Technical Field
[0001] The present invention relates to a blast-furnace operation method for restarting
blasting after the blasting of a blast furnace is stopped upon operation shutdown;
and a blast furnace used in such blast-furnace operation method.
Background Art
[0002] Conventionally, blast furnace operation is carried out on the premises that the operation
is never stopped after blowing-in except for short-period shutdowns involving scheduled
equipment repair, and that the operation itself shall continue though there may be
made operational adjustments such as reducing production volume. This is because there
is no economic rationality as the restart cost incurred by operation shutdown is enormous,
and there is no upward elasticity in terms of production volume as a period of about
half a year is required before restart once the operation is shutdown.
[0003] In the meantime, unlike up until now where steel demand has been consistently high globally
and there has been an underlying increase in its production, steel demand can now
change significantly in a short period of time due to the current unstable world economic
situation.
In this regard, flexibility to significant changes in production volume is now also
required for blast furnace operation, and banking, a process to stop the blast furnace
and put it into such a state where the operation can be resumed, has become increasingly
important.
[0004] A shutdown involving the refurbishment of a blast furnace takes place on the premise
that the shutdown lasts for a certain period of time; it is therefore common that
the furnace bottom part be disassembled to remove the coke, molten pig iron, and molten
slag that have accumulated therein. Meanwhile, in banking that assumes a flexible
restart depending on the economic situation, it is desired that such operation is
not conducted as it will lead to a prolonged shutdown period. However, if not removing
in-furnace residues, the coke remaining in the furnace will be combusted and consumed
to form smaller diameters, whereby there will be observed a deteriorated discharging
property of the molten pig iron and molten slag at the time of restart due to a decrease
in porosity. Further, the molten pig iron and molten slag that have remained due to
a decrease in furnace heat already have a deteriorated fluidity; therefore, if restarting
the blast-furnace operation without carrying out the discharge operation, there is
a high risk that a discharge failure of the molten pig iron and molten slag may occur,
and restart may even become impossible in the worst-case scenario.
[0005] With regard to the abovementioned problems, Patent Literature 1, for example, addresses
restriction of deterioration in discharging property at the time of restart by using
incombustibles with low-melting point compositions as incombustibles that are to be
put into the furnace for the purpose of avoiding troubles in the maintenance and repair
operation. Further, in Patent Literature 2, it was found that not only the smaller
diameters of the remaining coke that were formed by the combustion and consumption
thereof, but the pig iron, slag and the like adhering to such coke also contributed
to the increase in the amount of melt as they again melted at the time of restart.
As a result, in Patent Literature 2, the increase in the amount of melt at the time
of restart is prevented by charging new coke after purposefully combusting and eliminating
the aforementioned coke using a burner.
Citation List
Patent Literature
Summary of Invention
Technical Problem
[0007] However, in the case of Patent Literature 1, there is still a problem in that the
low-melting point incombustibles are in fact added from outside the system in addition
to the in-furnace slag generated upon operation restart, which results in a larger
amount of the molten slag that has to be discharged. Further, as compared to the conventional
technique, Patent Literature 2 is advanced in that the increase in the amount of melt
is restricted; however, the newly charged coke itself cannot be prevented from forming
smaller diameters when combusted, which leads to a problem that the longer the banking
lasts, the smaller the diameters of the coke will be when combusted and consumed,
and the less likely that the deterioration in discharging property caused thereby
is avoided.
[0008] It is an object of the present invention to provide a blast-furnace operation method
and blast furnace capable of realizing a smooth restart of a blast furnace by avoiding
deterioration in melt discharging property as a result of restricting coke from forming
smaller diameters due to combustion and consumption, which was not achievable by prior
patents.
Solution to Problem
[0009] The blast-furnace operation method of the present invention was developed to solve
the above problems. Specifically, the method of the invention is a blast-furnace operation
method for restarting blasting after the blasting of a blast furnace is stopped upon
operation shutdown, and this method includes:
a combustion step of combusting coke remaining in the furnace by blowing an oxygen-containing
gas into the furnace from a burner inserted into a tap hole after blasting is stopped,
and thereby reducing the volume of in-furnace residues;
a charging step of newly charging coke into a volume-reduced area formed in the combustion
step; and
a blasting step of restarting blasting from a tuyere,
wherein an introduction step of introducing an inert gas into the furnace is provided
during a period from after stopping blasting to before performing the blasting step.
[0010] Here, with regard to the blast-furnace operation method of the present invention
that is configured as above, it is considered that more preferable solutions can be
brought when:
- (1) a determination step of determining whether or not coke combustion in the blast
furnace is continuing is further provided after the introduction step;
- (2) in the determination step, gas concentration in the blast furnace is analyzed,
and it is determined that coke combustion in the blast furnace is continuing when
a CO gas concentration is as high as or higher than a threshold value;
- (3) if it is determined in the determination step that coke combustion in the blast
furnace is continuing, there is further performed an additional step of charging additional
coke into the furnace up to an upper region of the tuyere;
- (4) in the introduction step, the inert gas is introduced into the blast furnace in
an amount of not smaller than 7% and not larger than 13% per hour with respect to
the capacity of the blast furnace; and
- (5) in the introduction step, the inert gas is introduced into the blast furnace from
an introduction port formed above the tuyere of the blast furnace.
[0011] Further, the blast furnace of the present invention is a blast furnace configured
to perform the abovementioned blast-furnace operation method, and includes an introduction
port that is configured to introduce an inert gas and is formed above a tuyere.
Advantageous Effects of Invention
[0012] With the blast-furnace operation method of the present invention, by introducing
an inert gas into the blast furnace, coke in the blast furnace can be restricted from
forming smaller diameters, which is caused by the combustion and consumption of the
coke. In this way, the restart of a blast furnace can be performed smoothly as deterioration
in melt discharging property is prevented. Further, with the present invention, since
there is no need to keep the pressure inside the furnace positive, there is no risk
that the in-furnace gas may leak out of the furnace as a result of introducing an
inert gas, thereby allowing various operations to be carried out in parallel at the
periphery of the blast furnace.
Brief Description of Drawings
[0013]
[FIG.1] is a cross-sectional schematic diagram showing part of a furnace body cross-sectional
surface of a blast furnace.
[FIG.2] is a cross-sectional schematic diagram showing the furnace lower part of the
blast furnace of a state where a burner has been inserted from a tap hole.
[FIG.3] is a set of schematic diagrams showing one example of the burner.
[FIG.4] is a cross-sectional schematic diagram showing a state where the volume of
in-furnace residues has been reduced by burning the remaining coke with the burner.
[FIG.5] is a schematic diagram illustrating one embodiment of the furnace body of
the blast furnace configured to perform the blast-furnace operation method of the
present invention.
[FIG.6] is a graph showing a correlation between the amount of a N2 gas introduced into the furnace and a CO gas concentration in the furnace. Description
of Embodiments
[0014] An embodiment of the present invention is described in detail hereunder. Here, the
following embodiment is a set of examples of a device and/or method embodying the
technical concept of the present invention and is not to limit the configuration of
the present invention to those shown below. That is, various modifications can be
made to the technical concept of the present invention within the technical scope
described in the claims.
<Example of blast-furnace operation method and blast furnace as subjects of the present
invention>
[0015] FIG.1 is a cross-sectional schematic diagram showing part of a furnace body cross-sectional
surface of a blast furnace.
In the embodiment shown in FIG. 1, when stopping the blasting of the blast furnace for
a long period of time, blasting is stopped in such a way that the height of a raw
material-filled layer surface that is immediately above the tuyere(s) of the blast
furnace is lowered so as to be positioned lower than the upper end of the bosh zone
of the blast furnace. Later, when the blast furnace is put back into normal operation
by restarting blasting from the tuyere, a burner is at first inserted into the furnace
from the tap hole, whereby an oxygen-containing gas is or both an oxygen-containing
gas and a combustible gas are blown into the furnace from the burner so as to combust
the coke remaining in the furnace and thus reduce the volume of in-furnace residues
(combustion step).
[0016] FIG.2 is a cross-sectional schematic diagram showing the furnace lower part of the
blast furnace of a state where the burner has been inserted from the tap hole.
In the embodiment shown in FIG.2, since the tap hole is blocked by a material called
mud material when the blasting of the blast furnace is stopped, the tap hole blocked
by the mud material has to be opened at first so as to allow the burner to be inserted
into the furnace. The opening of the tap hole can be performed by a known tap hole
opener. The burner can be inserted into the furnace lower part of the blast furnace
from the tap hole after the tap hole is opened.
[0017] FIGs.3(a) and (b) are both schematic diagrams showing one example of the burner.
In the embodiments shown in FIGs.3(a) and (b), the burner has a double-pipe structure
composed of an inner pipe and outer pipe through which a gas flows. The burner also
has a cap that covers the end portions of the inner and outer pipes; and a thermocouple
that is provided outside the outer pipe and is used to measure the temperature of
the burner. When a cap is provided as is the case shown in FIG.3(a), a gas blown into
the burner from a gas introduction inlet of the inner pipe can be discharged from
a gas discharge outlet of the outer pipe without leaking outside. Meanwhile, when
there is provided no cap as is the case shown in FIG.3(b), the gas blown into the
burner from the gas introduction inlet of the inner pipe will be supplied into the
furnace. Thus, the burner has a function of being cooled by flowing a gas from the
inner pipe to the outer pipe with a cap being present, whereby the burner can be stably
inserted into the furnace.
[0018] Further, at the start of combustion, cooling by the gas flow from the inner pipe
to the outer pipe is stopped, whereby the cap is melted and removed by furnace heat
or the like so as to allow, for example, a combustible gas to be blown into the furnace
from the inner pipe of the burner and an oxygen-containing gas as a combustion-supporting
gas to be blown into the furnace lower part from the outer pipe of the burner. When
the temperature of the burner tip portion has exceeded the combustion start temperature
(approximately 800°C) of the coke that is present therearound, the coke will be burnt
by switching the gas blown from the burner to the oxygen-containing gas only. As the
oxygen-containing gas, it is preferred that pure oxygen is blown; however, there may
also be used a gas whose oxygen concentration is lower than 100% so long as coke combustion
can be sustained. Here, in this embodiment, there is shown an example where a combustible
gas and an oxygen-containing gas are blown from the burner; however, other than such
example, there may also be employed a configuration where only an oxygen-containing
gas is blown from the burner.
[0019] FIG.4 is a cross-sectional schematic diagram showing a state where the volume of
in-furnace residues has been reduced by burning the remaining coke with the burner.
In the embodiment shown in FIG.4, when coke has disappeared by combustion, more coke
will roll into the space from which the aforesaid coke has disappeared by combustion
depending on a repose angle, thereby causing coke to successively disappear by combustion,
thus reducing the volume of in-furnace residues.
[0020] Later, oxygen blowing from the burner is stopped, and unused coke is then charged
and loaded from the upper part of the blast furnace into a volume-reduced area which
is a space formed inside the furnace as a result of reducing the volume of in-furnace
residues (charging step). Next, oxygen is again blown from the burner to heat the
newly loaded coke, and when the temperature of the coke at the tuyere tip portion
has exceeded, for example, 2,000°C, a hot air of, for example, 1,100°C will be blasted
from the tuyere (blasting step), whereby the blast furnace is started up by switching
to heating from the tuyere.
<Characteristics of blast-furnace operation method and blast furnace of the present
invention>
[0021] The blast-furnace operation method and blast furnace of the present invention are
characterized in that there is provided an introduction step of introducing an inert
gas into the blast furnace during a period from after stopping blasting to before
performing the blasting step. Here, the "period from after stopping blasting to before
performing the blasting step" includes any time point selected from (1) a time point
after stopping blasting and before performing the combustion step; (2) a time point
after performing the combustion step and before performing the charging step; and
(3) a time point after performing the charging step and before performing the blasting
step. Of them, the time point (2) is preferred. If introducing an inert gas at the
time point (1), process delay will occur as coke combustion may be thwarted. If introducing
an inert gas at the time point (3), part of the unused coke charged in the charging
step will react due to a temperature rise in the furnace at the time point (2), thereby
diminishing the effect of the present invention.
[0022] In the blast-furnace operation method of the present invention, an inert gas is introduced
into the blast furnace in the introduction step, thereby restricting contact between
air and the coke charged in the volume-reduced area that is present between the tuyere
and the tap hole, thus restricting coke combustion. Here, as the inert gas, there
may be used various types of inert gases such as argon and nitrogen; nitrogen (N
2) is most suitable in terms of cost.
[0023] FIG.5 is a schematic diagram illustrating one embodiment of the furnace body of the
blast furnace configured to perform the blast-furnace operation method of the present
invention. As shown in FIG.5, the blast furnace is configured in such a manner that
a pipe serving as an introduction port is provided above the tuyere, and an inert
gas is introduced into the blast furnace from such introduction port. Here, in the
example shown in FIG.5, although the introduction port is provided immediately above
the tuyere, the introduction port may also be provided in the vicinity of the furnace
top of the blast furnace (e.g., a location that is about 5 m below the furnace top
of the blast furnace, provided that the height of the blast furnace is 100 m). By
providing the introduction port above the tuyere, hindrance to inert gas introduction
that is caused by the coke charged in the volume-reduced area between the tuyere and
the tap hole can be restricted. Further, since the introduction port for introducing
an inert gas is provided separately from other openings such as a raw material charging
port, the tuyere, and the tap hole, the inert gas introduction operation can be performed
without interfering with other operations and equipment as compared to a configuration
where the inert gas is introduced from other openings.
[0024] Here, the amount of the inert gas introduced into the blast furnace is determined
by the capacity of the blast furnace. Specifically, it is preferred that the inert
gas be introduced in an amount of not smaller than 7% and not larger than 13% per
hour with respect to the capacity of the blast furnace. The reason that this range
is preferable is because if the amount introduced is smaller than 7%, it is difficult
to restrict coke combustion due to the excessively small amount, and the combustion
restriction effect will remain the same even when the amount introduced is larger
than 13%.
[0025] Here, in the blast-furnace operation method of the present invention, it is preferred
that there is added a determination step of determining whether or not coke combustion
is still continuing in the blast furnace, after the introduction step of introducing
an inert gas into the blast furnace. Specifically, a gas analyzer is installed in
a recovery pipe (not shown) for collecting the gas discharged from the furnace top,
and this gas analyzer is used to analyze the gas concentration in the furnace (concentration
of gas discharged from the furnace top). Further, when the concentration of the CO
gas is high (as high as or higher than a threshold value), it will be determined that
coke combustion is continuing, and when the concentration of the CO gas is low (lower
than the threshold value), it will be determined that coke combustion is not continuing.
The threshold value of the CO gas concentration may, for example, be 1%.
[0026] Moreover, in the determination step, when it is determined that coke combustion is
still continuing, it is preferred that additional coke be charged into the furnace
up to an upper region of the tuyere, whereby the oxygen remaining in the furnace and
the coke above the tuyere that has been added can be reacted with each other (combusted).
In this way, the combustion and consumption of the coke that is present between the
tuyere and the tap hole can be restricted so that the coke between the tuyere and
the tap hole can be prevented from forming smaller diameters and contributing to a
poor discharging property caused thereby.
Examples
[0027] According to the abovementioned embodiment, in fact, a blast furnace having an inner
capacity of 5,000 m
3 was used, various amounts of N
2 gas were introduced into the furnace, and changes in the CO gas concentration in
the furnace were calculated. FIG.6 is a graph showing a correlation between the amount
of the N
2 gas introduced into the furnace and the CO gas concentration in the furnace. Here,
in the graph shown in FIG.6, plotting was omitted with regard to examples in which
the N
2 gas was introduced in amounts of smaller than 7%; incommensurably higher CO gas concentrations
(e.g., 8% or higher) were observed when the N
2 gas was introduced in amounts of smaller than 7% as compared to when it was introduced
in amounts of 7% or larger. In the examples, the CO gas concentration was about 0.8%
when the N
2 gas introduction amount was 7%; a sufficient decrease in CO gas concentration was
confirmed. Further, as a result of increasing the N
2 gas introduction amount to 10% for the purpose of completely restricting the combustion
and consumption of coke, while the N
2 gas introduction amount increased by 25% as compared to when the N
2 gas introduction amount was 8%, the CO gas concentration dropped to about 0.1% which
was an 80% decrease, indicating that the combustion and consumption of coke was able
to be restricted sufficiently. By using the present invention, a melt discharging
property at the time of starting up the blast furnace was ensured, whereby the blast
furnace was able to resume its process operations in 21 days after restart without
having to remove in-furnace residues.
1. A blast-furnace operation method for restarting blasting after the blasting of a blast
furnace is stopped upon operation shutdown, comprising:
a combustion step of combusting coke remaining in the furnace by blowing an oxygen-containing
gas into the furnace from a burner inserted into a tap hole after blasting is stopped,
and thereby reducing the volume of in-furnace residues;
a charging step of newly charging coke into a volume-reduced area formed in the combustion
step; and
a blasting step of restarting blasting from a tuyere,
wherein an introduction step of introducing an inert gas into the furnace is provided
during a period from after stopping blasting to before performing the blasting step.
2. The blast-furnace operation method according to claim 1, wherein a determination step
of determining whether or not coke combustion in the blast furnace is continuing is
further provided after the introduction step.
3. The blast-furnace operation method according to claim 2, wherein in the determination
step, gas concentration in the blast furnace is analyzed, and it is determined that
coke combustion in the blast furnace is continuing when a CO gas concentration is
as high as or higher than a threshold value.
4. The blast-furnace operation method according to claim 2 or 3, wherein when it is determined
in the determination step that coke combustion in the blast furnace is continuing,
there is further performed an additional step of charging additional coke into the
furnace up to an upper region of the tuyere.
5. The blast-furnace operation method according to claim 1, wherein in the introduction
step, the inert gas is introduced into the blast furnace in an amount of not smaller
than 7% and not larger than 13% per hour with respect to the capacity of the blast
furnace.
6. The blast-furnace operation method according to claim 1, wherein in the introduction
step, the inert gas is introduced into the blast furnace from an introduction port
formed above the tuyere of the blast furnace.
7. A blast furnace configured to perform the blast-furnace operation method according
to claim 1, comprising an introduction port that is configured to introduce an inert
gas and is formed above a tuyere.