between the total heat supply of the heating network
initial station 1 (heat = flowrate × temperature difference × specific heat capacity
as shown in below related equation) and the heat required by each heat station 2.
In this case, the heat supply increased in the heating network initial station 1 can
be stored among the primary network water return pipe 4, the heating network water
bypass 6 and the primary network water supply pipe 5, and the heating network water
corresponding to the increased heat supply can flow between the primary network water
return pipe 4 and the primary network water supply pipe 5 to avoid waste. At the same
time, as the temperature of the heating network water is increased, the heat supply
of the heat station(s) 2 remains unchanged.
[0035] After passing through the heat station(s) 2, the temperature and pressure of the
heating network water in the primary network return pipe 4 are both relatively low.
If the high pressure heating network water in the heating network water bypass 6 directly
flows into the primary network water return pipe 4, it tends to cause uneven pressure,
thereby affecting water return effect and increasing the burden of the circulating
water pump 3. Therefore, in this embodiment, the pressure relief device 63 is provided
on the heating network water bypass 6, and the pressure relief device 63 is used to
reduce the pressure of the high pressure heating network water in the heating network
water bypass 6, thus the pressure can be decreased to match with the pressure of the
heating network water in an upstream position of the primary network water return
pipe 4, in which the upstream position is at the connection position between the primary
network water return pipe 4 and the heating network water bypass 6, so that the water
in the heating network water bypass 6 can normally flow into the primary network water
return pipe 4 and then can be returned to the heating network initial station 1.
[0036] Heat release in heat supply pipe network means that when the cogeneration unit needs
to increase its output capacity in the power grid peak regulation process, the output
capacity can be increased by reducing the heating extraction steam flowrate of the
cogeneration unit. Insufficient heat load caused by the reduced extraction steam flowrate
of the cogeneration unit needs to be satisfied by the release of the stored heat in
the pipe network heating system. As an example, the heat supply of the heating network
initial station 1 is decreased only by reducing the water supply temperature of the
heating network water. When the heat supply is decreased in the heating network initial
station 1, the temperature of the heating network water is decreased, and the first
regulating valve 62 is controlled to be adjustably closed, thus the flowrate of the
heating network water flowing into the heating network water bypass 6 is decreased
and the flowrate of the heating network water entering the heat station(s) 2 is increased,
thus ensuring the heating load balance of the heat station(s) 2. In this case, it
is necessary to combine the peak regulation demand of the cogeneration unit and the
heat storage of heat supply pipe network to determine if the heat release process
can be finished or not. If the cogeneration unit continues to have a peak regulation
demand to increase the output capacity of the unit, the heat release process of the
heat supply pipe network can be finished until all the heat stored in heat supply
pipe network is released. While the total heat supply of the heating network initial
station 1 is equal to the total heat required by the heat station(s) 2, the first
regulating valve 62 is completely closed. If there is still some heat stored in the
pipe network heating system and there is a peak regulation demand to reduce the output
capacity of the cogeneration unit, it is necessary to finish the heat release process
of the heat supply pipe network and start the heat storage process, and at this time,
the opening degree of the first regulating valve 62 can be increased and a new heat
storage process can be started. It is worth noting that no matter whether the heat
stored in the heat pipe network is completely released, according to the peak regulation
demand, the heat release process shall be finished immediately and the heat storage
process shall be started. That is, at the end of the heat release process, the heat
supply pipe network can still have a remained heat store and can also completely release
all the stored heat, according to the specific peak regulation demand.
[0037] The above-mentioned embodiments describe three adjustment methods for changing the
heat supply of the heating network initial station 1. In one example, the flowrate
of the heating network water in the heat station(s) 2 needs to be adjusted when adopting
the adjustment method for changing the water supply temperature of the heating network
water in the heating network initial station 1. Therefore, a second regulating valve
21 and a second temperature-pressure-flowrate measuring instrument 23 are provided
on a water inlet pipe connecting the heat station(s) 2 and the primary network water
supply pipe 5, and a third regulating valve 22 and a temperature-pressure measuring
instrument 24 are provided on a water outlet pipe connecting the heat station(s) 2
and the primary network water return pipe 4. The second regulating valve 21 and the
third regulating valve 22 are used to adjust the flowrate of the heating network water
in the heat station(s) 2 and assist in adjusting the flowrate of the heating network
water flowing through the heating network water bypass 6 at the same time. The second
temperature-pressure-flowrate measuring instrument 23 is used to measure the temperature,
pressure and flowrate of the heating network water entering the heat station(s) 2,
and the temperature-pressure measuring instrument 24 is used to measure the temperature
and pressure of the heating network water from the heat station(s) 2. According to
the total heat supply of the heating network initial station 1 and the heat required
by each heat station 2, the flowrate of the heating network water flowing into the
heat station(s) 2 can be controlled by adjusting the opening degrees of the second
regulating valve 21 and the third regulating valve 22 of each heat station 2. The
second regulating valve 21 and the third regulating valve 22 both use a directly regulated
way so that the heating load balance of the heat station(s) 2 can be easier to be
regulated. The number of the second regulating valve 21, the second temperature-pressure-flowrate
measuring instrument 23, the third regulating valve 22 and the temperature-pressure
measuring instrument 24 matches with the number of the heat station(s) 2 respectively.
If the number of the heat station 2 is n, each number of the second regulating valve
21, the second temperature-pressure-flowrate measuring instrument 23, the third regulating
valve 22 and the temperature-pressure measuring instrument 24 is also n, in which
n is not less than 1.
[0038] Specifically, the second regulating valve 21 and the third regulating valve 22 are
used to be adjustably closed when storing heat, so that the flowrate of the heating
network water entering the heat station(s) 2 is decreased, and the flowrate of the
heating network water flowing through the heating network water bypass 6 is increased.
The second regulating valve 21 and the third regulating valve 22 are used to be adjustably
open when releasing heat, so that the flowrate of the heating network water entering
the heat station(s) 2 is increased, and the flowrate of the heating network water
flowing through the heating network water bypass 6 is decreased. The second temperature-pressure-flowrate
measuring instrument 23 and the temperature-pressure measuring instrument 24 are respectively
provided on the water inlet pipe and the water outlet pipe of the heat station(s)
2. According to the total heat supply of the heating network initial station 1 (specifically
reflected in the temperature and flowrate of the heating network water flowing into
and out of the heating network initial station 1) and the heat required by each heat
station 2 (specifically reflected in the temperature and flowrate of the heating network
water flowing into and out of the heat station(s) 2), the opening degrees of the second
regulating valve 21 and the third regulating valve 22 can be adjusted to ensure the
heating load balance in the heat station(s) 2.
[0039] A specific control method comprises the following steps:
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station 1 is increased and the temperature of the heating network
water is increased, the second regulating valve 21 and the third regulating valve
22 are used to be adjustably closed in order to reduce the flowrate of the heating
network water entering each heat station 2 and increase the flowrate of the heating
network water entering the heating network water bypass 6; and
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station 1 is decreased and the temperature of the heating network
water is decreased, the second regulating valve 21 and the third regulating valve
22 are used to be adjustably open in order to increase the flowrate of the heating
network water entering each heat station(s) 2 and reduce the flowrate of the heating
network water entering the heating network water bypass 6 until it is zero.
[0040] In order to facilitate the regulation of the pipe network heat storage system, in
one preferred embodiment, a water outlet regulating valve 13 for adjusting the water
supply flowrate of the heating network water is arranged on a water outlet of the
heating network initial station 1, and a water inlet regulating valve 14 for adjusting
the water return flowrate of the heating network water is arranged on a water inlet
of the heating network initial station 1. The circulating water pump 3 is arranged
at a position where the primary network water return pipe 4 is close to the water
inlet of the heating network initial station 1. A fifth temperature-pressure-flowrate
measuring instrument 12 is provided at a water outlet of the heating network initial
station 1 for measuring the temperature, pressure and flowrate of the heating network
water from the heating network initial station 1. A fourth temperature-pressure-flowrate
measuring instrument 11 is provided at a water inlet of the heating network initial
station 1 for measuring the temperature, pressure and flowrate of the heating network
water entering the heating network initial station 1.
[0041] All regulating valves in the aforementioned embodiments are electric regulating valves,
and all measuring instruments in the aforementioned embodiments are instruments in
the internet of things, which can perform wireless remote transmission of measurement
data.
[0042] It is worth noting that the adjustably open and adjustably closed state of each regulating
valve in the embodiments means that the opening degree of each regulating valve is
adjusted between fully open and fully closed state. Specifically, the opening degrees
of the second regulating valve 21 and the third regulating valve 22 can be adjusted
according to the heat required by the heat station(s) 2, so as to control the heat
transferring into each heat station 2. The heat of the heating network water bypass
6 is equal to a value which is the heat difference between the heat supply of the
heating network initial first station 1 and the heat required by each heating station
2. According to the heat required by the heating network water bypass 6, the opening
degree of the first regulating valve 62 can be adjusted, in which the first regulating
valve 62 can be fully opened, partially opened or fully closed.
[0043] In one preferred embodiment, the pipe network heat storage system further comprises
a water replenishing component including a primary network water replenishing pipe
7, a water replenishing water pump 71, a fourth regulating valve 72 and a third temperature-pressure-flowrate
measuring instrument 73, in which the third temperature-pressure-flowrate measuring
instrument 73, the water replenishing pump 71 and the fourth regulating valve 72 are
arranged on the primary network make-up water pipe 7 in sequence along the water flow
direction. The primary network make-up water pipe 7 is connected to the primary network
water return pipe 4. The fourth temperature-pressure-flowrate measuring instrument
11 is provided at an upstream position in the water flow direction of the primary
network water return pipe 4, in which the upstream position is at the connection poisiton
between the primary network make-up water pipe 7 and the primary network water return
pipe 4. After the parameter of the heating network water being measured by the fourth
temperature-pressure-flowrate measuring instrument 11, the heating network water flows
through the connection position of the primary network water return pipe 4 and a primary
network make-up water pipe 7. The fourth regulating valve 72 is operated to be open
when the water pressure in the primary network water return pipe 4 measured by the
fourth temperature-pressure-flowrate measuring instrument 11 is lower than a set pressure,
and the fourth regulating valve 72 is operated to be closed when the water pressure
in the primary network water return pipe 4 measured by fourth temperature-pressure-flowrate
measuring instrument 11 is not lower than the set pressure.
[0044] A specific water replenishing step comprises:
according to a pressure value measured by the fourth temperature-pressure-flowrate
measuring instrument 11, the fourth regulating valve 72 is operated to be open when
the water pressure in the primary network water return pipe 4 is lower than the set
pressure, and the water replenishing pump 71 replenishes water to the primary network
water return pipe 4; and, the fourth regulating valve 72 is operated to be closed
when the water pressure in the primary network water return pipe 4 is not lower than
the set pressure, and the water replenishing pump 71 stops replenishing water.
[0045] In one preferred embodiment, the heating network water bypass 6 is arranged at the
j
th heat station 2, in which 1≤j≤n, and the pressure measuring instrument 41 is arranged
on the primary network water return pipe 4 connecting to the j
th heat station 2. In order to improve the heat storage effect of the pipe network,
the location of the heating network water bypass 6 can be optimized. Number j represented
in the j
th heat station can be calculated as follows:
firstly, the maximum heating network water flowrate Gr of the heat supply pipe network can be determined according to the design flowrate
of the circulating water pump 3, and the design flowrate G0 (unit: t/h) is a known parameter, thereby the maximum heating network water flow
is defined as Gr = G0; then the minimum storage heat required by the heat supply pipe network can be determined
according to the heat storage required by the cogeneration unit in the power peak
regulation process, and the minimum storage heat Qmin (unit: GJ) is a known parameter;
secondly, the minimum heating network water flowrate

(unit: t/h, 1≤i≤ n) required by each heat station 2 during the high cold period can
be determined according to the maximum heating load Wi (unit: GJ/h, 1≤i≤n) required by each heat station 2 during the high cold period and
the maximum temperature difference between the heating network water supply temperature
and water return temperature of the heat supply pipe network, and the water supply
temperature and the water return temperature can be respectively indicated as T01 ( unit: °C) and T02 (unit: °C) which are both known preset parameters; the actual temperature measured
by the first temperature-pressure-flowrate measuring instrument 61 and the second
temperature-pressure-flowrate measuring instrument 23 can be adjusted to the preset
parameters accordingly; and, thus the minimum heating network water flowrate

is defined as

;
thirdly, the maximum heating network water flowrate Gs of the heat supply pipe network used for heat storage in the heating period can be
determined according to the minimum heating network water flowrate

required by each heat station 2 in the heating period and the maximum heating network
water flowrate Gr of the heat supply pipe network: Gs = Gr -

;
fourthly, the maximum value Amax of number j can be determined according to the design head H0 (unit: m) of the circulating water pump 3 and the resistance loss of different pipe
sections used to connect the heat supply pipe network with each heat station 2 during
the heating period, in which H0 is the design head of the circulating water pump, K (unit: m) is the equivalent absolute
roughness of the heat supply pipe network, ϕ (unit: %) is the local resistance equivalent
length percentage of the heat supply pipe network, Li (unit: m, 1≤i≤n) is the length of each pipe section connecting each heat station
to the heat supply pipe network, and Di (unit: m, 1≤i≤n) is the diameter of each pipe section connecting each heat station
2 to the heat supply pipe network; and, H0, K, ϕ, Li and Di are all known parameters;
the minimum value Bmin of number j can be determined according to the minimum heat storage required by the
heat supply pipe network; and,
the final value of number j can be determined according to the following relationship:
when Bmin ≥ Amax, the final value of number j is Amax; and,
when Bmin < Amax, the final value of number j is Amax if the heat dissipation loss rate and water leakage loss rate of the heat power pipe
network can be ignored, and the final value of number j is Bmin if the heat dissipation loss rate and water leakage loss rate of the heat supply
pipe network can not be ignored. The heat dissipation loss rate can be calculated
according to the heating network water parameters measured by each measuring instrument,
and the water leakage loss rate can be determined according to the water replenishment
amount of the water replenishing component. When the heat dissipation loss rate and
water leakage loss rate of heat supply pipe network are both less than the advanced
level values in the industry, the heat dissipation loss rate and water leakage loss
rate of heat supply pipe network can be ignored. For example, when the advanced level
values in the industry refer to standard CJJ/T185-2012 , the water leakage loss rate
should not be greater than 0.3%, and the heat dissipation loss rate should not be
greater than 0.1 °C /Km according to the temperature drop along the route.
[0046] In one preferred embodiment, the maximum value A
max of number j can be determined according to the design head H
0 (unit: m) of the circulating water pump 3 and the resistance loss of different pipe
sections used to connect the heat supply pipe network with each heat station 2 during
the heating period, and the maximum value A
max can be calculated as follows:
calculating the heating network water flowrate

in different pipe sections connecting each heat station 2 by the following equations:

calculating the resistance loss Rx (unit: Palm) in different pipe sections connecting each heat station 2 by the following
equation:

calculating the total pressure drop of the heat supply pipe network during the heating
period by the following equation:

and, then comparing the design head H0 of the circulating water pump 3 with the total pressure drop of the heat supply pipe
network during the heating period, and determining the maximum value Amax of number j according to the relationship: 10×H0≥0.002×Pz;
in which the design head H0 of the circulating water pump 3 is a known parameter, K (unit: m) is the equivalent
absolute roughness of the heat supply pipe network, ϕ (unit: %) is the local resistance
equivalent length percentage of the heat supply pipe network, Li (unit: m, 1≤i≤n) is the length of each pipe section connecting each heat station
2 to the heat supply pipe network, Di (unit: m, 1≤i≤n) is the diameter of each pipe section connecting each heat station
2 to the heat supply pipe network and ρ (unit: kg/m3) is the density of the heating network water.
[0047] In one preferred embodiment, the minimum value B
min of number j can be determined according to the minimum heat storage required by the
heat supply pipe network, and the minimum value B
min can be calculated as follows:
calculating the design heat storage of the heat supply pipe network by the following
equation:

and, determining the minimum value Bmin of number j according to the relationship: Qe≥ Qmin, in which ρ (unit: kg/m3) is the density of the heat supply network water and C (unit: J/(kg· °C)) is specific
heat capacity of the heat supply network water.
[0048] Based on the above calculation method, the value of number j can be determined, and
the position of the heating network water bypass 6 can be determined, so as to meet
the use requirements of the pipe network heat storage.
[0049] Those skilled in the art should understand that, the technical features of the above
embodiments can be arbitrarily combined. In an effort to provide a concise description,
not all possible combinations of all the technical features of the embodiments are
described. However, these combinations of technical features should be construed as
disclosed in the description as long as no contradiction occurs.
[0050] The above embodiments are merely illustrative of several implementation manners of
the present disclosure, and the description thereof is more specific and detailed,
but is not to be construed as a limitation to the patentable scope of the present
disclosure. It should be pointed out that several variations and improvements can
be made by those of ordinary skill in the art without departing from the conception
of the present disclosure, but such variations and improvements should fall within
the protection scope of the present disclosure. Therefore, the protection scope of
the present disclosure should be subject to the protection scope defined by the claims.
1. A pipe network heat storage system based on series connection of a supply main pipe
and a return main pipe in a heating network,
characterized in that the pipe network heat storage system comprises a heat supply pipe network including
a heating network initial station (1), heat station(s) (2), a circulating water pump
(3), a primary network water return pipe (4) and a primary network water supply pipe
(5), in which the heating network initial station (1) is communicated with a primary
network of the heat station(s) (2) through the primary network water return pipe (4)
and the primary network water supply pipe (5), the number of the heat station(s) (2)
is n which is not less than 1, the heating network water is driven by the circulating
water pump (3) to flow among the heating network initial station (1), the heat station(s)
(2), the primary network water return pipe (4) and the primary network water supply
pipe (5); wherein,
a heating network water bypass (6) is installed between the primary network water
supply pipe (5) and the primary network water return pipe (4), an adjustment component
is arranged on the heating network water bypass (6) for adjusting the flowrate and
pressure of the heating network water in the heating network water bypass (6), the
adjustment component comprises a first temperature-pressure-flowrate measuring instrument
(61), a pressure relief device (63) and a first regulating valve (62) which are arranged
on the heating network water bypass (6) in sequence along the water flow direction,
and a pressure measuring instrument (41) is provided at an upstream position in the
water flow direction of the primary network water return pipe (4), in which the upstream
position is at the connection position between the heating network water bypass (6)
and the primary network water return pipe (4);
a water outlet regulating valve (13) for adjusting the water supply flowrate of the
heating network water is arranged on a water outlet of the heating network initial
station (1), and a water inlet regulating valve (14) for adjusting a water return
flowrate of the heating network water is arranged on a water inlet of the heating
network initial station (1);
when the heat supply pipe network is storing heat, the heating network initial station
(1) is used to increase the heat supply and increase the water supply temperature
and/or water supply flowrate of the heating network water; and when the heat supply
pipe network is releasing heat, the heating network initial station (1) is used to
reduce the heat supply and reduce the water supply temperature and/or water supply
flowrate of the heating network water;
the first regulating valve (62) is used to be in a normally closed state to make the
flowrate of the heating network water in the heating network water bypass (6) be zero
when the heat supply pipe network is not storing or not releasing heat, the first
regulating valve (62) can be adjustably open to make the flowrate of the heating network
water in the heating network water bypass (6) be gradually increased while storing
heat, and the first regulating valve (62) can be adjustably closed to make the flowrate
of the heating network water in the heating network water bypass (6) be gradually
decreased while releasing heat; and,
the pressure relief device (63) is used to reduce the pressure of the heating network
water in the heating network water bypass (6) to match with the pressure measured
by the pressure measuring instrument (41), and then the heating network water can
be returned to the primary network water return pipe (4).
2. The pipe network heat storage system according to claim 1, wherein
a second regulating valve (21) and a second temperature-pressure-flowrate measuring
instrument (23) are arranged on a water inlet pipe connecting the heat station(s)
(2) with the primary network water supply pipe (5), and a third regulating valve (22)
and a temperature-pressure measuring instrument (24) are arranged on a water outlet
pipe connecting the heat station(s) (2) with the primary network water return pipe
(4); and,
when the heat supply pipe network is storing heat and the water supply temperature
of the heating network water in the heating network initial station (1) is increased,
the second regulating valve (21) and the third regulating valve (22) are used to be
adjustably closed in order to reduce the flowrate of the heating network water entering
the heat station(s) (2) and increase the flowrate of the heating network water entering
the heating network water bypass (6); and, when the heat supply pipe network is releasing
heat and the water supply temperature of the heating network water in the heating
network initial station (1) is decreased, the second regulating valve (21) and the
third regulating valve (22) are used to be adjustably open in order to increase the
flowrate of the heating network water entering the heat station(s) (2) and reduce
the flowrate of the heating network water entering the heating network water bypass
(6).
3. The pipe network heat storage system according to claim 1, wherein the pipe network
heat storage system further comprises a water replenishing component including a primary
network water replenishing pipe (7), a water replenishing pump (71), a fourth regulating
valve (72) and a third temperature-pressure-flowrate measuring instrument (73), in
which the third temperature-pressure-flowrate measuring instrument (73), the water
replenishing pump (71) and the fourth regulating valve (72) are arranged on the primary
network water replenishing pipe (7) in sequence along the water flow direction, and
the primary network water replenishing pipe (7) is connected to the primary network
water return pipe (4);
a fourth temperature-pressure-flowrate measuring instrument (11) is provided at an
upstream position in the water flow direction of the primary network water return
pipe (4), in which the upstream position is at the connection position between the
primary network water replenishing pipe (7) and the primary network water return pipe
(4); and, the fourth regulating valve (72) is operated to be open when the pressure
of the primary network water return pipe (4) measured by the fourth temperature-pressure-flowrate
measuring instrument (11) is lower than a set pressure, and the fourth regulating
valve (72) is operated to be closed when the pressure of the primary network water
return pipe (4) measured by the fourth temperature-pressure-flowrate measuring instrument
(11) is not lower than the set pressure; and,
a fifth temperature-pressure-flowrate measuring instrument (12) is provided at a water
outlet of the heating network initial station (1).
4. The pipe network heat storage system according to claim 1, wherein the heating network
water bypass (6) is arranged at the jth heat station (2), in which 1≤j≤n, and the pressure measuring instrument (41) is arranged
on the primary network water return pipe (4) connecting to the jth heat station (2).
5. The pipe network heat storage system according to claim 4, wherein the heating network
water bypass (6) is arranged at the j
th heat station (2), and number j represented in the j
th heat station (2) can be calculated as follows:
the maximum heating network water flowrate Gr of the heat supply pipe network can be determined according to the design flowrate
G0 (unit: t/h) of the circulating water pump (3): Gr = G0;
the minimum storage heat Qmin (unit: GJ) required by the heat supply pipe network can be determined according to
the heat storage required by the cogeneration unit for power peak regulation;
the minimum heating network water flowrate

(unit: t/h, 1≤i≤n) required by each heat station (2) during the heating period can
be determined according to the maximum heating load Wi (unit: GJ/h, 1≤i≤n) required by each heat station (2) during the heating period and
the maximum temperature difference between the heating network water supply temperature
and water return temperature of the heat supply pipe network, and the water supply
temperature and the water return temperature can be respectively indicated as T01 ( unit: °C) and T02 (unit: °C):

;
the maximum heating network water flowrate Gs of the heat supply pipe network used for heat storage in the heating period can be
determined according to the minimum heating network water flowrate

required by each heat station (2) in the heating period and the maximum heating network
water flowrate Gr of the heat supply pipe network:

;
the maximum value Amax of number j can be determined according to the design head H0 (unit: m) of the circulating water pump (3) and the resistance loss of different
pipe sections used to connect the heat supply pipe network with each heat station
(2) during the heating period;
the minimum value B min of number j can be determined according to the minimum heat storage required by the
heat supply pipe network; and,
the final value of number j can be determined according to the following relationship:
when Bmin ≥ Amax, the final value of number j is Amax; and,
when Bmin<Amax, the final value of number j is Amax if the heat dissipation loss rate and water leakage loss rate of the heat power pipe
network can be ignored, and the final value of number j is Bmin if the heat dissipation loss rate and water leakage loss rate of the heat supply
pipe network can not be ignored.
6. The pipe network heat storage system according to claim 5, wherein the maximum value
A
max of number j can be determined according to the design head H
0 (unit: m) of the circulating water pump (3) and the resistance loss of different
pipe sections used to connect the heat supply pipe network with each heat station
(2) during the heating period, and the maximum value A
max can be calculated as follows:
calculating the heating network water flowrate

in different pipe sections connecting each heat station (2) by the following equations:

calculating the resistance loss Rx (unit: Palm) in different pipe sections connecting each heat station (2) by the following
equation:

calculating the total pressure drop of the heat supply pipe network during the heating
period by the following equations:

and, then comparing the design head H0 of the circulating water pump (3) with the total pressure drop of the heat supply
pipe network during the heating period, and determining the maximum value Amax of number j according to the relationship 10×H0≥0.002×Pz;
in which: the design head H0 of the circulating water pump (3) is a known parameter; K (unit: m) is the equivalent
absolute roughness of the heat supply pipe network; ϕ (unit: %) is the local resistance
equivalent length percentage of the heat supply pipe network; Li (unit: m, 1≤i≤n) is the length of each pipe section connecting each heat station
(2) to the heat supply pipe network; Di (unit: m, 1≤i≤n) is the diameter of each pipe section connecting each heat station
(2) to the heat supply pipe network; and, ρ (unit: kg/m3) is the density of the heating network water.
7. The pipe network heat storage system according to claim 5, wherein the minimum value
B
min of number j can be determined according to the minimum heat storage required by the
heat supply pipe network, and the minimum value B
min can be calculated as follows:
calculating the design heat storage of the heat supply pipe network by the following
equation:

and, determining the minimum value Bmin of number j according to the relationship: Qe≥Qmin; in which: ρ (unit: kg/m3) is the density of the heat supply network water; and, C (unit: J/(kg· °C)) is specific
heat capacity of the heat supply network water.
8. A pipe network heat storage control method based on series connection of a supply
main pipe and a return main pipe in a heating network,
characterized in that the control method uses the pipe network heat storage system as described in any
one of claim 1 to claim 7 and comprises the following steps:
when the heat supply pipe network is not storing or not releasing heat, the first
regulating valve (62) is used to be in a normally closed state to make the flowrate
of the heating network water in the heating network water bypass (6) be zero, the
heating network water from the heating network initial station (1) is transported
to the heat station(s) (2) through the primary network water supply pipe (5), and
then the heating network water is returned to the heating network initial station
(1) through the primary network water return pipe (4) in a continuous cycle;
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station (1) is increased and the water supply temperature and/or water
supply flowrate of the heating network water is increased, the first regulating valve
(62) can be adjustably open to make the flowrate of the heating network water in the
heating network water bypass (6) be gradually increased; and, the pressure relief
device (63) is used to reduce the pressure of the heating network water in the heating
network water bypass (6) to match with the pressure measured by the pressure measuring
instrument (41), and then the heating network water can be returned to the heating
network initial station (1) through the primary network water return pipe (4); and,
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station (1) is decreased and the water supply temperature and/or water
supply flowrate of the heating network water is decreased, the first regulating valve
(62) can be adjustably closed to make the flowrate of the heating network water in
the heating network water bypass (6) be gradually decreased.
9. The pipe network heat storage control method according to claim 8, wherein the second
regulating valve (21) and the second temperature-pressure-flowrate measuring instrument
(23) are arranged on a water inlet pipe connecting the heat station(s) (2) with the
primary network water supply pipe (5), and the third regulating valve (22) and the
temperature-pressure measuring instrument (41) (24) are arranged on a water outlet
pipe connecting the heat station(s) (2) with the primary network water return pipe
(4);
when the heat supply pipe network is storing heat, the heat supply of the heating
network initial station (1) is increased and the water supply temperature of the heating
network water is increased, the second regulating valve (21) and the third regulating
valve (22) are used to be adjustably closed in order to reduce the flowrate of the
heating network water entering the heat station(s) (2) and increase the flowrate of
the heating network water entering the heating network water bypass (6); and,
when the heat supply pipe network is releasing heat, the heat supply of the heating
network initial station (1) is decreased and the water supply temperature of the heating
network water is decreased, the second regulating valve (21) and the third regulating
valve (22) are used to be adjustably open in order to increase the flowrate of the
heating network water entering the heat station(s) (2) and reduce the flowrate of
the heating network water entering the heating network water bypass (6).
10. The pipe network heat storage control method according to claim 8, wherein the control
method further comprises a water replenishing step:
the pipe network heat storage system comprises the water replenishing component including
the primary network water replenishing pipe (7), the water replenishing pump (71),
the fourth regulating valve (72) and the third temperature-pressure-flowrate measuring
instrument (73), in which the third temperature-pressure-flowrate measuring instrument
(73), the water replenishing pump (71) and the fourth regulating valve (72) are arranged
on the primary network water replenishing pipe (7) in sequence along the water flow
direction, the primary network water replenishing pipe (7) is connected to the primary
network water return pipe (4), and the fourth temperature-pressure-flowrate measuring
instrument (11) is provided at an upstream position in the water flow direction of
the primary network water return pipe (4), in which the upstream position is at the
connection position between the primary network water replenishing pipe (7) and the
primary network water return pipe (4); and,
according to a pressure value measured by the fourth temperature-pressure-flowrate
measuring instrument (11), the fourth regulating valve (72) is operated to be open
when the pressure of the primary network water return pipe (4) is lower than the set
pressure, and the water replenishing pump (71) replenishes water to the primary network
water return pipe (4); and, the fourth regulating valve (72) is operated to be closed
when the pressure of the primary network water return pipe (4) is not lower than the
set pressure, and the water replenishing pump (71) stops replenishing water.