FIELD OF THE INVENTION
[0001] The present invention generally relates to Cabon Capture and Storage (CCS) technology,
and more particularly to a system for offloading liquid CO
2 (LCO
2) from an LCO
2 carrier ship to an intermediate LCO
2 storage tank at an LCO
2 receiving terminal connected to a long term LCO
2 storage facility, wherein cross-contamination from cargo of one ship to another,
via common intermediate storage tanks, can be avoided. The invention also relates
to a corresponding method. The invention uses a slip stream of LCO
2 withdrawn from a main stream of LCO
2 being offloaded to the terminal which is vaporised and returned to the LCO
2 carrier ship, and the vaporisation is used to providing cooling for complete or partial
reliquefaction of a boil-off gas stream withdrawn from the intermediate LCO
2 storage tank, and a resulting reliquefied fraction is returned to the intermediate
LCO
2 storage tank. The present invention also relates to a corresponding method.
BACKGROUND ART
[0002] Captured and liquefied carbon dioxide can be transported in the liquid phase (LCO
2) from various locations and customers to CO
2 receiving terminals at which the CO
2 will be temporarily stored in intermediate buffer storage tanks onshore, before being
pumped in a dense phase via a pipeline and injected into an offshore long term storage
reservoir. The purpose of the buffer storage is to allow for continuous injection
to the long-term storage reservoir despite intermittent LCO
2 cargo transfer from ship.
[0003] A general description of an outline of a CCS chain can be found in Conceptualization
of CO
2 Terminal for Offshore CCS Using System Engineering Process by Hyonjeong et al.
Energies, 2019, 12, 4350. Said CCS chain description includes the return of CO
2 carriers to consider the vaporised CO
2 (VCO
2) in returning carriers. According to Hyonjeong et al., the same volume of VCO
2 must be loaded into the carrier's cargo tank when unloading LCO
2 from the carrier to the CO
2 terminal. The carrier's cargo tank is displaced by the VCO
2 of the storage tanks at the terminal, while LCO
2 fills the storage tanks. There are two reasons for loading VCO
2 into the carrier's cargo tank. The first is to allow the pressure and temperature
of the cargo tank to be controlled during the unloading process. Constant pressure
and temperature facilitate the process. The second reason is to prevent the rapid
decrease in temperature due to Joule-Thomson cooling.
[0004] Thus, for example, during LCO
2 cargo transfer between ship and onshore intermediate storage, the displaced vapour
in the onshore intermediate storage tank could be returned to the CO
2 carrier ship via a vapour return connection for pressure maintenance in both sets
of tanks, i.e. of the carrier ship and of the intermediate storage of the CO
2 receiving terminal, respectively.
[0005] However, depending on origin and purity of the LCO
2 being received at the terminal, the vapour in the onshore storage tank or tanks may
contain impurities. In the event that restrictions are imposed on the vapour quality
of vapour being returned to the ship that are not met by the vapour composition in
the onshore storage, such impurities could pose a substantial impediment to the functioning
of the CCS chain. In particular, LCO
2 receiving terminals served by multiple customers, with CO
2 originating from various sources, could face challenges from a technical and commercial
point with undesired cross-contamination caused by impurities contained in the vapour
space of the onshore storage tanks when returned to the ships.
[0006] It would be desirable to enable pressure maintenance in both sets of tanks, i.e.
of the carrier ship and of the intermediate storage of the CO
2 receiving terminal, while reducing, and preferably avoiding, the risk of contaminating
an LCOz carrier tank at a ship in connection with offloading LCO
2 from the ship to an LCO
2 receiving terminal. Moreover, this should preferably be achieved in an energy efficient
manner.
[0007] It is an object of the present invention to provide a system and a method enabling
the above.
SUMMARY OF THE INVENTION
[0008] The present invention is based on using a slip stream of LCO
2, which is being withdrawn from a main stream LCO
2 being offloaded from a ship and imported to the terminal, for partially or completely
reliquefying a stream of boil-off gas being withdrawn from an intermediate storage
tank to which intermediate storage tank the LCO
2 main stream is being led, wherein the two streams are kept separate, and wherein
a reliquefied fraction from the stream of boil-off gas is led back to the storage
tank. The required cooling for reliquefaction of a fraction of the stream of boil-off
gas is accomplished by subjecting the LCO
2 slip stream to a reduced pressure. The resulting cold partly vaporised LCO
2 slip stream, and the stream of boil-off gas are led to a heat exchanger for exchange
of heat. After complete vaporisation of the LCO
2 slip stream, the resulting CO
2 vapour is led back to the ship in a vapour return conduit.
[0009] Accordingly, in one aspect the invention relates to a system
50 for offloading LCO
2 cargo from an LCO
2 carrier ship
30 to an intermediate LCO
2 storage tank
40 at an LCO
2 receiving terminal
100, which system avoids cross-contamination of cargo from one LCO
2 carrier ship
30 to another, said system comprising: an intermediate LCO
2 storage tank
40; a boil-off gas outlet
60 from the intermediate LCO
2 storage tank
40 configured to withdrawing boil-off gas from the intermediate LCO
2 storage tank
40; an LCO
2 cargo import conduit
1, 10 connected to the intermediate LCO
2 storage tank
40 configured to receive an LCO
2 cargo import stream from the LCO
2 carrier ship
30; a CO
2 vapour return conduit
4, 5, 6, 7, 8, 9 configured to be connected to the LCO
2 carrier ship
30 and to return from the system
50 CO
2 vapour to the LCO
2 carrier ship
30; an LCO
2 outlet
70 from the intermediate LCO
2 storage tank
40 configured to discharging LCO
2 from the intermediate LCO
2 storage tank
40; which system additionally comprises an LCO
2 slip stream conduit
2 connected to the LCO
2 cargo import conduit
1 configured to withdrawing a slip stream of LCO
2 from the LCO
2 cargo import conduit
1; a pressure let-down valve
A connected to the LCO
2 slip stream conduit
2 configured to receiving the slip stream of LCO
2 having a first temperature
11, and to exiting an at least partly vaporised stream of LCO
2 having a second lower temperature
T2; a partly vaporised stream conduit
3 connected to the pressure let-down valve
A configured to receiving the at least partly vaporised stream of LCO
2 having a second lower temperature
T2; a boil-off gas conduit
11 connected to the boil-off gas outlet
60; a first heat exchanger
B connected to the partly vaporised stream conduit
3 and to the boil-off gas conduit
11, respectively, said heat exchanger being configured to receiving the at least partly
vaporised stream of LCO
2 having the second lower temperature
T2, to receiving the boil-off gas withdrawn from the boil-off gas outlet
60, to transferring heat from the boil-off gas to the at least partly vaporised stream
of LCO
2 having the second lower temperature
T2, to exiting a reliquefied fraction from the boil-off gas and to exiting an at least
partly vaporised stream of LCO
2, respectively; a conduit
12, 15 connected to the intermediate LCO
2 storage tank
40 configured to receiving the exiting reliquefied fraction from the first heat exchanger
B; wherein the CO
2 vapour return conduit
4, 5, 6, 7,
8, 9 is further configured to receive CO
2 vapour resulting from the at least partly vaporised stream of LCO
2 having the second lower temperature
T2; and wherein a vapour return compressor
F is arranged along the vapour return conduit
4, 5, 6, 7, 8, 9 configured to compressing the CO
2 vapour to be returned to the LCO
2 carrier ship
30.
[0010] In a preferred embodiment of the system, the system additionally comprises means
C, D, E configured to vaporising a remaining non-vaporised fraction of the at least partly
vaporised stream of LCO
2 exiting the first heat exchanger
B.
[0011] In yet a preferred embodiment of the system, the system comprises means
G, 13, H, 14, configured to separate, compress, and direct a remaining gaseous fraction of the
boil-off gas after partial reliquefaction thereof into a stream of compressed LCO
2 withdrawn from the intermediate LCO
2 storage tank
40 to be injected into a pipeline
110 connected to an underground long term storage facility
120.
[0012] In another aspect, the invention relates to a method for offloading LCO
2 cargo from an LCO
2 carrier ship
30 to an intermediate LCO
2 storage tank
40 at an LCO
2 receiving terminal
100, avoiding cross-contamination of cargo from one LCO
2 carrier ship
30 to another, said method comprising the following steps: i. receiving a main stream
of LCO
2 from an LCO
2 carrier ship
30 and directing the main stream to an intermediate LCO
2 storage tank
40; ii. withdrawing LCO
2 from an LCO
2 outlet
70 from the intermediate LCO
2 storage tank
40; iii. withdrawing a stream of boil-off gas from a boil-off gas outlet
60 from the intermediate LCO
2 storage tank
40; iv. returning CO
2 vapour from the terminal
100 back to the LCO
2 carrier ship
30, which method additionally comprises the following steps:
v. withdrawing from the main stream of LCOz a slip stream of LCO
2;
vi. subjecting the withdrawn slip stream of LCO
2 having a first temperature
T1 to a reduced pressure, thereby partly vaporising the withdrawn LCO
2 slip stream having a first temperature
T1 so as to produce an at least partly vaporised LCO
2 slip stream having a second lower temperature
T2; vii. subjecting the withdrawn stream of boil-off gas to heat exchange with the at least
partly vaporised LCO
2 slip stream having the second lower temperature
T2, thereby completely or partially liquefying the boil-off gas;
viii. returning the resulting liquefied fraction to the intermediate LCO
2 storage tank
40; wherein, in step
iv., the CO
2 vapour from the terminal
100 being returned to the LCO
2 carrier ship
30 comprises a stream of CO
2 vapour obtained from the slip stream of LCO
2 and is subjected to compression before being returned to the ship.
[0013] In a preferred embodiment of the method, the method additionally comprises a step
ix. wherein a remaining non-vaporised fraction of the at least partly vaporised LCO
2 slip stream after heat exchange in step
vii. is vaporised, and, and wherein, in step
iv., the CO
2 vapour from the terminal being compressed and returned to the LCO
2 carrier ship
30 comprises the resulting CO
2 vapour from step
ix.
[0014] In yet a preferred embodiment of the method, the method additionally comprises the
step
x., wherein, after heat exchange in step
vii., a remaining non-liquefied gaseous fraction from the boil-off gas stream is separated
and directed into a stream of LCO
2 being withdrawn from the intermediate LCO
2 storage tank
40 and conveyed to an underground long term storage facility
120.
[0015] The present invention provides a method and system providing vapour return for pressure
support of LCO
2 carrier ship
30 tanks during liquid off-loading by generating vapours directly from the off-loading
cargo at the terminal
100, eliminating the risk for potential off-spec vapour return from the onshore storage
tank facility
40.
[0016] Also, the invention provides an energy efficient measure to reliquefy displaced vapour
in the onshore storage tanks
40, by heat integration with the ship vapour return
4, 5, 6, 7, 8, 9.
[0017] The present invention provides a method for a force-vaporising a slip stream of the
off-loaded LCO
2 cargo, providing vapour for pressure support to the ship tanks without ingress of
any potential contaminants from the main onshore storage facility. The system also
provides cooling duty for reliquefaction of displaced vapour in the onshore storage
tanks, reducing the energy requirements for the BOG system.
[0018] The present invention achieves the advantage of providing CO
2 vapour return to an off-loading LCO
2 carrier ship
30, independent of the content in the onshore storage tanks, i.e. avoiding exposure of
potential contaminants contained in the vapour space from previous off-loaded cargos,
such as from other LCO
2 carrier ships
30.
[0019] Further embodiments and advantages of the invention will be apparent from the following
detailed description and appended claims.
[0020] In the present disclosure, same reference numeral is used both to denote the conduit
and the stream flowing therein. For example, reference numeral
2 is used to both denote the slip stream conduit, and also to denote the slip stream
itself flowing in said conduit.
[0021] The term "long-term" as used herein denotes a storage intended to be permanent.
[0022] The present system and method may be combined with either one or both of the embodiments
disclosed applicant's co-pending applications filed on even date herewith.
BRIEF DESCRIPTION OF THE ATTACHED DRAWING
[0023] Figure 1 shows an embodiment of the inventive system
50 as indicated by the dashed line implemented into an LCO
2 receiving terminal
100. The inventive system
50 in its most generic embodiment does not include
C, D, E, which in a preferred embodiment can be arranged along the vapour return conduit
4, 5, 6, 7, 8, 9, and does also not include
G and
H, which in a preferred embodiment can be provided for separating out a remaining gaseous
fraction after partial liquefaction of the boil-off gas from the reliquefied conduit
12, 15, and does also not include
I, and
J, which are units conventionally included in a conventional LCO
2 receiving terminal
100, in which the inventive system
50 has not been implemented.
DETAILED DESCRIPTION OF THE INVENTION
[0024] The core of the invention is a process scheme that enables efficient heat integration
between the cold closed-circuit vapour return stream to LCO
2 carrier ship
30 and the warmer displaced boil-off gas from the onshore storage tanks
40. This is achieved by using a slip stream of the off-loaded LCO
2 cargo, which serves a dual purpose:
- as the CO2 pressure is let down to e.g. 7 barg, the temperature will drop to approximately -45°C,
providing refrigeration for the boil-off gas displaced during filling of onshore storage
tanks 40. This enables at least partial recovery of the boil-off gas, which is reliquefied
and returned to the storage tank 40;
- the cold low pressure LCO2 is vaporised by indirect heat exchange in the first heat exchanger B which enables a closed-circuit vapour return system, eliminating the risk for return
of vapour potentially containing incompatible impurities from previous ships existing
in the onshore storage tank facility.
[0025] In the above connection, a lower pressure will increase the cooling duty in the first
heat exchanger
B, but will also increase the compressor duty of vapour return compressor
F.
[0026] Without CO
2 vapour return from the LCO
2 receiving terminal
100 to the LCO
2 carrier ship
30, e.g. in order to avoid cross-contamination of the tanks of the LCO
2 carrier ship
30, vapour for pressure maintenance on the ship could possibly alternatively be generated
by force-vaporising liquid CO
2 cargo on the ship. Such solution is however considered inferior to the solution offered
by the invention, since, i.a., with such solution, the displaced vapour in the intermediate
LCO
2 storage tank or tanks
40 during filling will increase the sizing and energy requirements for the BOG system
of the LCO
2 receiving terminal
100.
[0027] In the embodiment of the invention illustrated in
FIG. 1, LCO
2 is offloaded from a ship
30 at pressures from e.g. 15-18 barg (denoted as medium pressure (MP), with a typical
saturation temperature between -30°C and -20°C).
[0028] A slip stream
2 of the off-loaded cargo
1 is fed to a pressure let-down control valve
A, where the pressure is let down to e.g. 6-10 barg (denoted as low pressure (LP), with
a typical saturation temperature between -50°C and -40°C).
[0029] The flow rate of the slip stream
2 will be determined by the off-loading rate, and typically around 5% of the total
flow will be required.
[0030] On the downstream side
3 of the pressure let-down valve
A a two-phase LP LCO
2 stream is fed to the first heat exchanger
B. In the embodiment in
FIG. 1 the first heat exchanger
B is depicted as a shell and tube heat exchanger but could alternatively be of another
type, such as a plate or plate-fin heat exchanger. In the first heat exchanger
B, the cold two-phase LP stream provides cooling of the vapour displaced
11 from the storage tank
40 during filling thereof. The displacement rate will depend on the filing rate
10, the injection rate
16, and the return of reliquefied boil-off gas
15.
[0031] Ideally, in a case of operation wherein the two-phase LP LCO
2 stream has been fully vaporised after heat exchange
4 in the first heat exchanger
B, the resulting CO
2 vapour is returned to the ship after compression of the CO
2 vapour stream
7 in a vapour return compressor
F.
[0032] Following heat exchange in the first heat exchanger
B in a case of operation wherein the partly vaporised LP LCO
2 stream
4 has not been fully vaporised, the stream is further vaporised in a second heat exchanger
C, using the warm discharge stream
8 of vapour from the vapour return compressor
F. In the inventive system, first and second heat exchangers
B and C, respectively, could be referred to as cross heat exchangers.
[0033] In case the heat content of the boil-off stream
11 and of the compressor discharge stream
8 are not sufficient to completely vaporise the LP LCO2, so that a partly vaporised
LCO
2 stream
5 remains after the second heat exchanger
C, a dedicated vaporiser
D is provided. The vaporiser
D could be heated electrically, by ambient sea water or other suitable heat sources
available at the terminal
100.
[0034] From the vaporiser
D the LP CO
2 6 is preferably fed to a knock-out drum
E to ensure that any remaining liquid droplets are not found in the suction flow
7 to the vapour return compressor
F.
[0035] The vapour return compressor
F will increase the pressure to be compatible with the ship cargo tank pressure. The
compressor discharge
8 is cooled by cross-heat exchange in heat exchanger
C, providing heat for vaporisation of a remaining liquid phase in the LP LCO2 stream
4 as described above.
[0036] Vapour
9 is returned to ship
30 at pressure and temperature compatible with the MP cargo at a rate that equals the
volumetric flow of off-loaded liquid
1.
[0037] As shown in the embodiment of the invention illustrated in
FIG. 1, the offloaded LCOz is split into two process sections. As described above, the LP
LCO2
2 is providing vapour for the displaced liquid in the ship cargo tanks
30 in a closed circuit
2, 3, 4, 5, 6, 7, 8, 9. The major part of the imported LCO
2 1 is transferred
10 at MP conditions to the intermediate storage tank(s)
40.
[0038] The storage tank or tanks
40 are operated at MP condition, and liquid CO
2 is transferred
16 to injection pump or pumps
I. In the embodiment of
FIG. 1, the injection pump
I is shown as a single pump but could also be configured in series with booster pumps.
The pump(s) provide sufficient head for dense phase CO
2 to be exported to a pipeline
110 and subsequently injected into a reservoir
120 for permanent storage. Downstream of the injection pump
17, an injection heater
J may be arranged to avoid sub-zero temperatures entering the pipeline at the landfall
19. The injection heater
J could for example be heated electrically, by ambient sea water or other suitable
heat sources available at the terminal.
[0039] The export flow rate
16 is likely to be lower than cargo transfer rate
10, hence, as the level in the intermediate storage tank
40 increases vapour will be displaced. To control pressure, the displaced vapour
11 will need to be processed, to avoid CO
2 emission to atmosphere by vent.
[0040] The displaced vapour
11 at MP conditions will be reliquefied against the colder LP LCO
2 stream
3 in a heat exchanger
B. Ideally, in a case of operation wherein the BOG and/or displaced vapour
11 can be completely reliquefied, the reliquefied BOG or reliquefied displaced vapour
can be returned to intermediate storage tank
40 via conduit
12, 15. In a case of operation wherein a gaseous fraction remains
12 after cooling in the vapour return heat exchanger
B, the partly reliquefied vapours
12 are fed to a two-phase separator
G, where reliquefied BOG/reliquefied displaced vapour is returned
15 to the intermediate storage tank
40. The gas phase
13, enriched with non-condensable impurities, is fed to a boil-off gas compressor
H and the effluent from the compressor is injected into high-pressure LCO
2 in the export conduit
18, where it will be dissolved, complying with single phase flow assurance requirements.
LIST OF REFERENCE SIGNS USED
[0041]
- 1, 10
- LCO2 cargo import conduit
- 2
- LCO2 slip stream conduit
- 3
- partly vaporised LCO2 stream conduit
- 4, 5, 6, 7, 8,
- 9 CO2 vapour return conduit
- 11
- boil-off gas conduit
- 12, 13, 14
- remaining gaseous fraction conduit (from boil-off gas)
- 12, 15
- reliquefied fraction conduit
- 16
- conduit connecting bottom outlet 70 with injection pump I
- 17
- conduit connecting outlet from injection pump with injection heater J
- 30
- LCO2 carrier ship
- 40
- intermediate LCO2 storage tank
- 50
- system for offloading LCO2 cargo (from an LCO2 carrier ship)
- 60
- boil-off gas outlet (from intermediate LCO2 storage tank)
- 70
- LCO2 outlet (from intermediate LCO2 storage tank)
- 100
- LCO2 receiving terminal
- 110
- pipeline
- 120
- underground long term storage facility
- T1
- first temperature (of slip stream)
- T2
- second lower temperature (of partly vaporised LCO2 stream)
- A
- pressure let-down valve
- B
- first heat exchanger
- C
- second heat exchanger
- D
- vaporiser
- E
- knock-out drum
- F
- vapour return compressor
- G
- two-phase separator
- H
- boil-off gas compressor
- I
- injection pump
- J
- injection heater
1. A system (50) for offloading LCO
2 cargo from an LCO
2 carrier ship (30) to an intermediate LCO
2 storage tank (40) at an LCO
2 receiving terminal (100), which system avoids cross-contamination of cargo from one
LCO
2 carrier ship (30) to another, said system comprising:
- an intermediate LCO2 storage tank (40);
- a boil-off gas outlet (60) from the intermediate LCO2 storage tank (40) configured to withdrawing boil-off gas from the intermediate LCO2 storage tank (40);
- an LCO2 cargo import conduit (1, 10) connected to the intermediate LCO2 storage tank (40) configured to receive an LCO2 cargo import stream from the LCO2 carrier ship (30);
- a CO2 vapour return conduit (4, 5, 6, 7, 8, 9) configured to be connected to the LCO2 carrier ship (30) and to return from the system (50) CO2 vapour to the LCO2 carrier ship (30);
- an LCO2 outlet (70) from the intermediate LCO2 storage tank (40) configured to discharging LCO2 from the intermediate LCO2 storage tank (40);
characterized in additionally comprising,
- an LCO2 slip stream conduit (2) connected to the LCO2 cargo import conduit (1) configured to withdrawing a slip stream of LCO2 from the LCO2 cargo import conduit (1);
- a pressure let-down valve (A) connected to the LCO2 slip stream conduit (2) configured to receiving the slip stream of LCO2 having a first temperature (T1), and to exiting an at least partly vaporised stream
of LCO2 having a second lower temperature (T2);
- a partly vaporised stream conduit (3) connected to the pressure let-down valve (A)
configured to receiving the at least partly vaporised stream of LCO2 having a second lower temperature (T2);
- a boil-off gas conduit (11) connected to the boil off gas outlet (60);
- a first heat exchanger (B) connected to the partly vaporised stream conduit (3)
and to the boil-off gas conduit (11), respectively, said heat exchanger being configured
to receiving the at least partly vaporised stream of LCO2 having the second lower temperature (T2), to receiving the boil-off gas withdrawn
from the boil-off gas outlet (60), to transferring heat from the boil-off gas to the
at least partly vaporised stream of LCO2 having the second lower temperature (T2), to exiting a reliquefied fraction from
boil-off gas and to exiting an at least partly vaporised stream of LCO2, respectively;
- a reliquefied fraction conduit (12, 15) connected to the intermediate LCO2 storage tank (40) configured to receiving the exiting reliquefied fraction from the
first heat exchanger (B);
- wherein the CO2 vapour return conduit (4, 5, 6, 7, 8, 9) is further configured to receiving CO2 vapour resulting from the at least partly vaporised stream of LCO2 having the second lower temperature (T2); and
- a vapour return compressor (F) arranged along the vapour return conduit (4, 5, 6,
7, 8, 9) configured to compressing the CO2 vapour to be returned to the LCO2 carrier ship (30).
2. The system (50) of claim 1, additionally comprising
- means (C, D, E) arranged along the CO2 vapour return conduit (4, 5, 6, 7, 8, 9) configured to vaporising a remaining non-vaporised
fraction of the at least partly vaporised stream of LCO2 exiting the first heat exchanger (B).
3. The system (50) of claim 1 or 2, additionally comprising
- an injection pump (I) connected via a conduit (16) to the LCO2 outlet (70) from the intermediate LCO2 storage tank (40) configured to receiving LCO2 withdrawn from the intermediate LCO2 storage tank (40), and to ejecting a stream of compressed LCO2 to be injected into a pipeline (110) connected to an underground long term storage
facility (120); and
- a remaining gaseous fraction conduit (12, 13, 14) and means (G,H) arranged along
said remaining gaseous fraction conduit (12, 13, 14) configured to receiving, separating
from the reliquefied fraction conduit (12, 15), and compressing, a remaining gaseous
fraction exiting the first heat exchanger (B) resulting from the boil-off gas, and
to injecting the resulting compressed gaseous fraction of the boil-off gas into a
stream of compressed LCO2 to be injected into a pipeline (110) connected to an underground long term storage
facility (120).
4. A method for offloading LCO
2 cargo from an LCO
2 carrier ship (30) to an intermediate LCO
2 storage tank (40) at an LCO
2 receiving terminal (100), avoiding cross-contamination of cargo from one LCO
2 carrier ship (30) to another, said method comprising the following steps:
i.) receiving a main stream of LCO2 from an LCO2 carrier ship (30) and directing the main stream to an intermediate LCO2 storage tank (40);
ii.) withdrawing LCO2 from an LCO2 outlet (70) from the intermediate LCO2 storage tank (40);
iii.) withdrawing a stream of boil-off gas from a boil-off gas outlet (60) from the
intermediate LCO2 storage tank (40);
iv.) returning CO2 vapour from the terminal (100) back to the LCO2 carrier ship (30),
characterized in additionally comprising the following steps:
v.) withdrawing from the main stream of LCOz a slip stream of LCO2;
vi.) subjecting the withdrawn slip stream of LCO2 having a first temperature (T1) to a reduced pressure, thereby partly vaporising
the withdrawn LCO2 slip stream having a first temperature (T1) so as to produce an at least partly vaporised
LCO2 slip stream having a second lower temperature (T2);
vii.) subjecting the withdrawn stream of boil-off gas to heat exchange with the at
least partly vaporised LCO2 slip stream having the second lower temperature (T2), thereby partly or completely
liquefying the stream of boil-off gas into a liquefied fraction;
viii.) returning the resulting liquefied fraction to the intermediate LCO2 storage tank (40);
wherein, in step (iv.), the CO
2 vapour from the terminal (100) being returned to the LCO
2 carrier ship (30) comprises a stream of CO
2 vapour obtained from the slip stream of LCO
2 and is subjected to compression before being returned to the ship.
5. The method for offloading LCO
2 cargo from an LCO
2 carrier ship (30) to an intermediate LCO
2 storage tank (40) at an LCO
2 receiving terminal (100) of claim 4, additionally comprising the following steps:
ix.) vaporising a remaining non-vaporised fraction of the at least partly vaporised
LCO2 slip stream after heat exchange in step (vii);
wherein, in step (iv.), the CO2 vapour from the terminal being compressed and returned to the LCO2 carrier ship (30) comprises the resulting CO2 vapour from step (ix.).
6. The method of claim 4 or 5, additionally comprising the step of:
x.) after heat exchange in step (vii.) separating and directing a remaining non-liquefied
gaseous fraction from the boil-off gas stream into a stream of LCO2 being withdrawn from the intermediate LCO2 storage tank (40) and conveyed to an underground long term storage facility (120).