CROSS REFERENCE TO RELATED APPLICATIONS
[0001] The present disclosure claims the benefit of priority to Chinese Patent Application
No.
CN202210987643.4, filed on August 17, 2022, the entire disclosure of which is incorporated herein by reference in its entirety.
TECHNICAL FIELD
[0002] The present disclosure pertains to the technical field of prefabricated building
walls, and in particular to a permanent formwork, a building structure, and a spatial
entity setting-out construction method.
BACKGROUND
[0003] Construction setting-out involves measuring and setting out the planar position and
elevation of a building (structure) on the drawing to the construction site or engineering
entity through instrument measurement, ruler measurement, and other methods. For example,
ink lines are used to mark out the axis and one-meter line as the basis for construction
positioning. The accuracy of construction setting-out itself and the positioning accuracy
therefor play a crucial role in controlling the construction tolerance of a finished
surface.
[0004] In conventional construction setting-out, it is difficult to preserve the ink lines
for a long time during the construction process, and the human errors and accumulated
errors caused by repeated measurement and setting-out adversely affect the accuracy
of the construction finished surface. Although entity setting-out is easier to preserve,
it has stricter requirements on the accuracy of construction setting-out itself and
the positioning accuracy therefor. The existing formwork establishing methods, which
utilize steel, wood, and other materials as removable or permanent formworks and employ
clamps, bolts, and diagonal braces for installation, hardly meet the construction
measurement and setting-out requirements for high-precision entity setting-out.
SUMMARY
[0005] It is an objective of the present disclosure to provide a permanent formwork, a building
structure, and a spatial entity setting-out construction method, in order to solve
the technical problem that the existing formwork establishing methods for removable
formworks are difficult to achieve high-precision construction measurement and setting-out
and entity setting-out.
[0006] To achieve the aforementioned objective, the technical solution adopted in the present
disclosure is as follows. A first aspect of the present disclosure provides a permanent
formwork, including two parallel and opposing first formworks. Each of the first formworks
has a first profile panel for attaching to the foundation and a second profile panel
perpendicular to the first profile panel.
[0007] A first concreting cavity for concreting concrete is formed between the two second
profile panels, the two second profile panels are connected by a tie connector located
inside the first concreting cavity.
[0008] A side of the first profile panel facing away from the foundation and a side of the
second profile panel located outside the first concreting cavity each have a construction
control line and/or construction control plane.
[0009] Further, the construction control line includes a positioning line for fixing with
the foundation, and the construction control plane includes at least one of foundation
leveling layer finished surface, thermal insulation layer finished surface, floor
heating layer finished surface, stone bonding layer or wood floor leveling layer finished
surface, and floor heating boundary insulation strip finished surface.
[0010] Further, the first formwork is of a spliced structure.
[0011] Further, both the first profile panel and the second profile panel are made of fiberglass-reinforced
polyurethane profiles.
[0012] Further, the first profile panel and the second profile panel are integrally formed.
[0013] Further, a reverse side of the first profile panel and a reverse side of the second
profile panel are each formed with multiple first slots. A front side of the first
profile panel and a front side of the second profile panel are each formed with multiple
second slots. The reverse side of the first profile panel is the side that is intended
to be attached to the foundation, and the reverse side of the second profile panel
is the side facing the first concreting cavity.
[0014] Further, at least part of the first slots and at least part of the second slots are
arranged in an asymmetric and staggered pattern.
[0015] Further, at least part of the construction control lines and/or construction control
planes are located on walls of the second slots.
[0016] Further, a level gauge is installed inside one second slot.
[0017] Further, the tie connector includes a first pull piece and a second pull piece. The
first pull piece is a threaded rod, and the second pull piece is a U-shaped pull piece.
The U-shaped pull piece includes a central connecting piece and two parallel flanks
located on two sides of the central connecting piece. Each flank is formed with a
threaded hole, and the two flanks are respectively fixed to the two second profile
panels using screws.
[0018] Further, the U-shaped pull piece includes two L-shaped connecting pieces which are
assembled into the U-shaped pull piece through a detachable connection.
[0019] Further, the U-shaped pull piece further includes a straight connecting piece which
is configured to connect the two L-shaped connecting pieces.
[0020] Further, the permanent formwork further includes at least two parallel and spaced
second formworks. An extension direction of the second formworks is perpendicular
to an extension direction of the first formworks in three-dimensional space, and the
two second formworks are respectively connected to the two first formworks through
connecting pieces. The first formworks and the second formworks form different forms
of corner joints in space, and a second concreting cavity for concreting concrete
is formed between the two second formworks arranged in parallel.
[0021] Further, the shapes of the cross-sections of the first formwork and the second formwork
are the same.
[0022] A second aspect of the present disclosure provides a building structure, including
the permanent formwork as described above.
[0023] Further, the building structure is a guide wall, a structural column, or a lintel.
[0024] A third aspect of the present disclosure provides a spatial entity setting-out construction
method including:
assembling straight formworks, which includes pulling two parallel and spaced first
formworks toward each other from front or reverse sides to form a straight formwork
for entity setting-out, wherein two straight formworks oriented in different directions
intersect in space to form different types of corner joints; and
assembling corner formworks, which includes using a prefabricated first formwork to
assemble at a corner joint to form different types of corner formworks.
[0025] Further, pulling two parallel and spaced first formworks toward each other from the
front or reverse sides to form the straight formwork for entity setting-out includes:
connecting the two first formworks by pulling after the tie connector is engaged with
a slot of the first formwork.
[0026] The permanent formwork provided by the present disclosure includes two parallel and
spaced first formworks. Each of the first formworks has a first profile panel for
attaching to the foundation and a second profile panel perpendicular to the first
profile panel. The two second profile panels are connected by a tie connector. A first
concreting cavity for concreting concrete is formed between the two second profile
panels. A side of the first profile panel facing away from the foundation and a side
of the second profile panel located outside the first concreting cavity each have
a construction control line and/or construction control plane. The permanent formwork
is not affected by previous construction errors of the site during entity setting-out,
and can re-establish a three-dimensional construction positioning reference in space.
It can achieve measurement and setting-out accuracy level of finished surfaces in
one single step through entity construction setting-out in the site, and reduce human
errors caused by repeated measurement and setting-out such as pilot measurement and
projection measurement, as well as accumulated errors caused by step-by-step measurement
and setting-out according to the construction sequence, thereby achieving high-precision
construction measurement and setting-out and entity setting-out.
BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to illustrate the technical solutions in the embodiments of the present
disclosure more clearly, the drawings used in the description of the embodiments or
the conventional technology are briefly described below. It is apparent that the drawings
in the following description show only some embodiments of the present disclosure,
and other drawings may be obtained by those of ordinary skill in the art based on
these drawings without any creative efforts.
FIG. 1 is a schematic structural view of a permanent formwork provided in an embodiment
of the present disclosure;
FIG. 2 is a schematic structural view of a first formwork of the permanent formwork
provided in an embodiment of the present disclosure;
FIG. 3 is a schematic structural view of an L-shaped connecting piece of the permanent
formwork provided in an embodiment of the present disclosure;
FIG. 4 is a schematic structural view of a straight connecting piece of the permanent
formwork provided in an embodiment of the present disclosure;
FIG. 5 is a schematic structural view of a corner joint of the permanent formwork
provided in an embodiment of the present disclosure;
FIG. 6 is a schematic structural view of an installation scenario of the permanent
formwork provided in an embodiment of the present disclosure;
FIG. 7 is a flow chart of a spatial entity setting-out construction method for the
permanent formwork provided in an embodiment of the present disclosure;
FIG. 8 is a schematic structural view of a corner joint structure of male corners
of a permanent formwork provided in an embodiment of the present disclosure;
FIG. 9 is a schematic structural view of a corner joint structure of a male corner
and a female corner of a permanent formwork provided in an embodiment of the present
disclosure; and
FIG. 10 is a schematic structural view of a corner joint structure of female corners
of a permanent formwork provided in an embodiment of the present disclosure.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0028] To clarify the objectives, technical solutions, and advantages of the embodiments
of the present disclosure, the technical solutions in the embodiments of the present
disclosure will be described clearly and completely hereinafter in conjunction with
the drawings in the embodiments of the present disclosure. Apparently, the described
embodiments are only a part of the embodiments of the present disclosure, rather than
all embodiments. Based on the embodiments in the present application, all other embodiments
obtained by those of ordinary skill in the art without creative efforts fall within
the scope of protection of the present application.
[0029] In the description of the present disclosure, it should be understood that the terms
"including" and "having" used in this paper, as well as any variations thereof, are
intended to cover non-exclusive inclusion. For example, processes, methods, systems,
products, or devices that include a series of steps or units are not necessarily limited
to those steps or units explicitly listed, but may include other steps or units that
are not explicitly listed or are inherent to these processes, methods, products, or
devices.
[0030] In the present disclosure, unless otherwise expressly specified and limited, terms
such as "connect", "joint", "fix", "install", etc. should be interpreted in a broad
sense. For example, a connection may be mechanical or electrical; may be direct or
indirect via an intermediary; may refer to the internal communication between two
components or the interaction between two components. Unless otherwise explicitly
defined, for those skilled in the art, the specific meaning of the above terms in
this paper can be understood based on the specific circumstances.
[0031] It should be understood that the terms "length", "width", "up", "down", "front",
"rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside",
and other terms indicating orientation or positional relationships are based on the
orientation or positional relationships shown in the drawings. These terms are solely
used to facilitate the description of the present disclosure and simplify the description,
and do not indicate or imply that the devices or components referred to must have
specific orientations or be constructed and operated in specific orientations. Therefore,
these terms should not be construed as limitations on the present disclosure.
[0032] The terms "first" and "second" are solely used for descriptive purposes and should
not be interpreted as indicating or implying relative importance or implicitly specifying
the number of the technical features referred to. Thus, features modified by "first"
and "second" may explicitly or implicitly include one or more of these features. In
the description of this paper, unless otherwise stated, the meaning of "multiple"
is two or more. In this paper, the term "and/or" merely describes the associative
relationship between associated objects, indicating that there can be three types
of relationships. For example, A and/or B can represent sole existence of A, existence
of both A and B, and sole existence of B.
[0033] The following provides a detailed description of the permanent formwork, the building
structure, and the spatial entity setting-out construction method provided by the
present disclosure in conjunction with specific embodiments.
[0034] FIG. 1 is a schematic structural view of a permanent formwork provided in an embodiment
of the present disclosure, and FIG. 2 is a schematic structural view of a first formwork
of the permanent formwork provided in an embodiment of the present disclosure. Referring
to FIG. 1 and FIG. 2, the first aspect of the embodiments of the present disclosure
provides a permanent formwork, including two parallel and opposing first formworks
1. Each of the first formworks 1 has a first profile panel 11 for attaching to the
foundation and a second profile panel 12 perpendicular to the first profile panel
11. The two second profile panels 12 are connected by a tie connector 2. A first concreting
cavity A for concreting concrete is formed between the two second profile panels 12.
The tie connector 2 is positioned inside the first concreting cavity A. A side of
the first profile panel 11 facing away from the foundation and a side of the second
profile panel 12 located outside the first concreting cavity A each have a construction
control line and/or construction control plane.
[0035] Each of the first formworks 11 has a first profile panel 11 for attaching to the
foundation and a second profile panel 12 perpendicular to the first profile panel
11. In this embodiment, the first profile panel 11 is fixed to the foundation through
fixing elements during the installation of the permanent formwork. A first concreting
cavity A for pouring concrete is formed between the two second profile panels 12.
This embodiment imposes no specific limitation on the distance between the two first
formworks 1. The distance between the two second profile panels 12 in this embodiment
is the thickness of the concrete structure to be concreted, which can be preset in
advance according to actual needs.
[0036] The two second profile panels 12 in this embodiment are connected by a tie connector
2 arranged inside the first concreting cavity A. This embodiment imposes no specific
limitation on the specific form of the tie connector 2. The permanent formwork in
this embodiment does not require subsequent formwork disassembly and removal, reducing
the generation of construction waste. The first formwork 1 in this embodiment adopts
prefabricated parts, eliminating the need for on-site processing of the formwork during
assembly construction, reducing the interference of cross-construction on site, and
greatly shortening the construction period of entity setting-out, reducing unnecessary
repeated setting-out, and improving the work efficiency of on-site construction.
[0037] This embodiment imposes no specific limitation on the specific material of the first
formwork 1. For example, the first formwork 1 may be made of a material with a linear
expansion coefficient close to that of concrete and a small difference in material
deformation, so that the overall structural strength and dimensional accuracy of the
concreted component are high. For example, the first formwork 1 in this embodiment
may be made of fiberglass-reinforced polyurethane material.
[0038] In this embodiment, a side of the first profile panel 11 facing away from the foundation
and a side of the second profile panel 12 located outside the first concreting cavity
A each have a construction control line and/or construction control plane. For example,
the construction control plane in this embodiment may be a foundation leveling layer
finished surface, a floor heating layer finished surface, or a floor leveling layer
finished surface. The construction control line and/or construction control plane
in this embodiment are located on the permanent formwork, which unifies the dimensional
reference and construction rule in the entity setting-out.
[0039] The permanent formwork in this embodiment includes two parallel and spaced first
formworks. Each of the first formworks has a first profile panel for attaching to
the foundation and a second profile panel perpendicular to the first profile panel.
The two second profile panels are connected by a tie connector. A first concreting
cavity for concreting concrete is formed between the two second profile panels. A
side of the first profile panel facing away from the foundation and a side of the
second profile panel located outside the first concreting cavity each have a construction
control line and/or construction control plane. The permanent formwork is not affected
by previous construction errors of the site during entity setting-out, and can re-establish
a three-dimensional construction positioning reference in space. It can achieve measurement
and setting-out accuracy level of finished surfaces in one single step through entity
construction setting-out in the site, and reduce human errors caused by repeated measurement
and setting-out such as pilot measurement and projection measurement, as well as accumulated
errors caused by step-by-step measurement and setting-out according to the construction
sequence.
[0040] In a specific embodiment, referring to FIG. 1 and FIG. 2, the construction control
line includes a positioning line H1 for fixing with the foundation, and the construction
control plane includes at least one of foundation leveling layer finished surface
M1, thermal insulation layer finished surface M2, floor heating layer finished surface
M3, stone bonding layer or wood floor leveling layer finished surface M4, and floor
heating boundary insulation strip finished surface M5. The construction control line
in this embodiment includes a positioning line H1 for fixing with the foundation.
For example, when the first profile panel 11 of this embodiment is connected to the
foundation via bolts 3, the positioning line H1 for fixing with the foundation may
be a drilling line for bolts. This permanent formwork can calculate the self-precision
and positioning accuracy of the setting-out entity based on the technical indicator
of a construction tolerance limit Δ=±1mm for the finished surface. Through entity
construction setting-out in the site, it can achieve the measurement and setting-out
accuracy level of the foundation leveling layer finished surface M1, the thermal insulation
layer finished surface M2, the floor heating layer finished surface M3, the stone
bonding layer or wood floor leveling layer finished surface M4, and floor heating
boundary insulation strip finished surface M5 in one single step, and reduce human
errors caused by repeated measurement and setting-out such as pilot measurement and
projection measurement, as well as accumulated errors caused by step-by-step measurement
and setting-out according to the construction sequence. The foundation leveling layer
finished surface M1, the thermal insulation layer finished surface M2, the floor heating
layer finished surface M3, the stone bonding layer or wood floor leveling layer finished
surface M4, and the floor heating boundary insulation strip finished surface M5 serve
not only as control lines for the construction quality of various processes of a concealed
work, but also as verification standards for the construction acceptance of each process.
The first formwork of this embodiment is provided with a cutting positioning line
H2 in the height direction.
[0041] Unified dimensions are the fundamental principle for achieving collaborative work
among various processes. This permanent formwork integrates the construction control
lines of various processes in both planar and elevation control dimensions during
entity setting-out by providing construction control lines and/or surfaces on the
side of the first profile panel 11 facing away from the foundation and on the side
of the second profile panel 12 located outside the first concreting cavity A. With
the assistance of millimeter-level measurement and setting-out accuracy, this permanent
formwork unifies the construction and installation dimensions on site through the
construction control lines during entity setting-out. In the time dimension of the
construction cycle, unified construction and installation dimensions serve as an intangible
rule carrier, clarifying the on-site construction interface for subsequent and collaborative
work.
[0042] In a specific embodiment, the first formwork 1 is of a spliced structure. The first
formwork 1 in this embodiment is of a spliced structure, allowing technicians to splice
the first formwork 1 of different lengths according to on-site needs, providing strong
flexibility.
[0043] In a specific embodiment, both the first profile panel 11 and the second profile
panel 12 are made of fiberglass-reinforced polyurethane profiles. The material of
the first profile panel 11 and the second profile panel 12 in this embodiment is the
high-performance composite material, fiberglass-reinforced polyurethane. This material
has a low expansion coefficient, low shrinkage rate, high strength, light weight,
and low thermal conductivity. The first formwork 1, as a construction permanent formwork
of an entity setting-out member, has a linear expansion coefficient close to that
of concrete, so that there is a small difference in material deformation between the
two, and the overall structural strength and dimensional accuracy of the concreted
component are high.
[0044] In some embodiments, the first profile panel 11 and the second profile panel 12 are
integrally formed, making the manufacturing process simple. The permanent formwork
in this embodiment is made of fiberglass-reinforced polyurethane and is produced through
a pultrusion process. The permanent formwork has a stable structural size and high
bending strength.
[0045] Further, referring to FIG. 1 and FIG. 2, a reverse side of the first profile panel
11 and a reverse side of the second profile panel 12 are each formed with multiple
first slots 13. A front side of the first profile panel 11 and a front side of the
second profile panel 12 are each formed with multiple second slots 14. The reverse
side of the first profile panel 11 is the side that is intended to be attached to
the foundation, and the reverse side of the second profile panel 12 is the side facing
the first concreting cavity A. The shapes of the first slots 13 and the second slot
14 of the permanent formwork in this embodiment are set according to construction
standards and construction practices. Both the first slots 13 and the second slots
14 in this embodiment are universal slots. The first formwork 1 of this embodiment
is provided with seven general construction slots, distributed on the front and reverse
side of the first formwork 1. The first slots 13 on the front side and the second
slots 14 on the reverse side are arranged in an asymmetric and staggered manner. The
first slots 13 and the second slots 14 in this embodiment are arranged in an asymmetric
staggered manner, which can improve the strength of the first formwork 1.
[0046] Further, referring to FIG. 2, at least part of the construction control lines and/or
construction control planes are located on walls of the second slots 14. In this embodiment,
the foundation leveling layer finished surface M1, the thermal insulation layer finished
surface M2, the floor heating layer finished surface M3, the stone bonding layer or
wood floor leveling layer finished surface M4, and the floor heating boundary insulation
strip finished surface M5 on the first formwork are all set on the walls of the second
slots 14. In FIG. 2, the first formwork 1 integrates both the construction control
lines and construction control planes for quality control acceptance, as well as a
multi-functional, expandable universal slots for construction, on both the front and
reverse sides.
[0047] In some embodiments, a level gauge is provided inside one second slot 14. By providing
a level gauge inside the second slot 14, the level gauge can verify the levelness
of the installation during installation of the permanent formwork. This embodiment
does not impose any specific structural limitations on the level gauge.
[0048] The permanent formwork in this embodiment can standardize the spatial positioning
and dimensional criteria for full-field construction control through its own precision,
and define the access methods for expandable functional components through a universal
construction interface. It can also establish a standardized, unified, multifunctional,
and expandable universal construction interface platform while performing entity setting-out.
[0049] In a specific embodiment, referring to FIG. 1, the tie connector 2 includes a first
pull piece 21 and a second pull piece 22. The first pull piece 21 is a threaded rod,
with both ends of the threaded rod fixed to the two second profile panels 12 respectively.
The threaded rod is arranged inside the first concreting cavity A. The second pull
piece 22 is a U-shaped pull piece. The U-shaped pull piece includes a central connecting
piece and two parallel flanks located on two sides of the central connecting piece.
Each flank is formed with a threaded hole, and the two flanks are respectively fixed
to the two second profile panels 12 using screws. The first pull piece 21 and the
second pull piece 22 in this embodiment are both installed inside the two first formworks
1. After the construction of the permanent formwork is completed, they do not need
to be removed. The first pull piece 21 and the second pull piece 22 in this embodiment
are easy to install, making the construction site clean and orderly.
[0050] Further, FIG. 3 is a schematic structural view of the L-shaped connecting piece of
the permanent formwork provided in an embodiment of the present disclosure. Referring
to FIG. 3, the U-shaped pull piece includes two L-shaped connecting pieces 221 which
are assembled into the U-shaped pull piece through a detachable connection. The U-shaped
pull piece in this embodiment is formed by splicing two L-shaped connecting pieces
221 through a detachable connection, allowing the two L-shaped connecting pieces 221
to be spliced to form intermediate connecting parts of different lengths, which can
be applied to the fabrication of concrete structures of different thicknesses.
[0051] Further, FIG. 4 is a schematic structural view of a straight connecting piece of
the permanent formwork provided in an embodiment of the present disclosure. Referring
to FIG. 4, the U-shaped pull piece further includes a straight connecting piece 222
which is configured to connect the two L-shaped connecting pieces 221. In this embodiment,
using the straight connecting piece 222 to connect two L-shaped connecting pieces
221 expands the adjustable range of the length of the intermediate connecting part
of the U-shaped pull piece.
[0052] In a specific embodiment, FIG. 5 is a schematic structural view of a corner joint
of the permanent formwork provided in an embodiment of the present disclosure, and
FIG. 6 is a schematic structural view of an installation scenario where the permanent
formwork provided in an embodiment of the present disclosure is attached to an invisible
door frame. Referring to FIG. 5 and FIG. 6, the permanent formwork further includes
at least two parallel and spaced second formworks 4. An extension direction of the
second formworks 4 is perpendicular to an extension direction of the first formworks
1 in three-dimensional space, and the two second formworks 4 are respectively connected
to the two first formworks 1 through connecting pieces 5. The first formworks 1 and
the second formworks 4 form different forms of corner joints in space, and a second
concreting cavity B for concreting concrete is formed between the two second formworks
4 arranged in parallel.
[0053] FIG. 5 illustrates a type of corner joint formed when a guide wall intersects with
a structural column. This type of corner joint consists of five prefabricated standard
formworks (the first formworks 1 located on the left, right, and front sides, and
the second formworks 4 located on the left and right sides, where the structure of
the second formworks 4 in this embodiment is the same as that of the first formworks
1). These five prefabricated standard formworks are assembled and combined through
a first connecting piece 51 and a second connecting piece 52 both with threaded holes.
Two first formworks 1 are pulled toward each other from the reverse sides, and two
second formworks 4 are pulled toward each other from the front sides. The front side
of the first formwork 1 located on the right side and the reverse side of the second
formwork 4 located on the right side are assembled and combined through the first
connecting piece 51. The front side of the first formwork 1 located on the left side
and the reverse side of the second formwork 4 located on the left side are assembled
and combined through the first connecting piece 51. The front side of the first formwork
1 located on the front side and the front sides of the two first formworks 1 located
on the left and right sides are assembled and combined through the second connecting
piece 52. The first connecting piece 51 and the second connecting piece 52 are pressed
and positioned with set screws after installed at the universal construction interface.
After measurement and setting-out are finished, the corner formwork pieces are fixed
on the construction site with bolts 3.
[0054] In some embodiments, the shapes of the cross-sections of the first formwork 1 and
the second formwork 4 are the same. The first formwork 1 and the second formwork 4
in this embodiment may be the same formwork unit, and the manufacturing method therefor
is simple. When the first formwork 1 and the second formwork 4 are combined for different
corner joints, different cuts are made to the first formwork 1 and the second formwork
4. Of course, in other embodiments, the first formwork 1 and the second formwork 4
may be different formwork units.
[0055] The formwork establishment process of the permanent formwork in this embodiment does
not involve subsequent formwork disassembly and removal, reducing the generation of
construction waste. The permanent formwork precisely measures and sets out the on-site
construction control lines and/or construction control planes in both planar and elevation
dimensions during the three dimensional entity setting-out process. From the material
selection and mouth shape setting of the standard unit formwork to the factory prefabrication
and on-site assembly of the formwork pieces, the construction tolerance Δ can be controlled
throughout the entire process to be within ±1mm. Consistent dimensional criteria and
construction interfaces are maintained the same from concealed works to finished surfaces.
The permanent formwork provides a customized on-site verification standard for various
processes at the construction site during the three dimensional entity setting-out
process, ensuring that subsequent construction is not affected by previous construction.
Different trades, disciplines, and subcontractors can work simultaneously, saving
coordination costs and efficiently advancing the construction schedule.
[0056] A second aspect of the present disclosure provides a building structure, including
the permanent formwork as described in the above embodiments.
[0057] In a specific embodiment, the building structure may be a guide wall, a structural
column, or a lintel. This embodiment does not impose any specific limitations on the
specific form of the building structure.
[0058] The building structure of this embodiment includes the aforementioned permanent formwork,
and the formwork establishment process of the permanent formwork does not involve
subsequent formwork disassembly and removal, reducing the generation of construction
waste. The permanent formwork precisely measures and sets out the on-site construction
control lines and/or construction control planes in both planar and elevation dimensions
during the three dimensional entity setting-out process. From the material selection
and mouth shape setting of the standard unit formwork to the factory prefabrication
and on-site assembly of the formwork pieces, the construction setting-out accuracy
Δ can be controlled throughout the entire process to be within ±1mm. Consistent dimensional
criteria and construction interfaces are maintained the same from concealed works
to finished surfaces. The permanent formwork provides a customized on-site verification
standard for various processes at the construction site during the three dimensional
entity setting-out process, ensuring that subsequent construction is not affected
by previous construction. Different trades, disciplines, and subcontractors can work
simultaneously, saving coordination costs and efficiently advancing the construction
schedule.
[0059] FIG. 7 is a flow chart of a spatial entity setting-out construction method for the
permanent formwork provided in an embodiment of the present disclosure. Referring
to FIG. 7, a third aspect of the embodiment of the present disclosure provides a spatial
entity setting-out construction method which utilizes the permanent formwork described
in the aforementioned embodiments. The method includes:
[0060] S101, assembly of straight formworks, including pulling two parallel and spaced first
formworks toward each other from the front or reverse sides to form a straight formwork
for entity setting-out, where two straight formworks oriented in different directions
intersect in space to form different types of corner joints.
[0061] The first formworks of this embodiment are established by pulling from the front
or reverse sides according to the actual situation of construction setting-out, forming
the straight part of the entity setting-out. Exemplarily, FIG. 1 shows the establishment
method of pulling from the reverse sides of two standard first formworks 1. The first
formworks 1 are connected by pulling after the first pull piece 21 and the second
pull piece 22 are engaged with the universal construction interfaces of the first
formworks 1. After measurement and setting-out are finished, the straight formwork
is fixed on the construction site with bolts 3.
[0062] S102, assembly of corner formworks, including using a prefabricated first formwork
to assemble at a corner joint to form different types of corner formworks.
[0063] FIG. 8 is a schematic structural view of a corner joint structure of male corners
of a permanent formwork provided in an embodiment of the present disclosure; FIG.
9 is a schematic structural view of a corner joint structure of a male corner and
a female corner of a permanent formwork provided in an embodiment of the present disclosure;
and FIG. 10 is a schematic structural view of a corner j oint structure of female
corners of a permanent formwork provided in an embodiment of the present disclosure.
Referring to FIG. 8 to FIG. 10, straight formworks oriented in different directions
intersect in space to form different types of corner joints. Each type of corner joint
is composed of a prefabricated standard first formwork 1, which forms a complete entity
setting out. Different types of corner formwork pieces and straight formwork pieces
of different lengths are assembled and combined through straight connecting pieces
with threaded holes. The straight connecting pieces are pressed and positioned with
set screws after installed at the universal construction interfaces. The assembled
formwork pieces are the smallest units for controlling the accuracy of on-site entity
setting out. In this embodiment, the female corner refers to the inwardly recessed
wall corner, while the male corner refers to the protruding wall corner. During the
process of on-site entity setting-out, the corner formwork pieces and the straight
formwork pieces determine the precise relative positional relationship between the
entity setting-out components through their own absolute dimensional accuracy, and
achieve precise construction positioning for the entire site's plane and elevation
control through construction control points.
[0064] The prefabricated formworks in this embodiment eliminates the need for on-site processing
of the formwork during assembly construction, reduces the interference of cross-construction
on site, and greatly shortens the construction period of entity setting-out, thereby
reducing unnecessary repeated setting-out and improving the work efficiency of on-site
construction.
[0065] The permanent formwork in the spatial entity setting-out construction method of the
present disclosure includes two parallel and spaced first formworks. Each of the first
formworks has a first profile panel for attaching to the foundation and a second profile
panel perpendicular to the first profile panel. The two second profile panels are
connected by a tie connector. A first concreting cavity for concreting concrete is
formed between the two second profile panels. A side of the first profile panel facing
away from the foundation and a side of the second profile panel located outside the
first concreting cavity each have a construction control line and/or construction
control plane. The permanent formwork is not affected by previous construction errors
of the site during entity setting-out, and can re-establish a three-dimensional construction
positioning reference in space. It can achieve measurement and setting-out accuracy
level of finished surfaces in one single step through entity construction setting-out
in the site, and reduce human errors caused by repeated measurement and setting-out
such as pilot measurement and projection measurement, as well as accumulated errors
caused by step-by-step measurement and setting-out according to the construction sequence.
[0066] The three dimensional entity setting-out of the permanent formwork in this embodiment
provides a customized on-site verification standard for various processes at the construction
site, ensuring that subsequent construction is not affected by previous construction.
Different trades, disciplines, and subcontractors can work simultaneously, thereby
saving coordination costs and efficiently advancing the construction schedule.
[0067] In the above description, the descriptions of reference terms such as "an embodiment",
"some embodiments", "exemplarily", "specific examples", etc., refer to that the specific
features, structures, materials, or characteristics described in conjunction with
the embodiment or example are included in at least one embodiment or example of the
present disclosure. In this specification, the illustrative expressions of the aforementioned
terms do not necessarily refer to the same embodiment or example. Moreover, the specific
features, structures, materials, or characteristics described can be combined in an
appropriate manner in any one or multiple embodiments or examples. In the absence
of any contradiction, those skilled in the art can combine and integrate different
embodiments or examples described in this specification, as well as the features of
different embodiments or examples.
[0068] The above embodiments are only for illustrating the technical solutions of the present
disclosure, and are not intended to limit them. Although the present disclosure has
been described in detail with reference to the aforementioned embodiments, those skilled
in the art should understand that they can still modify the technical solutions described
in the aforementioned embodiments, or equivalently substitute some or all of the technical
features; all such modifications or substitutions do not make the essence of the corresponding
technical solution deviate from the scope of the technical solutions of the embodiments
of the present disclosure.
1. A permanent formwork, comprising:
two parallel and opposing first formworks, wherein each of the first formworks has
a first profile panel for attaching to a foundation and a second profile panel perpendicular
to the first profile panel;
wherein a first concreting cavity for concreting concrete is formed between the two
second profile panels, the two second profile panels are connected by a tie connector
located inside the first concreting cavity; and
a side of the first profile panel facing away from the foundation and a side of the
second profile panel located outside the first concreting cavity each have a construction
control line and/or construction control plane.
2. The permanent formwork according to claim 1, wherein the construction control line
comprises a positioning line for fixing with the foundation, and the construction
control plane comprises at least one of foundation leveling layer finished surface,
thermal insulation layer finished surface, floor heating layer finished surface, stone
bonding layer or wood floor leveling layer finished surface, and floor heating boundary
insulation strip finished surface.
3. The permanent formwork according to claim 1, wherein the first formwork is of a spliced
structure.
4. The permanent formwork according to claim 1, wherein both the first profile panel
and the second profile panel are made of fiberglass-reinforced polyurethane profiles.
5. The permanent formwork according to claim 1, wherein the first profile panel and the
second profile panel are integrally formed.
6. The permanent formwork according to any one of claims 1 to 5, wherein a reverse side
of the first profile panel and a reverse side of the second profile panel are each
formed with a plurality of first slots, a front side of the first profile panel and
a front side of the second profile panel are each formed with a plurality of second
slots, the reverse side of the first profile panel is a side that is intended to be
attached to the foundation, and the reverse side of the second profile panel is a
side facing the first concreting cavity.
7. The permanent formwork according to claim 6, wherein at least part of the first slots
and at least part of the second slots are arranged in an asymmetric and staggered
pattern.
8. The permanent formwork according to claim 6, wherein at least part of the construction
control lines and/or construction control planes are located on walls of the second
slots.
9. The permanent formwork according to claim 6, wherein a level gauge is installed inside
one second slot.
10. The permanent formwork according to any one of claims 1 to 9, wherein the tie connector
comprises a first pull piece and a second pull piece, wherein the first pull piece
is a threaded rod, and the second pull piece is a U-shaped pull piece, wherein the
U-shaped pull piece includes a central connecting piece and two parallel flanks located
on two sides of the central connecting piece, wherein each flank is formed with a
threaded hole, and the two flanks are respectively fixed to the two second profile
panels using screws.
11. The permanent formwork according to claim 10, wherein the U-shaped pull piece comprises
two L-shaped connecting pieces which are assembled into the U-shaped pull piece through
a detachable connection.
12. The permanent formwork according to claim 11, wherein the U-shaped pull piece further
comprises a straight connecting piece which is configured to connect the two L-shaped
connecting pieces.
13. The permanent formwork according to any one of claims 1 to 12, wherein the permanent
formwork further comprises at least two parallel and spaced second formworks, wherein
an extension direction of the second formworks is perpendicular to an extension direction
of the first formworks in three-dimensional space, and the two second formworks are
respectively connected to the two first formworks through connecting pieces, wherein
the first formworks and the second formworks form different forms of corner joints
in space, and a second concreting cavity for concreting concrete is formed between
the two second formworks arranged in parallel.
14. The permanent formwork according to claim 13, wherein shapes of cross-sections of
each first formwork and each second formwork are the same.
15. A building structure, comprising the permanent formwork according to any one of claims
1 to 14.
16. The building structure according to claim 15, wherein the building structure is a
guide wall, a structural column, or a lintel.
17. A spatial entity setting-out construction method, utilizing the permanent formwork
according to any one of claims 1 to 14, and comprising:
assembling straight formworks, which comprises pulling two parallel and spaced first
formworks toward each other from front or reverse sides to form a straight formwork
for entity setting-out, wherein two straight formworks oriented in different directions
intersect in space to form different types of corner joints; and
assembling corner formworks, which comprises using a prefabricated first formwork
to assemble at a corner joint to form different types of corner formworks.
18. The spatial entity setting-out construction method according to claim 17, wherein
pulling two parallel and spaced first formworks toward each other from the front or
reverse sides to form the straight formwork for entity setting-out comprises: connecting
the two first formworks by pulling after the tie connector is engaged with a slot
of the first formwork.