TECHNICAL FIELD
[0001] The present disclosure relates to a system including a work machine, a work machine
controller, and a method of controlling a work machine.
BACKGROUND ART
[0002] For example,
WO2020/224768 (PTL 1) discloses a conventional wheel loader.
CITATION LIST
PATENT LITERATURE
SUMMARY OF INVENTION
TECHNICAL PROBLEM
[0004] A wheel loader repeatedly performs an excavation work and a loading work. In automating
the loading work, the wheel loader is demanded to adapt to loading into containers
in various shapes.
[0005] The present disclosure proposes a system including a work machine, a work machine
controller, and a method of controlling a work machine that enable automation of a
loading work for loading into containers in various shapes.
SOLUTION TO PROBLEM
[0006] According to one aspect of the present disclosure, a system including a work machine
is proposed, the system including a work machine main body, a work implement attached
to the work machine main body, the work implement including a bucket, a work implement
posture sensor that detects a posture of the work implement, an object sensor that
detects an object around the work machine main body, and a controller that communicates
with the work implement posture sensor and the object sensor. The controller stores
a trace of the work implement and a reference point of the container while the work
machine is operated to load loads in the bucket into a container. When a position
of the reference point is changed, the controller changes the trace in conformity
with the changed reference point.
[0007] According to one aspect of the present disclosure, a work machine controller is proposed.
A trace of a work implement and a reference point of a container while a work machine
is operated to load loads carried in the work implement into the container are stored
in the controller. When a position of the reference point is changed, the trace is
changed in conformity with the changed reference point.
[0008] According to one aspect of the present disclosure, a method of controlling a work
machine is proposed. The method includes storing a trace of a work implement and a
reference point of a container while the work machine is operated to load loads carried
in the work implement into the container and changing, when a position of the reference
point is changed, the trace in conformity with the changed reference point.
ADVANTAGEOUS EFFECTS OF INVENTION
[0009] According to the system including the work machine, the work machine controller,
and the method of controlling the work machine in the present disclosure, the loading
work for loading into containers in various shapes can be automated.
BRIEF DESCRIPTION OF DRAWINGS
[0010]
Fig. 1 is a side view of a wheel loader as an exemplary work machine.
Fig. 2 is a block diagram showing an overall configuration of a control system that
controls the wheel loader.
Fig. 3 is a plan view of the wheel loader that performs excavation and loading works.
Fig. 4 is a block diagram showing a configuration of an automatic control system that
controls the wheel loader.
Fig. 5 is a flowchart showing a flow of processing for recording work implement control
when a skilled operator performs loading into a container.
Fig. 6 is a diagram showing a trace of a work implement when the skilled operator
performs loading into the container.
Fig. 7 is a flowchart showing a flow of processing for editing a recorded parameter.
Fig. 8 shows a graph of change in cylinder length during a loading work.
Fig. 9 is a diagram schematically showing a posture of the wheel loader when a bucket
dump operation is started.
Fig. 10 is a diagram schematically showing a posture of the wheel loader when a cutting
edge reaches a farthest position.
Fig. 11 is a diagram schematically showing a posture of the wheel loader when the
bucket dump operation is stopped.
Fig. 12 is a diagram schematically showing a posture of the wheel loader when a boom
raising operation is stopped.
Fig. 13 is a diagram schematically showing a posture of the wheel loader when a bucket
tilt operation is started.
Fig. 14 is a diagram schematically showing a posture of the wheel loader when the
bucket tilt operation is stopped.
Fig. 15 is a flowchart showing a flow of second processing for editing a parameter.
Fig. 16 is a schematic diagram showing a feature point in accordance with a vessel
different in vehicle rank.
Fig. 17 is a schematic diagram showing a reference point when a loading position in
a dump truck is changed.
Fig. 18 is a flowchart showing a flow of processing for loading loads carried in the
bucket into the container under automatic control.
DESCRIPTION OF EMBODIMENTS
[0011] An embodiment will be described below with reference to the drawings. The same components
and constituent elements in the description below have the same reference characters
allotted and their labels and functions are also the same. Therefore, detailed description
thereof will not be repeated. Extraction of any features from the embodiment and any
combination thereof are also originally intended.
<Overall Construction of Wheel Loader 1>
[0012] In an embodiment, a wheel loader 1 as an exemplary work machine will be described.
Fig. 1 is a side view of wheel loader 1 as an exemplary work machine.
[0013] As shown in Fig. 1, wheel loader 1 includes a vehicular body frame 2, a work implement
3, a travel apparatus 4, and a cab 5. A vehicular body of wheel loader 1 is composed
of vehicular body frame 2, cab 5, and the like. Work implement 3 and travel apparatus
4 are attached to the vehicular body of wheel loader 1. A main body of wheel loader
1 includes the vehicular body and travel apparatus 4.
[0014] Travel apparatus 4 serves for travel of the vehicular body of wheel loader 1 and
includes running wheels 4a and 4b. Wheel loader 1 is a wheeled vehicle provided with
running wheels 4a and 4b as rotational bodies for travel, on opposing sides in a lateral
direction of the vehicular body. Wheel loader 1 is self-propelled as running wheels
4a and 4b are rotationally driven and can perform desired works with work implement
3. Travel apparatus 4 corresponds to an exemplary travel unit.
[0015] A direction in which wheel loader 1 travels straight is herein referred to as a fore/aft
direction of wheel loader 1. In the fore/aft direction of wheel loader 1, a side where
work implement 3 is arranged with respect to vehicular body frame 2 is defined as
the fore direction and a side opposite to the fore direction is defined as the aft
direction. The lateral direction of wheel loader 1 refers to a direction orthogonal
to the fore/aft direction when wheel loader 1 on a flat ground is viewed in a plan
view. A right side and a left side in the lateral direction when one faces the fore
direction are defined as a right direction and a left direction, respectively. An
upward/downward direction of wheel loader 1 is a direction orthogonal to the plane
defined by the fore/aft direction and the lateral direction. A side where the ground
is located and a side where the sky is located in the upward/downward direction are
defined as a lower side and an upper side, respectively.
[0016] Vehicular body frame 2 includes a front frame 2a and a rear frame 2b. Front frame
2a is arranged in front of rear frame 2b. Front frame 2a and rear frame 2b are attached
to each other as being laterally operable.
[0017] A pair of steering cylinders 11 is attached across front frame 2a and rear frame
2b. Steering cylinder 11 is a hydraulic cylinder. As steering cylinder 11 extends
and contracts with hydraulic oil from a steering pump, a direction of travel of wheel
loader 1 laterally changes. Vehicular body frame 2 in an articulated structure is
composed of front frame 2a and rear frame 2b. Wheel loader 1 is an articulated work
machine in which front frame 2a and rear frame 2b are coupled to allow a flection
operation.
[0018] Work implement 3 and a pair of running wheels (front wheels) 4a are attached to front
frame 2a. Work implement 3 is attached in front of the main body of wheel loader 1.
Work implement 3 is supported by the vehicular body of wheel loader 1. Work implement
3 includes a boom 14 and a bucket 6. Bucket 6 is arranged at a tip end of work implement
3. Bucket 6 is a work tool for excavation and loading. A cutting edge 6a is a tip
end portion of bucket 6. A rear surface 6b is a part of an outer surface of bucket
6. Rear surface 6b is formed from a plane. Rear surface 6b extends rearward from cutting
edge 6a.
[0019] Boom 14 has a base end portion rotatably attached to front frame 2a by a boom pin
9. Bucket 6 is rotatably attached to boom 14 by a bucket pin 17 located at a tip end
of boom 14. Boom pin 9 and bucket pin 17 correspond to a plurality of articulations
of work implement 3.
[0020] Work implement 3 further includes a bell crank 18 and a link 15. Bell crank 18 is
rotatably supported on boom 14 by a support pin 18a located substantially in a center
of boom 14. Link 15 is coupled to a coupling pin 18c provided at a tip end portion
of bell crank 18. Link 15 couples bell crank 18 and bucket 6 to each other.
[0021] Front frame 2a and boom 14 are coupled to each other by a pair of boom cylinders
16. Boom cylinder 16 is a hydraulic cylinder. Boom cylinder 16 rotationally drives
boom 14 upward and downward around boom pin 9. Boom cylinder 16 has a base end attached
to front frame 2a. Boom cylinder 16 has a tip end attached to boom 14. Boom cylinder
16 is a hydraulic actuator that operates boom 14 upward and downward with respect
to front frame 2a. With movement upward and downward of boom 14, bucket 6 attached
at the tip end of boom 14 also moves upward and downward.
[0022] A bucket cylinder 19 couples bell crank 18 and front frame 2a to each other. Bucket
cylinder 19 has a base end attached to front frame 2a. Bucket cylinder 19 has a tip
end attached to a coupling pin 18b provided at a base end portion of bell crank 18.
Bucket cylinder 19 is a hydraulic actuator to cause bucket 6 to pivot upward and downward
with respect to boom 14. Bucket cylinder 19 is a work tool cylinder that drives bucket
6. Bucket cylinder 19 rotationally drives bucket 6 around bucket pin 17. Bucket 6
is constructed as being operable with respect to boom 14. Bucket 6 is constructed
as being operable with respect to front frame 2a.
[0023] Boom cylinder 16 and bucket cylinder 19 correspond to an exemplary work implement
actuator that drives work implement 3.
[0024] Cab 5 on which an operator rides and a pair of running wheels (rear wheels) 4b are
attached to rear frame 2b. Cab 5 in a box shape is arranged in the rear of boom 14.
Cab 5 is carried on vehicular body frame 2. In cab 5, a seat where the operator of
wheel loader 1 is seated, an operation apparatus 8 which will be described later,
and the like are arranged.
[0025] Cab 5 is provided with a perception device 111. Perception device 111 is arranged,
for example, in a ceiling portion of cab 5. Perception device 111 is mounted, for
example, on an upper surface of cab 5. Perception device 111 is arranged, for example,
in a front portion of cab 5. Perception device 111 is attached to cab 5, for example,
as facing forward, and it can obtain information on the front of cab 5. Details of
perception device 111 will be described later.
<System Configuration>
[0026] Fig. 2 is a block diagram showing an overall configuration of a control system that
controls wheel loader 1.
[0027] An engine 21 is a drive source that generates drive force to drive work implement
3 and travel apparatus 4, and it is, for example, a diesel engine. A motor driven
by a power storage, instead of engine 21, may be employed as the drive source, or
both of the engine and the motor may be employed. Output from engine 21 is controlled
by adjustment of an amount of fuel to be injected into a cylinder of engine 21.
[0028] Drive force generated by engine 21 is transmitted to a transmission 23. Transmission
23 converts drive force into appropriate torque and a rotation speed. An axle 25 is
connected to an output shaft of transmission 23. Drive force converted by transmission
23 is transmitted to axle 25. Drive force is transmitted from axle 25 to running wheels
4a and 4b (Fig. 1). Wheel loader 1 thus travels. In wheel loader 1 in the embodiment,
both of running wheel 4a and running wheel 4b implement drive wheels for travel of
wheel loader 1 upon receiving drive force.
[0029] Some of drive force from engine 21 is transmitted to a work implement pump 13. Work
implement pump 13 is a hydraulic pump driven by engine 21 to activate work implement
3 with hydraulic oil it delivers. Work implement 3 is driven by hydraulic oil from
work implement pump 13. Hydraulic oil delivered by work implement pump 13 is supplied
to boom cylinder 16 and bucket cylinder 19 through a main valve 32. As boom cylinder
16 extends and contracts upon receiving supply of hydraulic oil, boom 14 moves upward
and downward. As bucket cylinder 19 extends and contracts upon receiving supply of
hydraulic oil, bucket 6 pivots upward and downward.
[0030] Wheel loader 1 includes a vehicular body controller 50. Vehicular body controller
50 includes an engine controller 60, a transmission controller 70, and a work implement
controller 80.
[0031] Vehicular body controller 50 is generally implemented by reading of various programs
by a central processing unit (CPU). Vehicular body controller 50 includes a not-shown
memory. The memory functions as a work memory, and various programs for performing
functions of wheel loader 1 are stored in the memory.
[0032] Operation apparatus 8 is provided in cab 5. Operation apparatus 8 is operated by
an operator. Operation apparatus 8 includes a plurality of types of operation members
operated by the operator to operate wheel loader 1. Operation apparatus 8 includes
an accelerator pedal 41 and a work implement control lever 42. Operation apparatus
8 may include a steering wheel, a shift lever, and the like which are not shown.
[0033] Accelerator pedal 41 is operated to set the target number of rotations of engine
21. Engine controller 60 controls output from engine 21 based on an amount of operation
onto accelerator pedal 41. With increase in amount of operation (amount of pressing)
onto accelerator pedal 41, output from engine 21 increases. With decrease in amount
of operation onto accelerator pedal 41, output from engine 21 decreases. Transmission
controller 70 controls transmission 23 based on the amount of operation onto accelerator
pedal 41.
[0034] Work implement control lever 42 is operated to operate work implement 3. Work implement
controller 80 controls electromagnetic proportional control valves 35 and 36 based
on the amount of operation onto work implement control lever 42.
[0035] Electromagnetic proportional control valve 35 switches main valve 32 such that bucket
cylinder 19 contracts to move bucket 6 in a dump direction (a direction in which the
cutting edge of bucket 6 is lowered). Electromagnetic proportional control valve 35
switches main valve 32 such that bucket cylinder 19 extends to move bucket 6 in a
tilt direction (a direction in which the cutting edge of bucket 6 is raised). Electromagnetic
proportional control valve 36 switches main valve 32 such that boom cylinder 16 contracts
to lower boom 14. Electromagnetic proportional control valve 36 switches main valve
32 such that boom cylinder 16 extends to raise boom 14.
[0036] A machine monitor 51 shows various types of information upon receiving input of a
command signal from vehicular body controller 50. The various types of information
shown on machine monitor 51 may be, for example, information on works performed by
wheel loader 1, vehicular body information such as an amount of remaining fuel, a
temperature of coolant, and a temperature of hydraulic oil, an image of surroundings
obtained by image pick-up of the surroundings of wheel loader 1, and the like. Machine
monitor 51 may be implemented by a touch panel, and in this case, a signal generated
by touching by the operator onto a part of machine monitor 51 is outputted from machine
monitor 51 to vehicular body controller 50.
<Excavation and Loading Works>
[0037] Wheel loader 1 in the present embodiment performs excavation and loading works to
scoop an excavation target such as soil and to load the excavation target onto a loading
target such as a dump truck. Fig. 3 is a plan view of wheel loader 1 that performs
excavation and loading works. Fig. 3 illustrates wheel loader 1 that performs what
is called a V shape work.
[0038] Fig. 3 (A) illustrates wheel loader 1 that performs what is called unloaded forward
travel. Wheel loader 1 travels forward along an excavation path R1 toward an excavation
target 310 such as soil. Wheel loader 1 plunges bucket 6 into excavation target 310
and stops forward travel. By raising bucket 6 with cutting edge 6a of bucket 6 dug
into excavation target 310, the excavation work to scoop excavation target 310 in
bucket 6 is performed.
[0039] Fig. 3 (B) illustrates wheel loader 1 that performs what is called loaded rearward
travel. Excavation target 310 has been loaded in bucket 6. Wheel loader 1 travels
rearward along excavation path R1 to a position from which it started forward travel
in Fig. 3 (A).
[0040] Fig. 3 (C) illustrates wheel loader 1 that performs what is called loaded forward
travel. With excavation target 310 having been loaded in bucket 6, wheel loader 1
travels forward toward a vessel 301 of a dump truck 300. Wheel loader 1 travels forward
along a loading path R2 from the position where it started forward travel in Fig.
3 (A) toward dump truck 300. When wheel loader 1 approaches dump truck 300 and reaches
a prescribed position, it loads excavation target 310 in bucket 6 into vessel 301.
Vessel 301 corresponds to an exemplary "container" into which loads carried in work
implement 3 are to be loaded.
[0041] Fig. 3 (D) illustrates wheel loader 1 that performs what is called unloaded rearward
travel. While bucket 6 is empty as a result of full ejection of excavation target
310 in bucket 6 into vessel 301 of dump truck 300, wheel loader 1 travels rearward
along loading path R2 to the position where it started forward travel in Fig. 3 (C).
[0042] Wheel loader 1 can thus repeatedly perform a series of works including excavation,
rearward travel, dump approach, soil ejection, and rearward travel.
<Automatic Control System that Controls Wheel loader 1>
[0043] In automating a loading work for loading onto dump truck 300 by wheel loader 1, in
order to more quickly perform the loading work while an amount of works is ensured
without contact of bucket 6 with vessel 301, reproduction of operations of work implement
3 by a skilled operator under automatic control has been desired. Fig. 4 is a block
diagram showing a configuration of an automatic control system that controls wheel
loader 1.
[0044] An automation controller 100 is configured to transmit and receive a signal to and
from vehicular body controller 50 described with reference to Fig. 2. Automation controller
100 is configured to transmit and receive a signal to and from an external information
obtaining unit 110. External information obtaining unit 110 includes perception device
111 and a positional information obtaining device 112. Perception device 111 and positional
information obtaining device 112 are mounted on wheel loader 1.
[0045] Perception device 111 obtains information on surroundings of wheel loader 1. Perception
device 111 is attached, for example, to a front portion of the upper surface of cab
5. Perception device 111 corresponds to an exemplary "object sensor" that detects
an object around the main body of wheel loader 1.
[0046] Perception device 111 contactlessly detects a direction of an object outside wheel
loader 1 and a distance to the object. Perception device 111 is implemented, for example,
by light detection and ranging (LiDAR) that obtains information on an object by emission
of laser beams. Perception device 111 may be implemented by a visual sensor including
a camera. Perception device 111 may be implemented by radio detection and ranging
(Radar) that obtains information on an object by emission of radio waves. Perception
device 111 may be implemented by an infrared sensor.
[0047] Positional information obtaining device 112 obtains information on a current position
of wheel loader 1. Positional information obtaining device 112 obtains, for example,
positional information of wheel loader 1 in a global coordinate system with the Earth
being defined as a reference, with the use of a satellite positioning system. Positional
information obtaining device 112 uses, for example, global navigation satellite systems
(GNSS) and includes a GNSS receiver. The satellite positioning system calculates a
position of wheel loader 1 by computing a position of an antenna of the GNSS receiver
based on a positioning signal received from a satellite by the GNSS receiver.
[0048] External information on the outside of wheel loader 1 obtained by perception device
111 and positional information of wheel loader 1 obtained by positional information
obtaining device 112 are inputted to automation controller 100.
[0049] Vehicular body controller 50 is configured to transmit and receive a signal to and
from a vehicle information obtaining unit 120, and receives input of information on
wheel loader 1 obtained by vehicle information obtaining unit 120. Vehicle information
obtaining unit 120 is composed of various sensors mounted on wheel loader 1. Vehicle
information obtaining unit 120 includes an articulation angle sensor 121, a vehicle
speed sensor 122, a boom angle sensor 123, a bucket angle sensor 124, and a boom cylinder
pressure sensor 125.
[0050] Articulation angle sensor 121 detects an articulation angle which is an angle formed
between front frame 2a and rear frame 2b, and generates a signal indicating the detected
articulation angle. Articulation angle sensor 121 outputs a signal indicating the
articulation angle to vehicular body controller 50.
[0051] Vehicle speed sensor 122 detects a speed of movement of wheel loader 1 by travel
apparatus 4, for example, by detection of a rotation speed of an output shaft of transmission
23 and generates a signal indicating the detected vehicle speed. Vehicle speed sensor
122 outputs the signal indicating the vehicle speed to vehicular body controller 50.
Vehicle speed sensor 122 corresponds to an exemplary travel sensor that detects a
status of travel of travel apparatus 4 (travel unit).
[0052] Boom angle sensor 123 is implemented, for example, by a rotary encoder provided in
boom pin 9 which is a portion of attachment of boom 14 to vehicular body frame 2.
Boom angle sensor 123 detects an angle of boom 14 with respect to a horizontal direction
and generates a signal indicating the detected angle of boom 14. Boom angle sensor
123 outputs the signal indicating the angle of boom 14 to vehicular body controller
50.
[0053] Bucket angle sensor 124 is implemented, for example, by a rotary encoder provided
in support pin 18a which is a rotation shaft of bell crank 18. Bucket angle sensor
124 detects an angle of bucket 6 with respect to boom 14 and generates a signal indicating
the detected angle of bucket 6. Bucket angle sensor 124 outputs the signal indicating
the angle of bucket 6 to vehicular body controller 50.
[0054] Boom angle sensor 123 and bucket angle sensor 124 correspond to an exemplary "work
implement posture sensor" that detects a posture of work implement 3.
[0055] Boom cylinder pressure sensor 125 detects a pressure on a bottom side (boom bottom
pressure) of boom cylinder 16 and generates a signal indicating the detected boom
bottom pressure. The boom bottom pressure becomes higher while bucket 6 is loaded
and becomes lower while the bucket is unloaded. Boom cylinder pressure sensor 125
outputs a signal indicating the boom bottom pressure to vehicular body controller
50.
[0056] Vehicular body controller 50 outputs information inputted from vehicle information
obtaining unit 120 to automation controller 100. Automation controller 100 receives
detection values from vehicle speed sensor 122, boom angle sensor 123, and bucket
angle sensor 124 through vehicular body controller 50.
[0057] An actuator 140 is configured to transmit and receive a signal to and from vehicular
body controller 50. Upon receiving a command signal from vehicular body controller
50, actuator 140 is driven. Actuator 140 includes a brake EPC (electromagnetic proportional
control valve) 141 for activation of a brake of travel apparatus 4, a steering EPC
142 for adjustment of a travel direction of wheel loader 1, a work implement EPC 143
for operations of work implement 3, and a hydraulic mechanical transmission (HMT)
144.
[0058] Electromagnetic proportional control valves 35 and 36 shown in Fig. 2 implement work
implement EPC 143. Transmission 23 shown in Fig. 2 is implemented as HMT 144 that
utilizes electronic control. Transmission 23 may be a hydro-static transmission (HST).
A power transmission apparatus that transmits motive power from engine 21 to running
wheels 4a and 4b may include an electric drive apparatus such as a diesel electric
drive apparatus, and may include any combination of the HMT, the HST, and the electric
drive apparatus.
[0059] Transmission controller 70 includes a brake control unit 71 and an accelerator control
unit 72. Brake control unit 71 outputs a command signal for control of activation
of the brake to brake EPC 141. Accelerator control unit 72 outputs a command signal
for control of the vehicle speed to HMT 144.
[0060] Work implement controller 80 includes a steering control unit 81 and a work implement
control unit 82. Steering control unit 81 outputs a command signal for control of
the travel direction of wheel loader 1 to steering EPC 142. Work implement control
unit 82 outputs a command signal for control of operations of work implement 3 to
work implement EPC 143.
[0061] Automation controller 100 includes a position estimator 101, a path planning unit
102, and a path tracking control unit 103.
[0062] Position estimator 101 estimates an own position of wheel loader 1 based on the positional
information obtained by positional information obtaining device 112. Position estimator
101 recognizes a target position based on the external information obtained by perception
device 111. The target position is, for example, a position of excavation target 310
or dump truck 300 shown in Fig. 3. Position estimator 101 can obtain a prescribed
reference point of dump truck 300, such as a position of an upper end of a side surface
of vessel 301. Perception device 111 may recognize the target position and input the
target position to automation controller 100, or position estimator 101 may recognize
the target position based on a result of detection by perception device 111.
[0063] Path planning unit 102 generates an optimal path of wheel loader 1 in automatic control
of wheel loader 1. The optimal path includes a path for travel by travel apparatus
4 and a path for operations of work implement 3. For example, path planning unit 102
generates an optimal path of wheel loader 1 that performs loaded forward travel toward
dump truck 300 and an optimal path of wheel loader 1 that moves away from dump truck
300 in unloaded rearward travel, in the loading work for loading onto dump truck 300.
Path planning unit 102 generates an optimal path that connects a current own position
of wheel loader 1 to a target position to which wheel loader 1 is headed from now,
while the loading work for loading onto dump truck 300 is performed.
[0064] A path for travel by travel apparatus 4 included in the optimal path may be generated
based on an actual travel record based on the operation by the operator. Alternatively,
the path for travel may be a travel path obtained by computation.
[0065] Path tracking control unit 103 controls the accelerator, the brake, and steering
such that wheel loader 1 travels as following the optimal path generated by path planning
unit 102. Path tracking control unit 103 outputs a command signal for travel of wheel
loader 1 along the optimal path to brake control unit 71, accelerator control unit
72, and steering control unit 81. Path tracking control unit 103 controls boom cylinder
16 and bucket cylinder 19 such that work implement 3 operates along the optimal path
generated by path planning unit 102. Path tracking control unit 103 outputs a command
signal for movement of work implement 3 along the optimal path to work implement control
unit 82.
[0066] An interface 130 is configured to transmit and receive a signal to and from vehicular
body controller 50. Interface 130 includes a mode selection operation portion 131,
an engine emergency stop switch 132, and a mode indicator 133.
[0067] Mode selection operation portion 131 is operated by the operator. The operator selects
an operation mode of wheel loader 1 by operating mode selection operation portion
131. The operation mode of wheel loader 1 includes a manual mode in which wheel loader
1 is manually operated and an auto mode in which wheel loader 1 is automatically controlled.
The operation mode includes a record & edition mode in which an actual work based
on the operation by the operator is recorded and a parameter recorded during the work
is edited in order to generate the optimal path in automatic control of wheel loader
1.
[0068] While the manual mode is selected, works are performed by the operation by the operator.
While the auto mode is selected, wheel loader 1 is automatically controlled to perform
works. When the operator operates wheel loader 1 to perform works with the record
& edition mode having been selected, those works are recorded, a feature point in
the trace of work implement 3 during those works is extracted, and the position and
the posture of work implement 3 at each feature point are determined. A path that
sequentially follows feature points is generated, and this generated path is defined
as a path for operations of work implement 3 under automatic control of wheel loader
1.
[0069] Engine emergency stop switch 132 is operated by the operator. When an event that
requires emergency stop of engine 21 occurs, the operator operates engine emergency
stop switch 132. A signal resulting from an operation onto mode selection operation
portion 131 and engine emergency stop switch 132 is inputted to vehicular body controller
50.
[0070] Mode indicator 133 indicates whether wheel loader 1 is currently in the manual mode
in which the manual operation by the operator is performed, the auto mode in which
the wheel loader is automatically controlled, or the record & edition mode. Vehicular
body controller 50 outputs a command signal for control of turn-on of the indicator
to mode indicator 133.
<Records of Works (Records) by Skilled Operator>
[0071] Fig. 5 is a flowchart showing a flow of processing for recording work implement control
when the skilled operator performs loading works for loading of loads in bucket 6
into vessel 301 of dump truck 300.
[0072] Initially, as advance preparation, before start of the loading work, in step S100,
the operator selects the operation mode of wheel loader 1. The operator operates mode
selection operation portion 131 to select the record & edition mode. The operation
onto mode selection operation portion 131 may be an operation onto a button or an
operation onto a monitor.
[0073] In step S101, a shape of vessel 301 of dump truck 300 which is a container into which
loads are to be loaded is recognized. For example, the shape of dump truck 300 is
obtained by LiDAR which is perception device 111. Point group data indicating three-dimensional
coordinate values of measurement points on dump truck 300 is obtained by irradiating
dump truck 300 with laser beams from LiDAR. Dump truck 300 is sensed from four directions
of the fore direction, the aft direction, the right direction, and the left direction,
and the shape of vessel 301 can be recognized based on information on a point group.
The recognized shape of vessel 301 is inputted to automation controller 100.
[0074] In step S102, perception device 111 recognizes a reference point P of vessel 301
of dump truck 300. Dump truck 300 is detected by LiDAR which is perception device
111. Automation controller 100 recognizes the position of vessel 301 based on comparison
between the point group detected by perception device 111 and a master point group
representing the shape of vessel 301. Automation controller 100 sets as reference
point P, the upper end of the side surface of vessel 301 of dump truck 300 recognized
by LiDAR which is perception device 111.
[0075] In generation of the travel path based on the actual travel record based on operations
by the operator, reference point P is determined based on a position at the time when
loading is performed. In this case, perception device 111 detects a loading position
at the position of vessel 301 in the loading work and obtains reference point P based
on the loading position.
[0076] After processing in steps S101 and S102, in step S103, the operator who is in wheel
loader 1 performs an operation to load loads in bucket 6 into vessel 301. As described
with reference to Fig. 3 (C) and (D), the operator controls wheel loader 1 where loads
are carried in work implement 3 (bucket 6) to travel forward toward vessel 301. The
operator operates work implement 3 (boom 14 and bucket 6) at appropriate timing, and
switches a travel direction of wheel loader 1 from forward travel to rearward travel
at appropriate timing. The operator thus has the loads carried in work implement 3
(bucket 6) loaded into bucket 301.
[0077] Fig. 6 is a diagram showing a trace of work implement 3 when the skilled operator
performs loading into vessel 301. Fig. 6 and subsequent Figs. 9 to 14 schematically
show vessel 301 viewed from the fore/aft direction of dump truck 300, and schematically
show a part on a front side of wheel loader 1 that approaches vessel 301 from the
left side or the right side of dump truck 300. Wheel loader 1 travels over a flat
ground G. Ground G over which wheel loader 1 travels is horizontal.
[0078] A trace TR shown in Fig. 6 is a trace followed by cutting edge 6a of bucket 6 during
a period from a time point when wheel loader 1 starts forward travel (dump approach)
toward dump truck 300 for loading loads in bucket 6 into vessel 301 until wheel loader
1 moves away from dump truck 300 after it ejects the loads in bucket 6 into vessel
301.
[0079] As shown in Fig. 6, an xy coordinate system with reference point P being defined
as an origin is set. An x axis represents the lateral direction of dump truck 300
that passes through reference point P. A direction away from vessel 301 with reference
point P being defined as the reference is defined as a +x direction. A y axis represents
the upward/downward direction that passes through reference point P. An upward direction
from reference point P is defined as a +y direction.
[0080] A bucket angle θ shown in Fig. 6 represents an angle formed between the ground and
rear surface 6b of bucket 6. Bucket angle θ may be an angle formed between rear surface
6b of bucket 6 and a horizontal plane with the vehicular body being defined as the
reference.
[0081] In step S104, automation controller 100 recognizes the current position of cutting
edge 6a of bucket 6. Positional information obtaining device 112 obtains the current
position of the vehicular body of wheel loader 1 and obtains the posture of the work
implement with respect to the vehicular body with boom angle sensor 123 and bucket
angle sensor 124, to thereby recognize the current position of cutting edge 6a of
bucket 6 in the global coordinate system. The position of cutting edge 6a of bucket
6 relative to vessel 301 of dump truck 300 can be calculated based on the current
positions of wheel loader 1 and work implement 3 and the current position of dump
truck 300 in the global coordinate system.
[0082] Alternatively, perception device 111 may be used to obtain the direction and the
distance of reference point P of vessel 301 of dump truck 300 from a position of arrangement
of perception device 111, to thereby calculate the current position of cutting edge
6a of bucket 6 relative to reference point P. This relative position may be recognized
as the current position.
[0083] In step S105, path planning unit 102 of automation controller 100 records a parameter
while the operator performs the loading operation for loading into vessel 301. The
recorded parameter includes horizontal and vertical positions with reference point
P being defined as the reference, that is, an x coordinate and a y coordinate, of
cutting edge 6a of bucket 6. The parameter includes bucket angle θ. Path planning
unit 102 can calculate bucket angle θ based on results of detection by boom angle
sensor 123 and bucket angle sensor 124 attached to work implement 3.
[0084] The current position of cutting edge 6a of bucket 6 and bucket angle θ while the
operator is performing the loading operation for loading into vessel 301 are recorded.
The posture of work implement 3 while the operator is performing the loading operation
for loading into vessel 301 is recorded based on the current position of cutting edge
6a of bucket 6 and bucket angle θ.
[0085] In step S106, automation controller 100 determines whether or not the loading operation
has ended. For example, the fact that loads in bucket 6 are fully ejected into vessel
301 and bucket 6 is empty can be recognized based on a result of detection by boom
cylinder pressure sensor 125. When movement of the current position of cutting edge
6a of bucket 6 to a position distant from dump truck 300 while bucket 6 is empty is
recognized, determination that the loading operation has ended can be made.
[0086] When it is determined in step S106 that the loading operation has not ended (NO in
step S106), the process returns to step S104 and recognition of the current position
of cutting edge 6a of bucket 6 and recording of the parameter while the operator is
performing the loading operation for loading into vessel 301 are repeated.
[0087] When it is determined in step S106 that the loading operation has ended (YES in step
S106), recording of works by the skilled operator ends ("recording end" in Fig. 5).
[0088] During a period from start in step S103 until end in step S106, of the operation
by the skilled operator to load the loads carried in work implement 3 (bucket 6) into
vessel 301, recognition of the current position of cutting edge 6a in step S104 and
recording of the parameter at the current position in step S105 are repeated. By plotting
the horizontal and vertical positions with reference point P being defined as the
reference, that is, the x coordinate and the y coordinate, of cutting edge 6a of bucket
6, trace TR of cutting edge 6a shown in Fig. 6 is obtained. Obtained trace TR is stored
in path planning unit 102. Reference point P of vessel 301 obtained in step S102 is
stored in path planning unit 102.
<Edition (Edit) of Recorded Parameter>
[0089] Fig. 7 is a flowchart showing a flow of processing for editing the parameter recorded
in step S105 shown in Fig. 5, so as to be used in automatic control of the loading
works.
[0090] In step S201, path planning unit 102 extracts the feature point that defines trace
TR, from trace TR of work implement 3 (cutting edge 6a of bucket 6) during the loading
operation shown in Fig. 6. In the present embodiment, feature points a, b, c, d, f,
and g details of which will be described below are extracted.
[0091] Fig. 8 shows a graph of change in cylinder length during the loading work. The abscissa
in Fig. 8 represents lapse of time and extension lines are drawn at times when cutting
edge 6a passes through feature points a, b, c, d, f, and g. The ordinate in Fig. 8
represents the lengths of boom cylinder 16 and bucket cylinder 19.
[0092] A position of cutting edge 6a of bucket 6 at the time when wheel loader 1 starts
the operation of bucket 6 in the dump direction for loading the loads in bucket 6
into vessel 301 while wheel loader 1 is traveling forward toward dump truck 300 is
extracted as feature point a. Fig. 9 is a diagram schematically showing the posture
of wheel loader 1 when the dump operation of bucket 6 is started. Feature point a
is a position through which cutting edge 6a of bucket 6 passes during forward travel
of wheel loader 1 toward dump truck 300. Feature point a is more distant from vessel
301 than reference point P. Feature point a is located in front of reference point
P of vessel 301. Feature point a is located at a position higher than reference point
P of vessel 301.
[0093] As shown in Fig. 8 and Figs. 6 and 9, before cutting edge 6a reaches feature point
a, wheel loader 1 is traveling forward. The length of boom cylinder 16 increases,
and hence boom 14 is being raised. The length of bucket cylinder 19 is constant, and
hence the posture of bucket 6 is constant. Bucket 6 is in a tilted state with the
excavation target having been carried therein. Bucket 6 is in a posture in which it
can transport loads therein in a stable manner.
[0094] A position of cutting edge 6a of bucket 6 at the time when wheel loader 1 travels
forward to approach vessel 301 and cutting edge 6a of bucket 6 moves toward a farthest
side (the left side in Figs. 9 to 14) is extracted as feature point b. Fig. 10 is
a diagram schematically showing the posture of wheel loader 1 when cutting edge 6a
reaches the farthest position. Feature point b is a position where cutting edge 6a
of bucket 6 passes after it passes through feature point a and moves beyond reference
point P. Feature point b is located above vessel 301.
[0095] As shown in Fig. 8 and Figs. 9 and 10, wheel loader 1 continues forward travel until
cutting edge 6a reaches feature point b after it passes through feature point a. The
length of boom cylinder 16 keeps increasing, and hence boom 14 keeps rising. At the
time point when cutting edge 6a reaches feature point a, the operation of bucket 6
in the dump direction is started, and bucket 6 continues operating in the dump direction
until the cutting edge reaches feature point b. The length of bucket cylinder 19 keeps
decreasing. In movement of cutting edge 6a from feature point a to feature point b,
the dump operation of bucket 6 affects the position of cutting edge 6a more greatly
than rise of boom 14. Therefore, feature point b is lower in height position than
feature point a. A value of the y coordinate of feature point b is smaller than the
value of a y coordinate of feature point a.
[0096] As shown in Fig. 8, after cutting edge 6a reaches feature point a, a rate of rise
of boom 14 decreases. The operation to raise boom 14 becomes gentle. Before cutting
edge 6a reaches feature point b, the rate of rise of boom 14 again increases.
[0097] A position of cutting edge 6a of bucket 6 at the time when the operation of bucket
6 in the dump direction is stopped above vessel 301 is extracted as feature point
c. Fig. 11 is a diagram schematically showing the posture of wheel loader 1 when the
dump operation of bucket 6 is stopped. Feature point c is a position where cutting
edge 6a of bucket 6 passes after it passes through feature point b. The operation
of bucket 6 in the dump direction is continued during a period from passage of cutting
edge 6a of bucket 6 through feature point a until cutting edge 6a reaches feature
point c. While cutting edge 6a of bucket 6 is located at feature point c, bucket 6
is in a full dump state. While cutting edge 6a of bucket 6 is located at feature point
c, the length of bucket cylinder 19 is minimized. Feature point c is located at a
position closer to reference point P than feature point b.
[0098] As shown in Fig. 8 and Figs. 10 and 11, wheel loader 1 continues forward travel until
cutting edge 6a reaches feature point c after it passes through feature point b. The
length of boom cylinder 16 keeps increasing, and hence boom 14 keeps rising. The length
of bucket cylinder 19 keeps decreasing, and hence bucket 6 continues operating in
the dump direction. At a time point when cutting edge 6a reaches feature point c,
bucket 6 is in a full dump posture and the dump operation of bucket 6 is stopped.
At the time point when cutting edge 6a reaches feature point c, the length of bucket
cylinder 19 is minimized. In movement of cutting edge 6a from feature point b to feature
point c, the dump operation of bucket 6 affects the position of cutting edge 6a more
greatly than rise of boom 14. Therefore, feature point c is lower in height position
than feature point b. The value of the y coordinate of feature point c is smaller
than the value of the y coordinate of feature point b.
[0099] During the dump operation of bucket 6, boom 14 keeps rising. During soil ejection
from bucket 6, boom 14 keeps rising. During loading of loads into dump truck 300,
boom 14 keeps rising. During the dump operation of bucket 6, wheel loader 1 moves
toward vessel 301 of dump truck 300, and hence it also continues forward travel.
[0100] A position of cutting edge 6a of bucket 6 at the time when the operation to raise
boom 14 is stopped above vessel 301 is extracted as feature point d. Fig. 12 is a
diagram schematically showing the posture of wheel loader 1 when the operation to
raise boom 14 is stopped. Feature point d is a position where cutting edge 6a of bucket
6 passes after it passes through feature point c. In order to avoid interference with
vessel 301 by work implement 3, wheel loader 1 during forward travel toward dump truck
300 is performing the operation to raise boom 14. The operation to raise boom 14 is
continued during a period from start of dump approach by wheel loader 1 until cutting
edge 6a of bucket 6 reaches feature point d. While cutting edge 6a of bucket 6 is
located at feature point d, boom 14 is highest in height position. While cutting edge
6a of bucket 6 is located at feature point d, the length of boom cylinder 16 is maximized.
Feature point d is located at a position closer to reference point P than feature
point c.
[0101] As shown in Fig. 8 and Figs. 11 and 12, at the time when cutting edge 6a passes through
feature point c, wheel loader 1 is traveling forward, and at the time when cutting
edge 6a passes through feature point d, wheel loader 1 is traveling rearward. While
cutting edge 6a is moving between feature point c and feature point d, the travel
direction of wheel loader 1 is switched from forward travel to rearward travel. The
length of boom cylinder 16 keeps increasing, and hence boom 14 keeps rising. The length
of bucket cylinder 19 is constant, and hence the posture of bucket 6 with respect
to the vehicular body is constant. Feature point c is the position where the operation
of bucket 6 in the dump direction is stopped, and while cutting edge 6a is moving
from feature point c to feature point d, bucket 6 keeps the full dump posture.
[0102] At the time when boom 14 stops rising, loads in bucket 6 have already been loaded
in vessel 301 and bucket 6 is in an unloaded state. Since a weight of loads in bucket
6 has become smaller, influence by inertia at the time when boom 14 is stopped is
less. Therefore, vibration of the vehicular body at the time when the operation to
raise boom 14 is stopped at feature point d is less likely.
[0103] In switching of the travel direction of wheel loader 1 from forward travel to rearward
travel, the center of gravity varies in the fore direction. In decrease of rise of
boom 14, the center of gravity of the loads in bucket 6 moves. By thus smoothly moving
the loads in bucket 6 into vessel 301, a time period required for the loading work
can be reduced and a cycle time of the loading work can be reduced.
[0104] A position of cutting edge 6a of bucket 6 at the time when the operation of bucket
6 in the tilt direction is started above vessel 301 is extracted as feature point
f. Fig. 13 is a diagram schematically showing the posture of wheel loader 1 when the
tilt operation of bucket 6 is started. Feature point f is a position through which
cutting edge 6a of bucket 6 passes after it passes through feature point d. Bucket
6 maintains the full dump state during a period from passage of cutting edge 6a of
bucket 6 through feature point c until the cutting edge reaches feature point f. Feature
point f is set to be closer to reference point P than feature point d. The length
of boom cylinder 16 is constant and boom 14 is maintained at an uppermost position
during a period from passage of cutting edge 6a of bucket 6 through feature point
d until the cutting edge reaches feature point f.
[0105] As shown in Fig. 8 and Figs. 12 and 13, until cutting edge 6a reaches feature point
f after it passes through feature point d, wheel loader 1 continues rearward travel.
The length of boom cylinder 16 is constant, and therefore the posture of boom 14 with
respect to the vehicular body is constant. At this time, the height position of boom
14 is highest. At the time when boom 14 stops rising, loads in bucket 6 have already
been loaded in vessel 301 and bucket 6 is in an unloaded state. The length of bucket
cylinder 19 is constant, and therefore the posture of bucket 6 with respect to the
vehicular body is constant. While cutting edge 6a is moving from feature point d to
feature point f, wheel loader 1 is traveling rearward with the full dump state of
bucket 6 being maintained.
[0106] A position of cutting edge 6a of bucket 6 at the time when the operation of bucket
6 in the tilt direction is stopped is extracted as feature point g. Fig. 14 is a diagram
schematically showing the posture of wheel loader 1 when the tilt operation of bucket
6 is stopped. Feature point g is a position through which cutting edge 6a of bucket
6 passes after it passes through feature point f. The operation of bucket 6 in the
tilt direction is continued during a period from passage of cutting edge 6a of bucket
6 through feature point f until the cutting edge reaches feature point g. Feature
point g is located above reference point P. Boom 14 is maintained at the uppermost
position during a period from passage of cutting edge 6a of bucket 6 through feature
point d until the cutting edge reaches feature point g.
[0107] As shown in Fig. 8 and Figs. 13 and 14, until cutting edge 6a reaches feature point
g after it passes through feature point f, wheel loader 1 continues rearward travel.
The length of boom cylinder 16 is constant, and therefore the posture of boom 14 with
respect to the vehicular body is constant. At the time point when cutting edge 6a
reaches feature point f, the operation of bucket 6 in the tilt direction is started,
and bucket 6 keeps operating in the tilt direction until the cutting edge reaches
feature point g. The length of bucket cylinder 19 keeps increasing. At the time point
when cutting edge 6a reaches feature point g, the operation of bucket 6 in the tilt
direction is stopped. Feature point f is the position where the tilt operation of
bucket 6 is started. Feature point g is the position where the tilt operation of bucket
6 is stopped. While cutting edge 6a is moving from feature point f to feature point
g, wheel loader 1 is traveling rearward with bucket 6 performing the tilt operation.
Wheel loader 1 performs the loading work for loading into dump truck 300, and thereafter
performs the tilt operation of bucket 6 during rearward travel to move away from dump
truck 300.
[0108] During the tilt operation of bucket 6, the posture of boom 14 is kept constant. After
completion of ejection of loads from bucket 6, boom 14 is held and the tilt operation
of bucket 6 is performed. During this tilt operation of bucket 6, wheel loader 1 continues
rearward travel and travels in the direction away from vessel 301 of dump truck 300.
[0109] As shown in Fig. 8, after cutting edge 6a passes through feature point g, wheel loader
1 continues rearward travel. The length of boom cylinder 16 has decreased, and hence
boom 14 has been lowered. The length of bucket cylinder 19 is constant, and therefore
the posture of bucket 6 with respect to the vehicular body is constant.
[0110] Referring back to Fig. 7, in step S202, path planning unit 102 determines the position
and the posture of work implement 3 with respect to reference point P based on the
recorded parameter at each of extracted feature points a, b, c, d, f, and g. In path
planning unit 102, the horizontal and vertical positions with reference point P being
defined as the reference, that is, the x coordinate and the y coordinate, of cutting
edge 6a of bucket 6, and bucket angle θ when cutting edge 6a of bucket 6 follows trace
TR, are stored. The posture of work implement 3 while cutting edge 6a of bucket 6
is located at each point on trace TR is stored in path planning unit 102.
[0111] The position of work implement 3 at each of feature points a, b, c, d, f, and g is
determined by giving the x coordinate and the y coordinate of cutting edge 6a of bucket
6. The posture of work implement 3 at the time when cutting edge 6a of bucket 6 is
located at each of feature points a, b, c, d, f, and g is determined based on the
x coordinate and the y coordinate of each of feature points a, b, c, d, f, and g and
bucket angle θ at each of feature points a, b, c, d, f, and g.
[0112] Feature point a is located at a position where a height position of cutting edge
6a is highest (the y coordinate having a maximum value) during the loading work. Feature
point c is located at a position where the height position of cutting edge 6a is lowest
(the y coordinate having a minimum value) during ejection of loads in bucket 6. The
y coordinate of feature point a has a positive value. The y coordinate of feature
point c has a negative value. The y coordinates of feature points d, f, and g have
positive values.
[0113] The x coordinate of feature point a has a positive value. The x coordinates of feature
points b, c, d, and f have negative values. Feature point b is located at a position
where the x coordinate has the minimum value during ejection of loads in bucket 6.
The x coordinate of feature point g is zero. Feature point g is located directly above
reference point P.
[0114] Then, the process ends ("edition end" in Fig. 7).
<Edition (Edition 2) of Parameter in Conformity with Change of Reference Point>
[0115] In automating the loading work for loading into containers in various shapes, a parameter
that defines a relative position of wheel loader 1 and a posture of work implement
3 should be set in conformity with the shape of the container, and a function to readily
set the parameter for each container is demanded. Fig. 15 is a flowchart showing a
flow of second processing for editing a parameter in conformity with reference point
P of the container.
[0116] In step S211, the actual shape of the container into which wheel loader 1 loads loads
in bucket 6 under automatic control is recognized. As in step S101, for example, the
shape of dump truck 300 into which loads are to actually be loaded is obtained by
LiDAR which is perception device 111. Point group data indicating three-dimensional
coordinate values of measurement points on dump truck 300 is obtained by irradiating
dump truck 300 with laser beams from LiDAR. The shape of vessel 301 can be recognized
based on information on the point group by sensing dump truck 300 from four directions
of the fore direction, the aft direction, the right direction, and the left direction.
The recognized shape of vessel 301 is inputted to automation controller 100.
[0117] In step S212, a reference point P' of the actual container into which wheel loader
1 loads the loads in bucket 6 under automatic control is recognized. Dump truck 300
into which the loads are to actually be loaded is detected by LiDAR which is perception
device 111. Automation controller 100 recognizes the position of vessel 301 based
on comparison between the point group detected by perception device 111 and a master
point group representing the shape of vessel 301. Automation controller 100 sets as
reference point P', the upper end of the side surface of vessel 301 of dump truck
300 recognized by LiDAR which is perception device 111.
[0118] In step S213, path planning unit 102 determines positions of feature points a', b',
c', d', f', and g' with respect to reference point P' of the actual container into
which wheel loader 1 loads the loads in bucket 6 under automatic control.
[0119] Fig. 16 is a schematic diagram showing feature points a', b', c', d', f', and g'
in accordance with vessel 301 of dump truck 300 different in vehicle rank. Through
processing in step S212, reference point P' is set at the upper end of the side surface
of vessel 301. Dump truck 300 including vessel 301 shown in Fig. 16 is lower in vehicle
rank than dump truck 300 onto which the skilled operator performed the loading operation
in advance shown in Fig. 6. Vessel 301 shown in Fig. 16 is smaller than vessel 301
shown in Fig. 6 in value of a height (height from the ground) H which is a distance
from ground G to vessel 301.
[0120] When the container into which the loads in bucket 6 are to be loaded is changed,
the changed container is detected and whether or not to change the position of the
reference point is determined. Even when dump truck 300 into which the loads are to
actually be loaded under automatic control is a vehicle different from dump truck
300 onto which the skilled operator performed the loading work, the position of the
reference point is not changed so long as they are identical in vehicle rank and shape
of vessel 301. When the shape of vessel 301 is different, the reference point is changed
and the feature point is changed in conformity with the changed reference point.
[0121] Fig. 17 is a schematic diagram showing reference point P' when a loading position
in dump truck 300 is changed. Dump truck 300 shown in Fig. 17 includes vessel 301
with a height varying from the front toward the rear. When the skilled operator performs
the loading work, loads are loaded onto a front portion of vessel 301, and reference
point P at the upper end of the side surface of vessel 301 at that time is set. When
loads are actually loaded under automatic control, loads are loaded onto a rear portion
of vessel 301. The height position of reference point P' at the upper end of the side
surface of vessel 301 at that time is different from that of reference point P. Reference
point P' is located at a position lower than reference point P.
[0122] When the position in the container where loads are to be loaded is changed, whether
or not to change the position of the reference point is determined. Even when the
position in vessel 301 where loads are to actually be loaded under automatic control
is different from the position where loads were loaded in the loading work by the
skilled operator, the position of the reference point is not changed, for example,
so long as the upper end of the side surface of vessel 301 of dump truck 300 is horizontal
and the height positions of the reference points are the same. When the upper end
of the side surface of vessel 301 is inclined with respect to the horizontal direction
and the height positions of the reference points are different, the feature point
is changed in conformity with the reference point different in height position.
[0123] Since each feature point is extracted from trace TR of cutting edge 6a of bucket
6, change of the feature point can be concluded as change of the trace of cutting
edge 6a.
[0124] With change of reference point P to reference point P', feature points a, b, c, d,
f, and g are translated and positions of new feature points a', b', c', d', f, and
g' changed in conformity with changed reference point P' are determined.
[0125] The x coordinate and the y coordinate of feature point a' in the xy coordinate system
with reference point P' being defined as the origin are set to be the same as the
x coordinate and the y coordinate of feature point a in the xy coordinate system with
reference point P being defined as the origin. The x coordinates and the y coordinates
of feature points b', c', d', f', ang g' in the xy coordinate system with reference
point P' being defined as the origin are set to be the same as the x coordinates and
the y coordinates of feature points b, c, d, f, and g in the xy coordinate system
with reference point P being defined as the origin.
[0126] In step S214, path planning unit 102 determines the position and the posture of work
implement 3 with respect to reference point P' at each of changed feature points a',
b', c', d', f, and g'. Bucket angle θ at the time when cutting edge 6a of bucket 6
follows trace TR is stored in path planning unit 102. The posture of work implement
3 at the time when cutting edge 6a of bucket 6 is located at each point on trace TR
is stored in path planning unit 102. The position of work implement 3 at each of feature
points a', b', c', d', f, and g' is determined by giving the x coordinate and the
y coordinate of cutting edge 6a of bucket 6. The posture of work implement 3 at the
time when cutting edge 6a of bucket 6 is located at each of feature points a', b',
c', d', f, and g' is determined based on the x coordinate and the y coordinate of
each of feature points a', b', c', d', f, and g' and stored bucket angle θ at each
of feature points a, b, c, d, f, and g.
[0127] In step S215, path planning unit 102 defines the posture of work implement 3 at each
of feature points a', b', c', d', f, and g' with lengths of boom cylinder 16 and bucket
cylinder 19. The lengths of boom cylinder 16 and bucket cylinder 19 are uniquely determined
based on the x coordinate and the y coordinate of the feature point and bucket angle
θ. Path planning unit 102 determines the length of boom cylinder 16 and the length
of bucket cylinder 19 at the time when cutting edge 6a of bucket 6 is located at each
of feature points a', b', c', d', f, and g'. Path planning unit 102 generates a path
along which cutting edge 6a of bucket 6 sequentially follows feature point a', feature
point b', feature point c', feature point d', feature point f, and feature point g'
and defines this path as the path for operations of work implement 3 included in the
optimal path. Then, the process ends ("edition 2 end" in Fig. 15).
<Automatic Control (Play) of Loading Work>
[0128] Fig. 18 is a flowchart showing a flow of processing for loading loads carried in
bucket 6 into vessel 301 under automatic control. Processing for automatically controlling
wheel loader 1 in accordance with the changed trace when the reference point of the
container is changed and the trace of the work implement and the feature point on
the trace are changed with change of the reference point will be described below.
[0129] In step S301, automation controller 100 recognizes the current positions of wheel
loader 1 and work implement 3. Positional information obtaining device 112 obtains
the current position of the vehicular body of wheel loader 1 and obtains the posture
of the work implement with respect to the vehicular body with boom angle sensor 123
and bucket angle sensor 124, to thereby recognize the current positions of wheel loader
1 and work implement 3 in the global coordinate system. The position of cutting edge
6a of bucket 6 relative to vessel 301 of dump truck 300 can be calculated based on
the current positions of wheel loader 1 and work implement 3 and the current position
of dump truck 300 in the global coordinate system.
[0130] Alternatively, perception device 111 may be used to obtain the direction and the
distance of reference point P of vessel 301 of dump truck 300 from a position of arrangement
of perception device 111, to thereby calculate the current position of cutting edge
6a of bucket 6 relative to reference point P.
[0131] At which position with respect to each of feature points a', b', c', d', f', and
g' cutting edge 6a of bucket 6 is located is recognized based on the current position
of work implement 3. For example, cutting edge 6a is recognized as not having reached
feature point a' yet, cutting edge 6a is recognized as having passed through feature
point a' and being located between feature point a' and feature point b', cutting
edge 6a is recognized as having passed through feature point b' and being located
between feature point b' and feature point c', etc. Furthermore, a feature point to
which cutting edge 6a is headed next is recognized as the target position. For example,
when cutting edge 6a has not yet reached feature point a', feature point a' is recognized
as the target position, when cutting edge 6a is located between feature point a' and
feature point b', feature point b' is recognized as the target position, etc.
[0132] In step S302, automation controller 100 recognizes the length of boom cylinder 16
and the length of bucket cylinder 19 at the current position. Boom angle sensor 123
detects the angle of boom 14. Bucket angle sensor 124 detects the angle of bucket
6. The posture of work implement 3 is determined by the angle of boom 14 and the angle
of bucket 6. The length of boom cylinder 16 and the length of bucket cylinder 19 at
the current position are recognized based on the posture of work implement 3.
[0133] Instead of or in addition to boom angle sensor 123 and bucket angle sensor 124, an
angle sensor that detects an angle of bell crank 18 and an angle sensor that detects
an angle of link 15 may be provided. A stroke sensor that detects a length of a cylinder
stroke may be provided in boom cylinder 16 and bucket cylinder 19.
[0134] In step S303, automation controller 100 calculates a difference between the length
of boom cylinder 16 and the length of bucket cylinder 19 at the current position recognized
in step S302 and the length of boom cylinder 16 and the length of bucket cylinder
19 (which will be referred to as a target cylinder length below) at the target position
to which cutting edge 6a is headed next. Automation controller 100 calculates how
much the cylinder is to be moved until cutting edge 6a reaches the next target position.
[0135] In step S304, automation controller 100 refers to a current vehicle speed and determines
a target cylinder stroke speed that achieves the target cylinder length at the time
when cutting edge 6a reaches the target position to which the cutting edge is headed
next. Automation controller 100 controls boom cylinder 16 and bucket cylinder 19 such
that work implement 3 takes, when cutting edge 6a reaches the target position to which
it is headed next, a posture corresponding to that target position. The current vehicle
speed is obtained by vehicle speed sensor 122. Time until the cutting edge reaches
the next target position can be calculated based on the current position of cutting
edge 6a and the current vehicle speed. The target cylinder stroke speed can be determined
by dividing the difference in cylinder length calculated in step S303 by time until
the cutting edge reaches the next target position.
[0136] An amount of cylinder stroke while wheel loader 1 travels a unit distance may be
determined. Travel of the unit distance by wheel loader 1 may be determined based
on the vehicle speed or may be sensed by perception device 111.
[0137] In step S305, automation controller 100 outputs a command current corresponding to
the target cylinder stroke speed to vehicular body controller 50. Automation controller
100 outputs a command to extend and contract boom cylinder 16 and bucket cylinder
19 at the target cylinder stroke speed to work implement control unit 82 of work implement
controller 80. The command to extend and contract boom cylinder 16 and bucket cylinder
19 at the target cylinder stroke speed is outputted from work implement control unit
82 to work implement EPC 143.
[0138] In step S306, as work implement EPC 143 that has received the command signal adjusts
an opening, appropriate hydraulic oil is supplied to boom cylinder 16 and bucket cylinder
19. Boom cylinder 16 and bucket cylinder 19 thus operate.
[0139] In step S307, automation controller 100 recognizes the current lengths of boom cylinder
16 and bucket cylinder 19 as in step S302. Automation controller 100 determines whether
or not the current lengths of boom cylinder 16 and bucket cylinder 19 have reached
the target cylinder lengths.
[0140] When determination as having reached the target cylinder length is made in determination
in step S307 (YES in step S307), the process proceeds to step S308 and automation
controller 100 determines whether or not there is a next target position.
[0141] When determination as not having reached the target cylinder length is made in determination
in step S307 (NO in step S307) and when it is determined in step S308 that there is
a next target position (YES in step S308), the process returns to step S301 and processing
for extending and contracting boom cylinder 16 and bucket cylinder 19 based on the
current position of work implement 3 is repeated. The cylinder speed is successively
changed in accordance with the current position of cutting edge 6a of bucket 6. When
the current position of cutting edge 6a is displaced from a position based on the
cylinder speed set in previous processing, the cylinder speed is adjusted.
[0142] When it is determined in step S308 that there is no next target position (NO in step
S308), the loading work ends ("play end" in Fig. 18), which corresponds to a case
where the next target position after cutting edge 6a passes through feature point
g' is not set in the present embodiment.
[0143] By moving cutting edge 6a of bucket 6 as sequentially passing through feature point
a', feature point b', feature point c', feature point d', feature point f, and feature
point g', loads in bucket 6 can be loaded into vessel 301 without contact of bucket
6, the vehicular body, and running wheel 4a with vessel 301. By applying automatic
control to thus move bucket 6 to wheel loader 1, operations of work implement 3 equivalent
to operations performed by the skilled operator can be realized.
<Functions and Effects>
[0144] Characteristic features and functions and effects of the present embodiment will
be summarized as below, although some description may overlap with the description
above.
[0145] As shown in Figs. 5 and 6, trace TR of cutting edge 6a of bucket 6 and reference
point P of vessel 301 while wheel loader 1 is operated to load the loads carried in
work implement 3 into vessel 301 of dump truck 300 are stored in automation controller
100. As shown in Figs. 15 to 17, when the position of reference point P is changed
to reference point P', automation controller 100 changes trace TR of cutting edge
6a in conformity with changed reference point P'.
[0146] Trace TR of work implement 3 and reference point P of vessel 301 while the skilled
operator operates wheel loader 1 for loading are recorded, and when the reference
point is changed, the trace of work implement 3 in automatic control of the work implement
is set in conformity with changed reference point P'. Adaptation to loading into containers
different in shape or minor change of a situation on a side of the container can be
made. Since loading can be performed regardless of the shape of the container, the
loading work for loading into containers in various shapes can be automated.
[0147] As shown in Figs. 7 to 14, feature points a, b, c, d, f, and g that define trace
TR of cutting edge 6a while the operation to load the loads carried in work implement
3 into vessel 301 is performed are stored in automation controller 100. As shown in
Figs. 15 to 17, automation controller 100 changes feature points a, b, c, d, f, and
g to feature points a', b', c', d', f', and g' in conformity with changed reference
point P'. Feature points a', b', c', d', f, and g' in conformity with changed reference
point P' are determined and the trace of work implement 3 in automatic control of
work implement 3 is set in accordance with feature points a', b', c', d', f, and g',
so that the trace of automatically controlled work implement 3 can appropriately be
set and the operation by the skilled operator can be reproduced under automatic control.
[0148] As shown in Figs. 5 to 14, the posture of work implement 3 at feature points a, b,
c, d, f, and g is stored in automation controller 100. Under automatic control of
work implement 3 in accordance with the positions of feature points a, b, c, d, f,
and g and the posture of work implement 3 at feature points a, b, c, d, f, and g,
the operation by the skilled operator can more faithfully be reproduced.
[0149] As shown in Figs. 15 and 16, when vessel 301 into which loads are to be loaded is
changed, automation controller 100 detects changed vessel 301 and determines whether
or not to change the position of reference point P. When the shape of vessel 301 is
changed, the reference point is changed and trace TR of cutting edge 6a is changed
in conformity with changed reference point P'. For example, the height of boom 14
can be adjusted to maintain constant, the y coordinate of the feature point with the
reference point being defined as the reference. When the height position of reference
point P' is lower than reference point P, adjustment to lower boom 14 can be made
to change trace TR of cutting edge 6a. The loading work for loading loads into the
container different in shape under automatic control can be thus performed.
[0150] As shown in Figs. 15 and 17, when the position in vessel 301 where loads are to be
loaded is changed, automation controller 100 determines whether or not to change the
position of reference point P. When the height position of the position where loads
are to be loaded is changed, the reference point is changed and trace TR of cutting
edge 6a is changed in conformity with changed reference point P'. Thus, even when
the situation on the side of the container changes, the loading work for loading loads
into the container can be performed under automatic control.
[0151] As shown in Figs. 8 and 9, feature point a is the position of cutting edge 6a at
the time when the operation of bucket 6 in the dump direction is started while wheel
loader 1 is traveling forward toward vessel 301. Under automatic control of wheel
loader 1 such that cutting edge 6a passes through feature point a, the dump operation
of bucket 6 can start at the time point before cutting edge 6a reaches vessel 301.
By simultaneously performing forward travel of wheel loader 1 toward dump truck 300
and the dump operation of bucket 6 as a plurality of operations temporally overlapping,
the cycle time of the loading work can be reduced.
[0152] As shown in Figs. 8 and 11, feature point c is the position of cutting edge 6a at
the time when the operation of bucket 6 in the dump direction is stopped above vessel
301. Under automatic control of wheel loader 1 such that cutting edge 6a passes through
feature point c, loads in bucket 6 can reliably be loaded into vessel 301.
[0153] As shown in Figs. 8 and 12, feature point d is the position of cutting edge 6a at
the time when the operation to raise boom 14 is stopped above vessel 301. Under automatic
control of wheel loader 1 such that cutting edge 6a passes through feature point d,
the loading work can be performed without the operation of work implement 3 being
stopped and sway of the vehicle by inertia at the time when boom 14 is stopped can
be suppressed.
[0154] As shown in Figs. 8 and 13, feature point f is the position of cutting edge 6a at
the time when the operation of bucket 6 in the tilt direction is started above vessel
301. Under automatic control of wheel loader 1 such that cutting edge 6a passes through
feature point f, contact of cutting edge 6a and rear surface 6b of bucket 6 with vessel
301 can be avoided.
[0155] As shown in Figs. 8 and 14, feature point g is the position of cutting edge 6a at
the time when the operation of bucket 6 in the tilt direction is stopped. Under automatic
control of wheel loader 1 such that cutting edge 6a passes through feature point g,
contact of bucket 6 with vessel 301 can reliably be avoided. The tilt operation to
such an extent that bucket 6 can move as reliably eluding vessel 301 is performed
without the tilt operation of bucket 6 more than necessary, so that bucket 6 can promptly
make transition to the posture for next excavation works.
[0156] Automation controller 100 included in the automatic control system for wheel loader
1 described in the embodiment above does not necessarily have to be mounted on wheel
loader 1. Such a system that a controller outside wheel loader 1 implements automation
controller 100 may be configured. Vehicular body controller 50 mounted on wheel loader
1 may perform processing for transmitting information obtained by external information
obtaining unit 110, vehicle information obtaining unit 120, and the like to an external
controller and the external controller that receives a signal may extract the positions
of feature points a, b, c, d, f, and g that define trace TR of cutting edge 6a of
bucket 6 with reference point P being defined as the reference.
[0157] The external controller may be arranged at a worksite of wheel loader 1 or at a remote
location distant from the worksite of wheel loader 1. The external controller may
be a transportable device. The external controller may be a portable device that can
be used as being carried by a worker, such as a notebook personal computer, a tablet
computer, or a smartphone.
[0158] In the embodiment, works for loading loads carried in work implement 3 (bucket 6)
into vessel 301, with vessel 301 of dump truck 300 being illustrated as the container,
are described. The container into which loads carried in work implement 3 are to be
loaded is not limited to vessel 301 of dump truck 300, and for example, a hopper may
be applicable.
[0159] In the embodiment, an example in which wheel loader 1 is a manned vehicle including
cab 5 on which the operator rides is described. Wheel loader 1 may be an unmanned
vehicle. Wheel loader 1 does not have to include cab 5 on which the operator rides
for performing operations. Wheel loader 1 does not have to be equipped with a function
for manipulating by the operator who rides on the cab. Wheel loader 1 may be a work
machine dedicated for remote control. Wheel loader 1 may be manipulated through a
wireless signal from a remote control device.
<Additional Aspects>
[0160] The description above includes features additionally described below.
(Additional Aspect 1)
[0161] A system including a work machine includes
a work machine main body,
a work implement attached to the work machine main body, the work implement including
a bucket,
a work implement posture sensor that detects a posture of the work implement,
an object sensor that detects an object around the work machine main body, and
a controller that communicates with the work implement posture sensor and the object
sensor, and
the controller stores a trace of the work implement and a reference point of the container
while the work machine is operated to load loads in the bucket into a container, and
when a position of the reference point is changed, the controller changes the trace
in conformity with the changed reference point.
(Additional Aspect 2)
[0162] In the system according to Additional Aspect 1,
a position of a feature point that defines the trace is stored, and
the feature point is changed in conformity with the changed reference point.
(Additional Aspect 3)
[0163] The system according to Additional Aspect 1 or 2 obtains a posture of the work implement
at the feature point.
(Additional Aspect 4)
[0164] In the system according to any one of Additional Aspects 1 to 3,
when the container into which the loads are to be loaded is changed, the changed container
is detected, and whether to change the position of the reference point is determined.
(Additional Aspect 5)
[0165] In the system according to any one of Additional Aspects 1 to 3,
when a position in the container where the loads are to be loaded is changed, whether
to change the position of the reference point is determined.
(Additional Aspect 6)
[0166] In the system according to any one of Additional Aspects 1 to 5,
the feature point includes a position of the work implement at time when an operation
of the bucket in a dump direction is started while the work machine travels forward
toward the container.
(Additional Aspect 7)
[0167] In the system according to any one of Additional Aspects 1 to 6,
the feature point includes a position of the work implement at time when an operation
of the bucket in a dump direction is stopped above the container.
(Additional Aspect 8)
[0168] In the system according to any one of Additional Aspects 1 to 7,
the work implement includes a boom having a tip end attached to the bucket, and
the feature point includes a position of the work implement at time when an operation
to raise the boom is stopped above the container.
(Additional Aspect 9)
[0169] In the system according to any one of Additional Aspects 1 to 7,
the feature point includes a position of the work implement at time when an operation
of the bucket in a tilt direction is started above the container.
(Additional Aspect 10)
[0170] In the system according to Additional Aspect 9,
the feature point includes a position of the work implement at the time when the operation
of the bucket in the tilt direction is stopped
[0171] It should be understood that the embodiment disclosed herein is illustrative and
non-restrictive in every respect. The scope of the present invention is defined by
the terms of the claims rather than the description above and is intended to include
any modifications within the scope and meaning equivalent to the terms of the claims.
REFERENCE SIGNS LIST
[0172] 1 wheel loader; 2 vehicular body frame; 2a front frame; 2b rear frame; 3 work implement;
4 travel apparatus; 4a, 4b running wheel; 5 cab; 6 bucket; 8 operation apparatus;
9 boom pin; 11 steering cylinder; 13 work implement pump; 14 boom; 15 link; 16 boom
cylinder; 17 bucket pin; 18 bell crank; 18a support pin; 18b, 18c coupling pin; 19
bucket cylinder; 21 engine; 23 transmission; 25 axle; 32 main valve; 35, 36 electromagnetic
proportional control valve; 41 accelerator pedal; 42 work implement control lever;
50 vehicular body controller; 51 machine monitor; 60 engine controller; 70 transmission
controller; 71 brake control unit; 72 accelerator control unit; 80 work implement
controller; 81 steering control unit; 82 work implement control unit; 100 automation
controller; 101 position estimator; 102 path planning unit; 103 path tracking control
unit; 110 external information obtaining unit; 111 perception device; 112 positional
information obtaining device; 120 vehicle information obtaining unit; 121 articulation
angle sensor; 122 vehicle speed sensor; 123 boom angle sensor; 124 bucket angle sensor;
125 boom cylinder pressure sensor; 130 interface; 131 mode selection operation portion;
132 engine emergency stop switch; 133 mode indicator; 140 actuator; 141 brake EPC;