Incorporation by Reference
[0001] The present application claims priority from Japanese patent application
JP 2021-55350 filed on March 29, 2021, the content of which is hereby incorporated by reference into this application.
Technical Field
[0002] This invention relates to a crane for hanging and transporting a payload and a method
of controlling the crane.
Background Art
[0003] In recent years, aging of skilled crane operators and increasing installation of
cranes have caused labor shortage; inexperienced and unskilled workers more often
operate cranes. Unskilled workers are especially not good at steadying operation to
suppress sway of the payload (payload sway). Payload sway generates high risks of
accidents such as collision with and press by the payload. Furthermore, it takes a
long time to be stopped, which increases the working time. Accordingly, a technique
for automatically suppressing the payload sway is demanded to increase the safeness
and work efficiency.
[0004] In hoisting a grounded payload, if the horizontal transport device (trolley) carrying
the payload with a rope has a horizontal positional deviation from the payload, the
payload may start pendular movement at the moment when the payload leaves the ground,
causing payload sway (initial sway).
[0005] To reduce this initial sway, a technique is disclosed in Patent Document 1. The existing
technique according to Patent Document 1 winds up the rope into a taut and slackless
state before hoisting the payload, measures the length of the rope in the taut state,
slightly moves the trolley in the direction to reduce the rope length, and repeats
the foregoing operation until the trolley is positioned directly above the payload
where the rope length is minimized and the positional deviation is eliminated. According
to Patent Document 1, the condition to determine that the rope length is minimized
is that the variation in rope length caused by move of the trolley has decreased to
a predetermined small value or the variation in rope length changes from decreasing
to increasing.
CITATION LIST
PATENT DOCUMENT
SUMMARY
PROBLEMS TO BE SOLVED BY THE INVENTION
[0007] Patent Document 1 determines whether the rope length is minimized with its variation.
However, the variation in rope length becomes smaller as the positional deviation
of the trolley from the payload becomes smaller and accordingly, the precision in
detecting the position where the rope length is minimized has a limit, generating
a limit in reducing the positional deviation.
[0008] Furthermore, Patent Document 1 repeats straining the rope by winding up, measuring
the rope length, and slightly moving the trolley and therefore, if the positional
deviation is large, the operation has to be repeated for a large number of times.
It takes a long time (operation time) to move the trolley to directly above the payload.
[0009] This invention is accomplished in view of these problems and aims to provide a crane
and a method of controlling the crane that can hoist a grounded payload sooner by
attaining a smaller horizontal positional deviation of the trolley from the payload
in a shorter operating time of the trolley before the hoisting operation.
Solution to Problem
[0010] One aspect of the present invention is a crane includes a horizontal transport device
horizontally movable with a motor, a hoisting device mounted on the horizontal transport
device, the hoisting device being capable of winding a rope with a hoist motor, a
hook attached on the rope to hang a payload and a control unit including a processor
and a memory, the control unit being configured to control the horizontal transport
device and the hoisting device. The control unit includes a rope tension determination
unit configured to determine whether the rope is in a taut state without a slack;
a state measurement unit configured to measure at least one state value of the crane
when the rope has been wound up into a taut state by the hoisting device being driven
and
a transport control unit configured to move the horizontal transport device. The state
measurement unit is configured to identify a payload location xp of a grounded payload,
using a position x of the horizontal transport device and the at least one state value
measured when the rope is in a taut state, and the transport control unit is configured
to move the horizontal transport device to the identified payload location xp to position
the rope directly above the payload.
EFFECTS OF THE INVENTION
[0011] This invention enables a crane to hoist a grounded payload sooner by attaining a
smaller horizontal positional deviation of a trolley from the payload in a shorter
operating time of the trolley before the hoisting operation.
[0012] The details of at least one embodiment of a subject matter disclosed herein are set
forth in the accompanying drawings and the following description. Other features,
aspects, and effects of the disclosed subject matter become apparent from the following
disclosure, drawings, and claims.
Brief Description of Drawings
[0013]
FIG. 1 illustrates a general configuration of an overhead crane in a first embodiment
of this invention.
FIG. 2 illustrates a configuration of the control device of the crane in the first
embodiment of this invention.
FIG. 3A illustrates the movement of the crane in hoisting a grounded payload in the
first embodiment of this invention.
FIG. 3B illustrates the movement of the crane in hoisting a grounded payload in the
first embodiment of this invention.
FIG. 4 is a flowchart of an example of the control in accordance with an existing
art.
FIG. 5 illustrates the movement of the crane in accordance with the existing art.
FIG. 6 illustrates the relation among the positions of the trolley and the payload
and the rope length in the first embodiment of this invention.
FIG. 7 is a graph representing the relation between the positional deviation D and
the rope length L obtained from Expression in the first embodiment of this invention.
FIG. 8 is a graph representing the relation between the rope length L and the trolly
position x for illustrating the principle of the first embodiment of this invention.
this invention.
FIG. 9 is a diagram illustrating the movement of the crane in the first embodiment
of this invention.
FIG. 10 is a flowchart of an example of processing to be performed in the control
device 100 of the first embodiment of this invention.
FIG. 11 is a flowchart of the details of identifying the payload location in the first
embodiment of this invention.
FIG. 12 illustrates the movement of the crane in a third embodiment of this invention.
FIG. 13 illustrates the movement of the crane in a fourth embodiment of this invention.
FIG. 14 illustrates a configuration of the control device of the crane in the third
and fourth embodiment of this invention.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0014] Hereinafter, embodiments of this invention will be specifically described with reference
to the drawings. However, this invention is not limited to the embodiments and the
scope of this invention includes various modifications and applications within its
technical concept.
EMBODIMENT 1
Configuration and Operation of Crane
[0015] The configuration and operation of a crane 1 in Embodiment 1 of this invention are
described. Throughout the drawings, the same apparatuses (devices and components)
are denoted by the same reference signs and description about already described apparatuses
may be skipped in the subsequent description.
[0016] FIG. 1 illustrates a general configuration of an overhead crane. The crane 1 includes
runways 2 provided along the walls on opposite sides of a building such as a factory
(not shown), a girder 3 that moves on the top sides of the runways 2, and a trolley
4 that moves along the underside of the girder 3.
[0017] The girder 3 and the trolley 4 have wheels (not shown) to be driven by electric motors
(not shown); the girder 3 and the trolley 4 can move with these wheels. The girder
3 travels along the runways 2 and the trolley 4 moves along the underside of the girder
3 transversely (horizontally: leftward and rightward in FIG. 1) between the runways
2.
[0018] The trolley 4 is provided with a hoisting device (hoist) 5. The hoisting device 5
includes a drum (not shown) to be driven by an electric motor; this drum is rotated
to wind or unwind a rope 6, so that a hook 7 at the end of the rope 6 is raised or
lowered.
[0019] A payload 9 is hooked on the hook 7 directly or through wires 8; the payload 9 is
raised and lowered with up and down of the hook 7. The crane 1 can move the payload
9 horizontally by horizontal movement (traveling) of the girder 3 and horizontal movement
(traversing) of the trolley 4 and can move the payload 9 vertically (up and down)
with the hoisting device 5.
[0020] The sling member for hanging the payload 9 from the hook 7 is not limited to the
wires 8; other kinds of slings such as chain and rope can be employed.
[0021] In FIG. 1, the trolley 4 and the girder 3 correspond to horizontal transport devices.
However, at least either one of the trolley 4 and the girder 3 can be referred to
as horizontal transport device; otherwise, the trolley 4 that moves along the girder
3 can be referred to as a first horizontal transport device and the girder 3 that
moves along the runways 2 can be referred to as a second horizontal transport device.
[0022] The hoisting device 5 includes an encoder 5a (see FIG. 2) for detecting the rotation
angle of the drum to measure the length of the rope 6 (rope length) paid out from
the drum.
Control Device
[0023] FIG. 2 illustrates a configuration of the control device of the crane 1 in this embodiment.
For simplicity of description, FIG. 2 illustrates traverse control for the trolley
4 and up and down control for the hoisting device 5 and excludes travel control for
the girder 3.
[0024] FIG. 2 also does not include driving members such as electric motors. The control
device 100 of the crane 1 includes an arithmetic and control unit, a traverse motor
controller 300 for controlling the electric motor (traverse motor) of the trolley
4, a hoist motor controller 310 for controlling the electric motor (hoist motor) of
the hoisting device 5, an operation input device 200, and a display device 210. Although
not shown in FIG. 2, the control device 100 includes a travel motor controller for
controlling the electric motor (travel motor) to drive the girder 3 along the runways
2.
[0025] The control device 100 calculates and outputs speed command values for the trolley
4 and the hoisting device 5 and outputs information to the display device 210, based
on the operation command input through the operation input device 200 and information
acquired from sensors including the encoder 5a (first sensor).
[0026] The arithmetic and control unit in the control device 100 is commonly a general-purpose
computer; it includes a micro-processing unit (MPU) 101 for performing control and
arithmetic operation using installed programs and data, a memory 102 for storing the
programs and data, and an input/output control unit 103 for inputting data and signals
from the external and outputting signals arithmetically processed by the MPU 101 to
the external. The MPU 101, the memory 102, and the input/output control unit 103 are
connected by a bus line 104 for transmitting signals and data.
[0027] The operation input device 200 is connected to an operation terminal 201 to be operated
by the operator of the crane 1. The operation terminal 201 has operation buttons 202
associated with transport directions of the payload: forward, backward, rightward,
leftward, upward, and downward.
[0028] The display device 210 displays information such as the state of the crane 1. The
operation terminal 201 can be connected to the control device 100 with wire or wirelessly.
The display device 210 can be mounted on the same housing as the operation terminal
201.
[0029] The traverse motor controller 300 and the hoist motor controller 310 control the
electric motors of the trolley 4 and the hoisting device 5 in accordance with the
speed command values output from the control device 100. Although FIG. 2 does not
illustrate specific configurations of the traverse motor controller 300 and the hoist
motor controller 310, they can be configured with general-use computers like the control
device 100 or inverter circuits. The traverse motor controller 300 and the hoist motor
controller 310 can be mounted on the same housing as the control device 100.
[0030] Although not shown in FIG. 2, the control device 100 further outputs a speed command
value for the girder 3, in addition to the speed command values for the trolley 4
and hoisting device 5. As for the girder 3, a not-shown electric motor (travel motor)
controller controls an electric motor in accordance with this speed command value.
[0031] The memory 102 includes a rope tension determination unit 21, a state measurement
unit 22, a hoisting control unit 23, and a transport control unit 24, which are programs
loaded and executed by the MPU 101.
[0032] The MPU 101 performs processing in accordance with the programs of function units
to work as the function units for providing predetermined functions. For example,
the MPU 101 performs processing in accordance with the rope tension determination
program to function as the rope tension determination unit 21. The same applies to
the other programs. Furthermore, the MPU 101 works as function units for providing
functions of a plurality of processes executed by a program. A computer and a computer
system are an apparatus and a system including these function units.
[0033] The rope tension determination unit 21 determines whether the rope 6 is in a taut
and slackless state based on the current value of the electric motor of the hoisting
device 5. The state measurement unit 22 measures the state values such as the rope
length and the positions of the trolley 4 and the girder 3 after winding up the rope
6 connected to a grounded payload into a taut state, infers the location of the payload
from the state values, and positions the crane 1 by moving the trolley 4 and the girder
3 so that the rope 6 is positioned directly above the payload 9.
[0034] The transport control unit 24 receives command values from the operation terminal
201 and the payload location from the state measurement unit 22 and drives the trolley
4 and the girder 3 with the traverse motor controller 300 and a not-shown travel motor
controller, respectively, to horizontally move the trolley 4 and the girder 3.
[0035] The hoisting control unit 23 outputs command values to the hoist motor controller
310 in accordance with the command values from the operation terminal 201 and the
state measurement unit 22.
Hoisting Grounded payload
[0036] In hoisting a grounded payload 9, payload sway (initial sway) may occur when the
payload 9 leaves the ground (or the floor). FIGS. 3A and 3B illustrate the movement
of the crane 1 in hoisting a grounded payload 9. If the trolley 4 has a positional
deviation D from the grounded payload 9 in a horizontal direction as illustrated in
FIG. 3A, the payload 9 starts pendular movement with an amplitude D (positional deviation
D) and an angular frequency (g/L)
1/2 (L: the distance from the trolley 4 to the payload 9, g: the acceleration of gravity)
when the rope 6 is wound and the payload 9 leaves the ground as illustrated in FIG.
3B. This is the initial sway.
Existing Art and Issues
[0037] To reduce this initial sway, the horizontal positional deviation of the trolley 4
from the payload 9 when the payload 9 leaves the ground should be reduced and accordingly,
the trolley 4 should be moved to directly above the payload 9 before hoisting the
payload 9. To satisfy this condition, there exists an art disclosed in the aforementioned
Patent Document 1.
[0038] This existing art winds up the rope into a taut and slackless state before hoisting
the payload, measures the length of the rope in the taut state, slightly moves the
trolley in the direction to reduce the rope length, and repeats the foregoing operation
until the trolley is positioned directly above the payload where the rope length is
minimized and the positional deviation is eliminated.
[0039] According to Patent Document 1, the condition to determine that the rope length is
minimized is that the variation in rope length caused by the movement of the trolley
has decreased to a predetermined small value or the variation in rope length changes
from decreasing to increasing.
[0040] FIG. 4 is a flowchart of an example of the control in accordance with an existing
art. The details are as follows. Described here is an example of the control such
that the control device controls the trolley and the hoisting device to transport
a payload.
[0041] The control device first prohibits a hoisting operation (S101). Next, the control
device instructs the hoisting device to wind up the rope into a taut and slackless
state (S102). The control device detects the rope length as a state value ψ with an
encoder attached on the hoisting device (S103).
[0042] At Step S104, the control device performs termination determination based on the
state value ψ. The termination condition is that the variation in rope length is smaller
than a predetermined value or that the rope length changes from decreasing to increasing.
If the termination condition is not satisfied, the control device proceeds to Step
S105 and if satisfied, proceeds to Step S107.
[0043] At Step S105, the control device determines the direction to move the trolley. It
determines the direction to decrease the rope length to be the direction to move (transversally)
the trolley. At Step S106, the control device moves the trolley in the direction determined
by the control device at the foregoing Step S105 by a predetermined distance. After
the trolley has moved, the control device returns to Step S102 and repeats the above-described
processing.
[0044] At Step S107, the control device determines whether the termination condition is
satisfied and the trolley has moved to directly above the payload and permits a hoisting
operation to the operator.
[0045] FIG. 5 illustrates the movement of the crane 1 in accordance with the existing art.
The existing art moves the trolly 4 asymptotically to directly above the payload 9
by repeating straining the rope 6 by winding up, measuring the rope length, and slightly
moving the trolly 4.
[0046] This existing art has raised two issues. One of them is the limit of reducing the
positional deviation because of the precision in detection of the rope length. FIG.
6 illustrates the relation among the positions of the trolley 4 and the payload 9
and the rope length. Letting D be the positional deviation of the trolley 4 from the
payload 9 in a horizontal direction and H be the height from the payload 9 to the
trolley 4, the distance from the trolley 4 to the payload 9 or the length L of the
rope 6 including the length of the wires 8 can be expressed by the following Expression
(1):
[Expression 1]

[0047] FIG. 7 is a graph representing the relation between the positional deviation D and
the rope length L obtained from Expression 1. FIG. 7 indicates that the variation
of the rope length L becomes smaller and the travel distance of the trolley 4 required
to detect variation of the rope length L becomes longer as the positional deviation
D becomes smaller. The rope length L can be detected by the encoder 5a and let ΔL
be the detection resolution of the encoder 5a for the rope length L. The minimum value
Dmin for the positional deviation D can be expressed by the following Expression (2):
[Expression 2]

[0048] As understood from the above description, the minimum value Dmin for the positional
deviation D depends on the detection resolution of the encoder 5a and reducing the
positional deviation D has a limit.
[0049] Another issue is that the operating time to move the trolly 4 to directly above the
payload 9 is long when the positional deviation D is large. As illustrated in FIG.
4, the existing art repeats straining the rope by winding up, measuring the rope length,
and slightly moving the trolley 4. For this reason, when the positional deviation
D is large, more repeats are required, increasing the operating time.
Overview and Principle of This Invention
[0050] This invention addresses the above-described issues as follows. FIG. 8 is a graph
representing the relation between the rope length L and the trolly position x for
illustrating the principle of this invention. FIG. 9 is a diagram illustrating the
movement of the crane 1 in this invention. The trolley position x(i) in the traversing
direction of the trolley 4 and the distance L(i) between the trolley 4 at the position
x(i) and the payload 9 (the length of the taut rope including the length of the wires
8) have the relation expressed by the following Expression (3):
[Expression 3]

where i is a natural number representing the ordinal number of the measurement of
the rope length L.
[0051] In FIG. 8, the payload location xp is the position of the trolley 4 where the rope
length L takes a minimum value when the trolley 4 is moved transversely (along the
girder 3) and is the location (payload location) xp of the payload 9 in the transverse
direction. The following Expression (4) can be obtained by squaring the both members
of the Expression (3):
[Expression 4]

[0052] Letting p1 and p2 be the parameters including the height H from the payload 9 to
the trolley 4 (or the hoisting device 5) and the payload location xp, the foregoing
Expression (4) can be expressed by the following Expression (5):
[Expression 5]

[0053] As expressed by Expression (5), the squared value of the rope length L(i) can be
expressed by a quadratic function of the trolley position x(i). Hence, the control
device 100 in this embodiment moves the trolley 4 transversely and measures at least
two different trolley positions x(i) and the rope lengths L(i) of the taut rope there
as state values and fits the acquired trolley positions x(i) and rope lengths L(i)
to the foregoing Expression (5) by a well-known or publicly known method such as the
method of least squares to calculate the parameters p1 and p2. The fitting in this
embodiment obtains the best curve (the foregoing expression (5)) that fits the measured
data by curve fitting or curve regression.
[0054] The control device 100 can calculate the payload location xp of the payload 9 in
the transverse direction, using the following Expression (6) with the calculated parameters
p1 and p2:
[Expression 6]

[0055] In similar, the control device 100 measures at least two different girder positions
y(i) in its traveling direction and the rope length L(i) there to calculate the payload
location yp of the payload 9 in the traveling direction where the rope length L from
the trolley 4 takes the minimum value in the traveling direction of the girder 3,
like the payload location xp.
[0056] The control device 100 can reduce the horizontal positional deviation D of the trolley
4 from the payload 9 by moving the trolley 4 in the transverse direction and the traveling
direction to the calculated payload location (xp, yp) and as a result, the initial
sway is reduced.
[0057] As described above, the method of this invention fits the rope lengths L(i) and the
trolley positions x(i) to the quadratic curve expressed by the foregoing Expression
(5). This method can determine the position directly above the payload 9 more precisely
than the existing art that depends on the detection resolution of the encoder, achieving
a smaller positional deviation D.
[0058] Furthermore, the method of this invention requires at least two times of operation
of straining the rope 6 by winding up, measuring the rope length L, and moving the
trolley 4 in each of the transverse direction and the traveling direction. The number
of repeats is smaller than the existing art, achieving a shorter operating time.
Control in This Invention
[0059] FIG. 10 is a flowchart of an example of processing to be performed in the control
device 100 of this invention. This processing starts based on the operator's instruction.
The details are as follows.
[0060] At Step S201, the control device 100 changes the operation mode to an initial positioning
mode in this invention to move the trolley before hoisting a grounded payload. For
example, the operation input device 200 can have an operation mode selection switch
and the operator operates the switch to change the operation mode.
[0061] The control device 100 may display the operation mode with the display device 210
or the crane 1 can have a lamp for indicating the operation mode so that the surroundings
can know the selected operation mode.
[0062] At Step S202, the control device 100 moves the trolley 4 to identify the payload
location xp in the transverse direction. The details of this control will be described
later. At Step S203, the control device 100 moves the girder 3 along the runways 2
to identify the payload location yp in the traveling direction of the girder 3.
[0063] At Step S204, the control device 100 moves the trolley and the girder 3 to the identified
payload location (xp, yp). As a result, the rope 6 drooping from the trolley 4 is
positioned directly above the payload 9.
[0064] At Step S205, the control device 100 changes the operation mode to a normal operation
mode in which the crane 1 transports the payload 9 in the direction corresponding
to the pressed operation button 202 of the operation terminal 201. This mode change
can be performed not only in response to an explicit operation such as operating the
operation mode selection switch of the operation terminal 201 but also automatically
as soon as the trolley 4 reaches the payload location (xp, yp).
[0065] To ensure the safeness, the trolley 4 can be configured to move only when an operation
button 202 of the operation terminal 201 is being pressed in the above-described Steps
S202, S203, and S204.
[0066] FIG. 11 is a flowchart of the details of identifying the payload location xp at Step
S202 in FIG. 10. The details are as follows. The details of Step S203 are the same
as those of Step S202 in which the transverse direction in the following description
is replaced by the traveling direction.
[0067] At Step S301, the control device 100 winds up the rope 6 until it becomes taut at
the initial position x(1) of the trolley 4 and measures the rope length L(1) when
the rope 6 is taut from the detection value of the encoder 5a.
[0068] Whether the rope 6 is taut can be determined by a well-known or publicly-known technique,
for example, by determining whether the current value of the hoist motor is higher
than a threshold value or by determining whether the tension of the rope 6 is higher
than a threshold value with a tension sensor attached to the rope 6.
[0069] At Step S302, the control device 100 moves the trolley 4 to a trolley position x(2)
that is distant from the trolley position x(1) by a predetermined distance dx, winds
up the rope 6 at the position x(2) until the rope becomes taut, and measures the rope
length L(2) with the encoder 5a. The horizontal position of the trolley 4 can be calculated
from the moving time of the trolley 4 or measured with a laser distance sensor attached
on the trolley 4.
[0070] The control device 100 performs the foregoing Steps S301 and S302 with respect to
the traveling direction of the girder 3 in the same way; specifically, the control
device 100 moves the girder 3 to a girder position y(2) that is distant from the initial
girder position y(1) by a predetermined distance dy, winds up the rope 6 at the position
y(2) until the rope 6 becomes taut, and measures the rope length L(2) with the encoder
5a.
[0071] At Step S303, the control device 100 fits the trolley positions and rope lengths
(x(1), L(1)) and (x(2), L(2)) measured at the foregoing Steps S301 and S302 to the
aforementioned Expression (5) by a well-known or publicly-known method such as the
method of least squares to identify the parameters p1 and p2 in the traversing direction
of the trolley 4.
[0072] The control device 100 further identifies the parameters p1 and p2 in the traveling
direction of the girder 3 by the same method as described above, or by fitting the
girder positions and rope lengths (y(1), L(1)) and (y(2), L(2)) to the aforementioned
Expression (5) by a well-known or publicly-known method such as the method of least
squares.
[0073] At Step S304, the control device 100 determines the payload location xp in the transverse
direction where the rope length L (state value) takes a minimum value using the aforementioned
Expression (6) with the parameter in the traversing direction of the trolley 4 denoted
by p1x in FIG. 11. Further, the control device 100 determines the payload location
yp in the traveling direction where the rope length L takes a minimum value using
the aforementioned Expression (6) with the parameter in the traveling direction of
the girder 3 denoted by ply in FIG. 11.
[0074] At the aforementioned Step S302, if the trolley 4 is moved in the state where the
rope 6 is taut, the payload 9 may be dragged. Accordingly, the rope 6 should be paid
out before moving the trolley 4. The same applies to moving the girder 3 in the traveling
direction.
[0075] Although this example moves the trolley transversally to measure the rope length
at two positions, the positions to measure the rope length can be increased for higher
accuracy in detecting the payload location xp.
[0076] As described above, the location of the payload 9 can be determined more precisely
by fitting the trolley positions x(1) and x(2) and the lengths L(1) and L(2) of the
taut rope to the quadratic curve in FIG. 8, so that a smaller positional deviation
is attained.
[0077] This embodiment requires straining the rope 6 by the hoisting device 5 winding up,
measuring the rope length L, and moving the trolley 4 (or the girder 3) for at least
two times in each of the transverse direction and the traveling direction, achieving
a smaller number of repeats. Accordingly, the operating time of the trolley 4 before
hoisting the grounded payload can be reduced, enabling the hoisting operation to start
sooner.
Modified Example 1
[0078] Focusing on the constant terms of the foregoing Expressions (4) and (5), the height
H can be calculated by the following Expression (7):
[Expression 7]

[0079] Subtracting the rope length Lr (x = xp) of the taut rope 6 from the trolley 4 positioned
directly above the payload 9 to the hook 7 from this height H provides the length
Lw of the wires 8 from the hook 7 to the payload 9 as expressed in the following Expression
(8):
[Expression 8]

[0080] The above expression enables automatic acquisition of the length Lw of the wires
8 (hereinafter wire length). This wire length Lw enables automatic acquisition of
the distance L from the trolley 4 to the payload 9 by being added to the length Lr
of the rope 6 from the trolley 4 to the hook 7 detected with the encoder 5a. This
distance L is the same as the aforementioned rope length L from the trolley 4 to the
payload 9.
[0081] This distance L is a parameter necessary for the control to suppress the payload
sway occurring in transporting a suspended payload 9. The payload sway in transportation
is generated by an inertia force caused by acceleration or deceleration of the trolley
4 and acting on the suspended payload 9. The inertia force exerts sway at an angular
frequency ωr expressed as follows:

[0082] This payload sway can be suppressed by payload sway suppression control to remove
the frequency component of angular frequency ωr from the speed command value for the
trolley 4, as provided in
WO 2018/211739 A (hereinafter, the known art), for example.
[0083] However, this known art predetermines the wire length Lw or reads out a recorded
value; it does not disclose a method of automatically acquiring the wire length Lw
depending on the wires 8 in use. The foregoing calculation enables automatic acquisition
of the wire length Lw, improving the performance to suppress the payload sway in transporting
a payload.
Effect of Modified Example 1
[0084] The foregoing calculation also enables automatic acquisition of the height H from
the payload 9 to the trolley 4. Hence, the limit in unwinding (paying out) the rope
6 can be automatically determined; the payload can prevent inadvertent impact onto
the ground or unhook from slack wires caused by excessive unwinding, increasing the
safeness of the crane 1.
EMBODIMENT 2
[0085] Described next is a crane 1 in Embodiment 2 of this invention. The repetitive description
of the points in common with the foregoing embodiment is omitted here. The configurations
of the crane 1 and the control device 100 are the same as those in Embodiment 1.
[0086] The crane 1 in Embodiment 1 identifies the payload location using the distance between
the trolley 4 and the payload 9 (the length of the rope 6 including the length of
the wires 8) as a state value. In this regard, a hook 7 is attached at the end of
the rope 6 drooping from the trolley 4 to hang the payload 9 with the wires 8, as
illustrated in FIG. 1.
[0087] Although the distance from the trolley 4 to the hook 7 or the length of the rope
6 can be detected with the encoder attached on the hoisting device 5, the crane 1
does not usually equip a device for directly detecting the distance from the hook
7 to the payload 9 or the length of the wires 8. Accordingly, this embodiment regards
the length of the wires 8 as an unknown to identify the payload location xp (yp).
[0088] Letting Lr(i) be the rope length, Lw be the wire length, x(i) be the position of
the trolley 4, xp be the payload location, and H be the height from the payload 9
to the trolley 4, these have a relation as expressed by the following Expression (9):
[Expression 10]

[0089] The following Expression (10) can be obtained by squaring the both members of Expression
(9):
[Expression 11]

[0090] Letting p1, p2, and p3 be the parameters including the wire length Lw, the height
H, and the payload location xp, the following Expression (11) is obtained:
[Expression 12]

[0091] The control device 100 transversely moves the trolley 4 and measures at least three
different trolley positions x(i) and the rope lengths Lr(i) of the taut rope 6 there
and fits the acquired trolley positions x(i) and rope lengths Lr(i) to the foregoing
Expression (11) by the method of least squares to calculate the parameters p1, p2,
and p3. Then, the payload location xp of the payload 9 in the transverse direction
can be calculated by the following Expression (12) with the calculated parameters:
[Expression 13]

[0092] In similar, the control device 100 measures at least three different girder positions
y(i) in the traveling direction and the rope lengths Lr(i) there. Then, the control
device 100 can calculate the payload location yp of the payload 9 in the traveling
direction where the rope length Lr takes a minimum value when the girder 3 is moved
in the traveling direction.
[0093] The control device 100 can eliminate the horizontal positional deviations of the
trolley 4 and the girder 3 from the payload 9 by moving the trolley 4 and the girder
3 to the calculated payload location (xp, yp) and as a result, the initial sway is
reduced.
[0094] The above-described method enables the location of the payload 9 to be identified,
even if the distance from the hook 7 to the payload 9 or the wire length Lw is unknown.
Modified Example 2
[0095] Focusing on the coefficients of the rope length Lr(i) in the foregoing Expressions
(10) and (11), the wire length Lw can be calculated by the following Expression (13):
[Expression 14]

[0096] Focusing on the constant terms of the Expressions (10) and (11), the height H can
be calculated by the following Expression (14):
[Expression 15]

[0097] The wire length Lw can also be calculated by the aforementioned Expression (8) with
the calculated height H and the rope length Lr (x = xp) of the taut rope 6 from the
trolley 4 positioned directly above the payload 9 to the hook 7.
[0098] The above-described method enables automatic acquisition of the wire length Lw, which
improves the payload sway suppression control in transporting a payload. Further,
automatic acquisition of the height H is also available; the safeness of the crane
1 can be increased by automatically determining the limit in unwinding the rope 6.
EMBODIMENT 3
[0099] Described next is a crane 1 in Embodiment 3 of this invention. The repetitive description
of the points in common with the foregoing embodiments is omitted here.
[0100] FIG. 14 illustrates a configuration of the control device of the crane 1 in Embodiment
3. The configurations same as those in the foregoing Embodiment 1 are assigned same
reference signs and repetitive description thereof is omitted here. FIG. 14 includes
a force sensor 4a (fourth sensor) on the trolley 4 to detect the force transversely
acting on the trolley 4, a tension sensor 5b (third sensor) on the hoisting device
5 to detect the tension of the rope 6, and a sway angle sensor 7a (second sensor)
on the hook 7 to detect the angle of the rope 6, in addition to the configuration
in the foregoing Embodiment 1. Furthermore, the control device 100 additionally includes
a horizontal force detector 301 (another implementation means of the fourth sensor)
for detecting the transversal force applied to the trolley 4 and a tension detector
311 (another implementation means of the third sensor) for measuring the tension of
the rope 6.
[0101] FIG. 12 illustrates the movement of the crane 1 in Embodiment 3. The crane 1 in this
Embodiment 3 detects the angle (rope sway angle) of the rope 6 in a taut state with
respect to the vertical direction of the trolley 4 with the sway angle sensor 7a and
uses the rope sway angle as a state value to identify the payload location.
[0102] The rope sway angle can be detected with the encoder by detecting the angle of a
weight hanging from the hook 7 as described in the aforementioned Patent Document
1 or with a gyrosensor attached on the hook 7.
[0103] Letting θ(i) be the rope sway angle, x(i) be the position of the trolley 4, xp (or
yp) be the location of the payload 9, and H be the height from the payload 9 to the
trolley 4, these have a relation expressed by the following Expression (15):
[Expression 16]

[0104] Letting p1 and p2 be the parameters including the height H and the payload location
xp, the following Expression (16) is obtained:
[Expression 17]

[0105] The control device 100 transversely moves the trolley 4 and measures at least two
different trolley positions x(i) and the rope sway angles θ(i) there and fits the
acquired trolley positions x(i) and rope sway angles θ(i) to the foregoing Expression
(16) by the method of least squares to calculate the parameters p1 and p2.
[0106] The control device 100 can calculate the trolley position where the rope sway angle
takes a minimum value or the location of the payload 9 in the transverse direction,
using the following Expression (17) with the calculated parameters p1 and p2:
[Expression 18]

[0107] In similar, the control device 100 measures at least two different girder positions
y(i) in the traveling direction of the girder 3 and the rope sway angles θ(i) there.
Then, the control device 100 can calculate the payload location yp of the payload
9 in the traveling direction where the rope sway angle takes a minimum value when
the girder 3 is moved in the traveling direction.
[0108] The acquired location (xp, yp) is the location of the payload; the control device
100 can eliminate the horizontal positional deviations of the trolley 4 and the girder
3 from the payload 9 by moving the trolley 4 and the girder 3 to this calculated payload
location, and as a result, the initial sway is reduced.
[0109] The above-described method enables the location of the payload 9 to be identified,
using the sway angle θ of a taut rope 6 as a state value.
Modified Example 3
[0110] Focusing on the coefficient of tanθ in the foregoing Expressions (15) and (16), the
height H can be calculated by the following Expression (18):
[Expression 19]

[0111] The control device 100 can calculate the wire length Lw by the aforementioned Expression
(8) with the calculated height H and the rope length Lr (x = xp) of the taut rope
6 from the trolley 4 positioned directly above the payload 9 to the hook 7.
[0112] The above-described method enables automatic acquisition of the wire length Lw, which
improves the payload sway suppression control in transporting a payload. Further,
automatic acquisition of the height H is also available; the safeness of the crane
1 can be increased by automatically determining the limit in unwinding the rope 6.
EMBODIMENT 4
[0113] Described next is a crane 1 in Embodiment 4 of this invention. The repetitive description
of the points in common with the foregoing embodiments is omitted here. The configurations
of the crane 1 and the control device 100 are the same as those in Embodiment 3 illustrated
in FIG. 14.
[0114] FIG. 13 illustrates the movement of the crane 1 in Embodiment 4. The crane 1 in this
embodiment uses the tension of the taut rope 6 and the force horizontally acting on
the trolley 4 as state values to identify the payload location.
[0115] The tension of the rope 6 can be detected by the tension sensor 5b attached on the
hoisting device 5 or the tension detector 311 that calculates the tension of the rope
6 from the current value of the hoist motor acquired from the hoist motor controller
310.
[0116] The force horizontally acting on the trolley 4 can be detected by the force sensor
4a or the horizontal force detector 301 that detects the motor current when the trolley
4 keeps a horizontal position in a transverse direction.
[0117] Letting T(i) be the tension of the rope 6, F(i) be the force horizontally acting
on the trolley 4, x(i) be the position of the trolley, xp (or yp) be the location
of the payload 9, and H be the height from the payload 9 to the trolley 4, these have
relations expressed by the following Expressions (19) and (20):

[0118] Letting p1 and p2 be the parameters including the height H and the payload location
xp, the following Expression (21) is obtained:
[Expression 21]

[0119] The control device 100 transversely moves the trolley 4 and measures at least two
different trolley positions x(i) and the tensions T(i) of the rope 6 and the forces
F(i) horizontally acting on the trolley 4 there and fits the acquired trolley positions
x(i), tensions T(i), and forces F(i) to the foregoing Expression (21) by the method
of least squares to calculate the parameters p1 and p2.
[0120] Then, the control device 100 can calculate the position xp of the trolley 4 where
the rope sway angle θ(i) takes a minimum value or the location xp of the payload 9
in the transverse direction, using the following Expression (22) with the calculated
parameters p1 and p2:
[Expression 22]

[0121] In similar, the control device 100 measures at least two different girder positions
y(i) in the traveling direction of the girder 3 and the tensions T(i) of the rope
6 and the forces F(i) horizontally acting on the trolley 4 there to calculate the
payload location yp of the payload 9 in the traveling direction where the rope sway
angle θ(i) takes a minimum value when the girder 3 is moved in the traveling direction.
[0122] The control device 100 can eliminate the horizontal positional deviations of the
trolley 4 and the girder 3 from the payload 9 by moving the trolley 4 and the girder
3 to the calculated payload location (xp, yp), and as a result, the initial sway is
reduced.
[0123] The above-described method enables the location of the payload 9 to be identified,
using the tension of the rope 6 and the force horizontally acting on the trolley 4
as state values.
Modified Example 4
[0124] The crane 1 in this Modified Example 4 can also identify the wire length Lw and the
height H in the same way as the crane 1 in Modified Example 3. Automatic acquisition
of the wire length Lw enables improvement in payload sway suppression control in transporting
a payload and automatic acquisition of the height H enables increase in safeness of
the crane 1 because automatic determination of the limit in unwinding the rope 6 is
available.
EMBODIMENT 5
[0125] Described next is a crane 1 in Embodiment 5 of this invention. The repetitive description
of the points in common with the foregoing embodiments is omitted here. The configurations
of the crane 1 and the control device 100 are the same as those in Embodiment 3 illustrated
in FIG. 14.
[0126] The crane 1 in Embodiment 5 pays out the rope 6 before moving the trolley 4 to prevent
the payload 9 from being lifted or dragged, in the case where the payload 9 is grounded.
The control device 100 uses the time taken to wind up the rope 6 from the paid-out
state to a taut state as a state value to identify the payload location.
[0127] Letting Lf(i) be the paid-out length of the rope 6, Tf(i) be the time taken to wind
up the rope 6 into a taut state, V be the winding speed, L0 be the rope length when
the rope 6 is first wounded up to a taut state, x(i) be the position of the trolley
4, and xp be the location of the payload 9, these have relations expressed by Expressions
(23) and (24) below. The winding speed V can be calculated by the control device 100
from the time Tf taken to wind up the rope 6 into a taut state and the variation of
the rope length L0 when the rope 6 is wounded to the taut state. The time Tf taken
to wind up the rope 6 into a taut state can be measured with a timer included in the
control device 100. The rope length L0 can be measured with the encoder 5a, like in
the above-described Embodiment 1.

[0128] The following Expression (25) can be obtained by squaring the both members of Expression
(24):
[Expression 24]

[0129] Letting p1, p2, and p3 be the parameters including the rope length L0, the height
H, and the payload location xp, the following Expression (26) is obtained:
[Expression 25]

[0130] The control device 100 transversely moves the trolley 4 and measures at least three
different trolley positions x(i) and the lengths Lf(i) of the rope 6 paid out before
moving the trolley 4 and the times Tf(i) taken to wind up the rope into a taut state
there and fits the acquired trolley positions x(i), paid-out lengths Lf(i), and winding
times Tf(i) to the foregoing Expression (25) by the method of least squares to calculate
the parameters p1, p2, and p3. Then, the control device 100 can calculate the trolley
position where dL takes a maximum value or the location of the payload 9 in the transverse
direction, using the following Expression (27) with the calculated parameters:
[Expression 26]

[0131] In similar, the control device 100 measures at least three different girder positions
y(i) in the traveling direction of the girder 3 and the lengths Lf(i) of the rope
6 paid out before moving the girder 3 and the times Tf(i) taken to wind up the rope
into a taut state there to calculate the payload location yp of the payload 9 in the
traveling direction where dL takes a maximum value when the girder 3 is moved in the
traveling direction.
[0132] The control device 100 can eliminate the horizontal positional deviations of the
trolley 4 and the girder 3 from the payload 9 by moving the trolley 4 and the girder
3 to the calculated payload location (xp, yp), and as a result, the initial sway is
reduced.
[0133] The above-described method enables the location of the payload 9 to be identified,
using the length of the rope 6 paid out before moving the trolley 4 and the time taken
to wind up the rope 6 into a taut state as state values.
Modified Example 5
[0134] Focusing on the coefficient of the dL(i) and the constant terms in the foregoing
Expressions (24) and (25), the height H can be calculated by the following Expressions
(28) and (29):

[0135] The control device 100 can calculate the wire length Lw by the aforementioned Expression
(8) with the calculated height H and the rope length Lr (x = xp) of the taut rope
6 from the trolley 4 positioned directly above the payload 9 to the hook 7.
[0136] The above-described method enables automatic acquisition of the wire length Lw, which
improves the payload sway suppression control in transporting a payload. Further,
automatic acquisition of the height H is also available; the safeness of the crane
1 can be increased by automatically determining the limit in unwinding the rope 6.
[0137] As described in the foregoing Embodiments 1 to 5, this invention is generally effective
for cranes 1 capable of horizontally transporting a payload 9 and is applicable to
not only a crane 1 (such as an overhead crane) for transporting a payload in the transverse
direction and the traveling direction with a trolley 4 and a girder 3 but also a crane
(such as an unloader) for transporting a load only in either the transverse direction
or the traveling direction. That is to say, the term "crane" referred to in the subsequent
description includes any kinds of cranes capable of horizontally transporting a payload
9.
[0138] The payload (hooked payload) to be transported by the crane 1 is hung by a rope 6
or a chain in transportation. The hanging member (or sling member) used in this invention
is not limited to a specific one, even in terms of its material or shape, as far as
it can be used to hang a payload.
[0139] Accordingly, the term "rope" is used as a generic term for referring to a hanging
member (sling member) for hanging a payload, as already stated. That is to say, the
term "rope" includes not only a so-called rope but also chain, belt, wire, cable,
band, cord, and the like.
CLOSING
[0140] As set forth above, claims based on the above-described embodiments can be configured
as follows.
[0141]
- (1) A crane comprising a horizontal transport device (trolley 4) horizontally movable
with a motor, a hoisting device (5) mounted on the horizontal transport device (4)
and being capable of winding a rope (6) with a hoist motor, a hook (7) attached on
the rope (6) to hang a payload (9), and a control unit (control device 100) including
a processor (MPU 101) and a memory (102) and being configured to control the horizontal
transport device (4) and the hoisting device (5), wherein the control unit (100) includes
a rope tension determination unit (21) configured to determine whether the rope (6)
is in a taut state without a slack, a state measurement unit (22) configured to measure
at least one state value of the crane when the rope (6) has been wound up into a taut
state by the hoisting device (5) being driven, and a transport control unit (24) configured
to move the horizontal transport device (4); the state measurement unit (22) is configured
to identify a payload (9) location of a grounded payload (9), using a position of
the horizontal transport device (4) and the at least one state value measured when
the rope (6) is in a taut state; and the transport control unit (24) is configured
to move the horizontal transport device (4) to the identified payload (9) location
to position the rope (6) directly above the payload (9).
The above-described configuration enables the control device 100 to determine the
location of the payload 9 more precisely by fitting the trolley positions x(1) and
x(2) and the lengths L(1) and L(2) of the taut rope to the quadratic curve in FIG.
8, attaining a smaller positional deviation.
- (2) The crane according to the foregoing (1), wherein the at least one state value
is a distance L from the horizontal transport device (4) to the payload (9) when the
rope (6) has been wound up into a taut state; and the state measurement unit is configured
to measure the position x of the horizontal transport device (4) and the distance
L from the horizontal transport device (4) to the payload (9) with a first sensor
(encoder 5a) attached on the horizontal transport device (4) at least two points in
a moving direction, calculate parameters p1 and p2 in x2 - L2 + p1 × x + p2 = 0 with results of the measurement, and calculate a position x of
the horizontal transport device (4) at which the distance L takes a minimum value
as the payload (9) location xp, using the calculated parameters p1 and p2.
The above-described configuration enables the control device 100 in Embodiment 1 to
require straining the rope 6 by the hoisting device 5 winding up, measuring the rope
length L, and moving the trolley 4 (or the girder 3) for at least two times in each
of the transverse direction and the traveling direction, achieving a smaller number
of repeats. Accordingly, the operating time of the trolley 4 before hoisting the grounded
payload can be reduced, enabling the hoisting operation to start sooner.
- (3) The crane according to the foregoing (1), wherein the rope (6) is connected to
the hook (7) at an end and the hook (7) is connected to a sling member to hang the
payload (9); the at least one state value is a rope (6) length when the rope (6) has
been wound up into a taut state; and the state measurement unit (22) is configured
to measure the position x of the horizontal transport device (4) and the rope (6)
length Lr with a first sensor (5a) attached on the horizontal transport device (4)
at least three points in a moving direction, calculate parameters p1, p2, and p3 in
x2 - Lr2 + p1 × x + p2 × Lr + p3= 0 with results of the measurement, and calculate a position
x of the horizontal transport device (4) at which the rope (6) length Lr takes a minimum
value as the payload (9) location xp, using the calculated parameters p1, p2, and
p3.
The above-described configuration enables the control device 100 to automatically
acquire the wire length Lw, so that the control device 100 can identify the location
of the payload 9 even if the distance from the hook 7 to the payload 9 or the distance
including the wire length Lw is unknown.
- (4) The crane according to the foregoing (1), wherein the at least one state value
is a sway angle (θ) of the rope (6) with respect to the horizontal transport device
(4) when the rope (6) has been wound up into a taut state; and the state measurement
unit (22) is configured to measure the position x of the horizontal transport device
(4) and the sway angle θ of the rope (6) with a second sensor (sway angle sensor 7a)
attached on the horizontal transport device (4) at least two points in a moving direction,
calculate parameters p1 and p2 in x + p1 × tanθ + p2 = 0 with results of the measurement,
and calculate a position x of the horizontal transport device (4) at which the sway
angle θ takes a minimum value as the payload (9) location xp, using the calculated
parameters p1 and p2.
The above-described configuration enables the control device 100 to identify the location
of the payload 9 using the sway angle θ of the rope 6 in a taut state as a state value
and eliminate the horizontal positional deviations of the trolley 4 and the girder
3 from the payload 9 by moving the trolley 4 and the girder 3 to the calculated payload
location, so that the initial sway is reduced.
- (5) The crane according to the foregoing (1), wherein the at least one state value
comprises a tension T of the rope (6) and a force F horizontally acting on the horizontal
transport device (4) when the rope (6) has been wound up into a taut state; and the
state measurement unit (22) is configured to measure the position x of the horizontal
transport device (4) and the tension T of the rope (6) with a third sensor (tension
sensor 5b) attached on the hoisting device (5) and the horizontally acting force F
with a fourth sensor (horizontal force detector 301) attached on the horizontal transport
device (4) at least two points in a moving direction, calculate a sway angle θ of
the rope (6) and parameters p1 and p2 in x + p1 x tanθ + p2 = 0 using θ = arcsin(F/T)
and results of the measurement, and calculate a position x of the horizontal transport
device (4) at which the sway angle θ takes a minimum value as the payload (9) location
xp, using the calculated parameters p1 and p2.
The above-described configuration enables the control device 100 to identify the location
of the payload 9 using the tension of the rope 6 and the force horizontally acting
on the trolley 4 as state values and eliminate the horizontal positional deviations
of the trolley 4 and the girder 3 from the payload 9, so that the initial sway is
reduced.
- (6) The crane according to the foregoing (1), wherein the at least one state value
comprises a length Lf of the rope (6) paid out before moving the horizontal transport
device (4) and a time Tf taken to wind up the rope (6) into a taut state; and the
state measurement unit (22) is configured to measure the position x of the horizontal
transport device (4), the paid-out length Lf of the rope (6), and the time Tf taken
to wind up the rope (6) into a taut state at least three points in a moving direction,
calculate a rope (6) winding speed V from variations t in the paid-out length Lf of
the rope (6) and the times Tf taken to wind up the rope into a taut state, calculate
parameters p1, p2, and p3 in x2 - dL2 + p1 × x + p2 × dL + p3 = 0 using dL = Lf - V × Tf and results of the measurement,
and calculate a position x of the horizontal transport device (4) at which dL takes
a minimum value as the payload (9) location xp, using the calculated parameters p1,
p2, and p3.
The above-described configuration enables the control device 100 to identify the location
of the payload 9 using the length of the rope 6 paid out before moving the trolley
4 and the time taken to wind up the rope 6 into a taut state as state values and eliminate
the horizontal positional deviations of the trolley 4 and the girder 3 from the payload
9 by moving the trolley 4 and the girder 3 to the calculated payload location (xp,
yp), so that the initial sway is reduced.
- (7) The crane according to any one of the foregoing (1) to (6), wherein the state
measurement unit (22) is configured to identify a height H from the payload (9) to
the horizontal transport device (4) based on the at least one state value and the
position x of the horizontal transport device (4).
The above-described configuration enables the control device 100 to automatically
acquire the height H from the payload 9 to the trolley 4. Hence, the limit in unwinding
the rope 6 can be automatically determined; the payload can prevent inadvertent impact
onto the ground or unhook from slack wires caused by excessive unwinding, increasing
the safeness of the crane 1.
- (8) The crane according to the foregoing (7), wherein the state measurement unit (22)
is configured to identify the height H from the payload (9) to the horizontal transport
device (4) based on the at least one state value and the position x of the horizontal
transport device (4) and identify a length Lw of a sling member from a length Lr of
the rope (6) and the height H.
The above-described configuration enables the control device 100 to automatically
acquire the wire length Lw, improving he payload sway suppression control in transporting
a payload. Further, automatic acquisition of the height H is also available.
- (9) The crane according to the foregoing (3), wherein the state measurement unit (22)
is configured to identify a length Lw of the sling member based on the at least one
state value and the position x of the horizontal transport device (4).
[0142] The above-described configuration enables the control device 100 to automatically
acquire the wire length Lw, improving the payload sway suppression control in transporting
a payload.
[0143] This invention is not limited to the embodiments described above, and encompasses
various modification examples. For instance, the embodiments are described in detail
for easier understanding of this invention, and this invention is not limited to modes
that have all of the described components. Some components of one embodiment can be
replaced with components of another embodiment, and components of one embodiment may
be added to components of another embodiment. In each embodiment, other components
may be added to, deleted from, or replace some components of the embodiment, and the
addition, deletion, and the replacement may be applied alone or in combination.
[0144] Some of all of the components, functions, processing units, and processing means
described above may be implemented by hardware by, for example, designing the components,
the functions, and the like as an integrated circuit. The components, functions, and
the like described above may also be implemented by software by a processor interpreting
and executing programs that implement their respective functions. Programs, tables,
files, and other types of information for implementing the functions can be put in
a memory, in a storage apparatus such as a hard disk, or a solid state drive (SSD),
or on a recording medium such as an IC card, an SD card, or a DVD.
[0145] The control lines and information lines described are lines that are deemed necessary
for the description of this invention, and not all of control lines and information
lines of a product are mentioned. In actuality, it can be considered that almost all
components are coupled to one another.
1. A crane comprising:
a horizontal transport device horizontally movable with a motor;
a hoisting device mounted on the horizontal transport device, the hoisting device
being capable of winding a rope with a hoist motor;
a hook attached on the rope to hang a payload; and
a control unit including a processor and a memory, the control unit being configured
to control the horizontal transport device and the hoisting device,
wherein the control unit includes:
a rope tension determination unit configured to determine whether the rope is in a
taut state without a slack;
a state measurement unit configured to measure at least one state value of the crane
when the rope has been wound up into a taut state by the hoisting device being driven;
and
a transport control unit configured to move the horizontal transport device,
wherein the state measurement unit is configured to identify a payload location xp
of a grounded payload, using a position x of the horizontal transport device and the
at least one state value measured when the rope is in a taut state, and
wherein the transport control unit is configured to move the horizontal transport
device to the identified payload location xp to position the rope directly above the
payload.
2. The crane according to claim 1,
wherein the at least one state value is a distance L from the horizontal transport
device to the payload when the rope has been wound up into a taut state, and
wherein the state measurement unit is configured to:
measure the position x of the horizontal transport device and the distance L from
the horizontal transport device to the payload with a first sensor attached on the
horizontal transport device at least two points in a moving direction; and
calculate parameters p1 and p2 in x2 - L2 + p1 × x + p2 = 0 with results of the measurement and calculate a position x of the
horizontal transport device at which the distance L takes a minimum value as the payload
location xp, using the calculated parameters p1 and p2.
3. The crane according to claim 1,
wherein the rope is connected to the hook at an end and the hook is connected to a
sling member to hang the payload,
wherein the at least one state value is a rope length Lr when the rope has been wound
up into a taut state, and
wherein the state measurement unit is configured to:
measure the position x of the horizontal transport device and the rope length Lr with
a first sensor attached on the horizontal transport device at least three points in
a moving direction; and
calculate parameters p1, p2, and p3 in x2 - Lr2 + p1 × x + p2 × Lr + p3= 0 with results of the measurement and calculate a position
x of the horizontal transport device at which the rope length Lr takes a minimum value
as the payload location xp, using the calculated parameters p1, p2, and p3.
4. The crane according to claim 1,
wherein the at least one state value is a sway angle θ of the rope with respect to
the horizontal transport device when the rope has been wound up into a taut state,
and
wherein the state measurement unit is configured to:
measure the position x of the horizontal transport device and the sway angle θ of
the rope with a second sensor attached on the horizontal transport device at least
two points in a moving direction; and
calculate parameters p1 and p2 in x + p1 × tanθ + p2 = 0 with results of the measurement
and calculate a position x of the horizontal transport device at which the sway angle
θ takes a minimum value as the payload location xp, using the calculated parameters
p1 and p2.
5. The crane according to claim 1,
wherein the at least one state value comprises a tension T of the rope and a force
F horizontally acting on the horizontal transport device when the rope has been wound
up into a taut state, and
wherein the state measurement unit is configured to:
measure the position x of the horizontal transport device and the tension T of the
rope with a third sensor attached on the horizontal transport device and the horizontally
acting force F with a fourth sensor attached on the horizontal transport device at
least two points in a moving direction; and
calculate sway angles θ of the rope and parameters p1 and p2 in x + p1 × tanθ + p2
= 0 using θ = arcsin(F/T) and results of the measurement and calculate a position
x of the horizontal transport device at which the sway angle θ takes a minimum value
as the payload location xp, using the calculated parameters p1 and p2.
6. The crane according to claim 1,
wherein the at least one state value comprises a length Lf of the rope paid out before
moving the horizontal transport device and a time Tf taken to wind up the rope into
a taut state, and
wherein the state measurement unit is configured to:
measure the position x of the horizontal transport device, the paid-out length Lf
of the rope, and the time Tf taken to wind up the rope into a taut state at least
three points in a moving direction and calculate a rope winding speed V from variations
t in the paid-out length Lf of the rope and the times Tf taken to wind up the rope
into a taut state; and
calculate parameters p1, p2, and p3 in x2 - dL2 + p1 × x + p2 × dL + p3 = 0 using dL = Lf - V × Tf and results of the measurement
and calculate a position x of the horizontal transport device at which dL takes a
minimum value as the payload location xp, using the calculated parameters p1, p2,
and p3.
7. The crane according to any one of claims 1 to 6, wherein the state measurement unit
is configured to identify a height H from the payload to the horizontal transport
device based on the at least one state value and the position x of the horizontal
transport device.
8. The crane according to claim 7, wherein the state measurement unit is configured to
identify the height H from the payload to the horizontal transport device based on
the at least one state value and the position x of the horizontal transport device
and identify a length Lw of a sling member from a rope length Lr and the height H.
9. The crane according to claim 3, wherein the state measurement unit is configured to
identify a length Lw of the sling member based on the at least one state value and
the position x of the horizontal transport device.
10. A method of controlling a crane including a horizontal transport device horizontally
movable with a motor, a hoisting device mounted on the horizontal transport device
and being capable of winding a rope with a hoist motor, a hook attached on the rope
to hang a payload, and a control unit including a processor and a memory and configured
to control the horizontal transport device and the hoisting device,
the method comprising:
a rope tension determination step of determining, by the control unit, whether the
rope is in a taut state without a slack;
a state measurement step of measuring, by the control unit, at least one state value
of the crane when the rope has been wound up into a taut state by the hoisting device
being driven; and
a transport control step of moving, by the control unit, the horizontal transport
device,
wherein the state measurement step includes identifying a payload location xp of a
grounded payload using a position x of the horizontal transport device and the at
least one state value measured when the rope is in a taut state, and
wherein the transport control step includes moving the horizontal transport device
to the identified payload location xp to position the rope directly above the payload.
11. The method of controlling the crane according to claim 10,
wherein the at least one state value is a distance L from the horizontal transport
device to the payload when the rope has been wound up into a taut state, and
wherein the state measurement step includes:
measuring the position x of the horizontal transport device and the distance L from
the horizontal transport device to the payload with a first sensor attached on the
horizontal transport device at least two points in a moving direction; and
calculating parameters p1 and p2 in x2 - L2 + p1 × x + p2 = 0 with results of the measurement and calculating a position x of
the horizontal transport device at which the distance L takes a minimum value as the
payload location xp, using the calculated parameters p1 and p2.
12. The method of controlling the crane according to claim 10,
wherein the rope is connected to the hook at an end and the hook is connected to a
sling member to hang the payload,
wherein the at least one state value is a rope length Lr when the rope has been wound
up into a taut state, and
wherein the state measurement step includes:
measuring the position x of the horizontal transport device and the rope length Lr
with a first sensor attached on the horizontal transport device at least three points
in a moving direction; and
calculating parameters p1, p2, and p3 in x2 - Lr2 + p1 × x + p2 × Lr + p3= 0 with results of the measurement and calculating a position
x of the horizontal transport device at which the rope length Lr takes a minimum value
as the payload location xp, using the calculated parameters p1, p2, and p3.
13. The method of controlling the crane according to claim 10,
wherein the at least one state value is a sway angle θ of the rope with respect to
the horizontal transport device when the rope has been wound up into a taut state,
and
wherein the state measurement step includes:
measuring the position x of the horizontal transport device and the sway angle θ of
the rope with a second sensor attached on the horizontal transport device at least
two points in a moving direction; and
calculating parameters p1 and p2 in x + p1 × tanθ + p2 = 0 with results of the measurement
and calculating a position x of the horizontal transport device at which the sway
angle θ takes a minimum value as the payload location xp, using the calculated parameters
p1 and p2.
14. The method of controlling the crane according to claim 10,
wherein the at least one state value comprises a tension T of the rope and a force
F horizontally acting on the horizontal transport device when the rope has been wound
up into a taut state, and
wherein the state measurement step includes:
measuring the position x of the horizontal transport device and the tension T of the
rope with a third sensor attached on the horizontal transport device and the horizontally
acting force F with a fourth sensor attached on the horizontal transport device at
least two points in a moving direction; and
calculating a sway angle θ of the rope and parameters p1 and p2 in x + p1 × tanθ +
p2 = 0 using θ = arcsin(F/T) and results of the measurement, and calculating a position
x of the horizontal transport device at which the sway angle θ takes a minimum value
as the payload location xp, using the calculated parameters p1 and p2.
15. The method of controlling the crane according to claim 10,
wherein the at least one state value comprises a length Lf of the rope paid out before
moving the horizontal transport device and a time Tf taken to wind up the rope into
a taut state, and
wherein the state measurement step includes:
measuring the position x of the horizontal transport device, the paid-out length Lf
of the rope, and the time Tf taken to wind up the rope into a taut state at least
three points in a moving direction and calculating a rope winding speed V from variations
t in the paid-out length Lf of the rope and the times Tf taken to wind up the rope
into a taut state; and
calculating parameters p1, p2, and p3 in x2 - dL2 + p1 × x + p2 × dL + p3 = 0 using dL = Lf - V × Tf and results of the measurement
and calculating a position x of the horizontal transport device at which dL takes
a minimum value as the payload location xp, using the calculated parameters p1, p2,
and p3.
16. The method of controlling the crane according to any one of claims 10 to 15, wherein
the state measurement step includes identifying a height H from the payload to the
horizontal transport device based on the at least one state value and the position
x of the horizontal transport device.
17. The method of controlling the crane according to claim 16, wherein the state measurement
step includes:
identifying the height H from the payload to the horizontal transport device based
on the at least one state value and the position x of the horizontal transport device
and identifying a length Lw of a sling member from a rope length Lr and the height
H.
18. The method of controlling the crane according to claim 12, wherein the state measurement
step includes:
identifying a length Lw of the sling member based on the at least one state value
and the position x of the horizontal transport device.