[0001] This invention relates to a method of and apparatus for collating sheets, which are
received serially in groups of similar sheets.
[0002] In prior art collators, all the first sheets of a multi-sheet document are produced
and transported serially to the collator and there inserted.one sheet at a time into
different physically discrete bins. Then, all the second sheets of the document are
produced and transported serially to the collator and there inserted into the bins,
each of which already contains a first sheet. This process is repeated until a complete
set has been built up in each of the bins.
[0003] The size of collators is directly dependent on the number of discrete bins and the
physical dimensions thereof. Generally, the number of discrete bins determines the
maximum number of sets that can be run in a particular job. The physical dimensions
of each discrete bin determine the maximum sheet size that can be processed and the
maximum number of sheets per discrete bin.
[0004] Since there is usually an overall physical size limitation, prior art collators have
been designed to strike a balance between the maximum number of sets that can be run
in a job and the maximum number of sheets that can comprise a set. Thus, in order
to meet the physical size requirement, typical prior art machines have a capacity
of 20 sets comprising 100 sheets each, giving a total sheet capacity of 2,000. Such
a machine suffers from the disadvantage that a job of more than 20 sets or of sets
comprising more than 100 sheets each cannot be run, even though the total of sheets
is less than the sheet capacity of 2,000, for example 30 sets of 20 sheets each, or
lO sets of 150 sheets each.
[0005] There is also a built-in operator inconvenience and cost in unloading these collators.
For example, for a 20 bin collator which is loaded to capacity,'20 separate hand motions
are required by an operator to unload, and for those collators not having automatic
stapling, the operator will have to take care not to mix the sets by either stapling
each set as it is removed, or by stacking the sets offset from one another to clearly
demarcate them. ,
[0006] Now, according to one aspect of the present invention, a method of collating sets
of sheets, which are received serially in groups of similar sheets, comprises the
steps of stacking the sheets of the first group received in individually offset fashion,
demarcating each first sheet from adjacent first sheets, and inserting individual
sheets of the next group in the same offset fashion contiguous to individual first
sheets, and thereafter inserting, if necessary, individual sheets of subsequent groups
in the same contiguous to individual prior-inserted sheets of the same set to form
collated sets of sheets.
[0007] According to another aspect of the invention, apparatus for collating sets of sheets,
which are received serially in groups of similar sheets, comprises means to stack
the sheets of the first group received in individually offset fashion, demarcating
each first sheet from adjacent first sheets, and means to insert individual sheets
of the next group in the same offset fashion contiguous to individual.first sheets
and to insert, if necessary, individual sheets of subsequent groups in the same offset
fashion contiguous to individual prior inserted sheets of the same set to form collated
sets of sheets.
[0008] The invention thus provides job flexibility in that within the total sheet capacity
of the collator jobs are not limited to a maximum number of sets or to a maximum number
of sheets in a set.
[0009] In addition, the collated sets of a job may be removed from the collator in one operator
action, the sets being clearly demarcated from each other.
[0010] The claimed invention may be carried out in the ways described in detail below with
reference to the accompanying drawings, in which:
FIG. 1 is a perspective view of the apparatus according to the invention;
FIG. 2 is an enlarged perspective view of part of the apparatus of Fig.l;
FIG. 3 is a side elevation of the apparatus of Fig.l;
FIG. 4 is a section on the lines IV-IV of Fig.3;
FIG. 5 is an enlarged perspective view from below of another part apparatus of Fig.l;
FIG. 6 is an enlarged side view of yet a further part of the apparatus of Fig.l;
FIGS. 7 and 8 are plan views of other parts of the apparatus of Fig.l in different
positions of operation;
FIGS. 9 to 14 illustrate the method of collating according to the invention;
FIG. 15 is a circuit diagram of an embodiment of control logic for the apparatus of
Fig.l; and
FIG. 16 is a timing diagram illusyiting the

[0011] 
The sheet entry scation 18 includes lower and upper sheet guides 24 and 2f between
which is a path for incoming sheets. A pair of low friction rollers 28 and 30 is fixed
to a drive roller shaft 32 which is journaled in upset tabs 34 and 36 integral with
the guide 26. The shaft 32 is operatively coupled to a mctor (not shown) to rotate
the rollers 28 and 30 to feed a sheet 14 between the guides 24 and 26 to the arcuate
sheet transport station 20. Mounted on the top surface of upper sheet guide 26 adjacent
the station 20 is a lever actuated sheet path switch 38, whose actuator lever is in
the sheet path and engageable by a sheet to detect the presence or absence of a sheet
at the sheet transport station 20. Also mvunted on the top surface of the guide 26
to one side of the sheet path are first and second lever actuated sheet gripper position
switches 40 and 42. The switch 40 has two pairs of contacts, one normally closed,
the othe normally open. The switch 42 has a normally closed par of contacts.
[0012] The arcuate sheet transport station 20 includes four pairs of gripper belt pulley
44 and 46, 48 and 50, 52 and 54, and 56 and 58. The pairs of pulleys are fixed to
pulley shafts 60, 62, 64 and 66, respectively. The pulley shafts are journaled in
a main support frame 68 and grooved peripherally to be engaged by teeth on the inner
surfaces of two gripper transporting timing belts 70 and 72 which encircle and engage
pulleys 44, 48, 52 and 56, and 46, 50, 54 and 58, respectively. A drive shaft pulley
74 is fixed to the shaft 66 externally of the frame 68. A gripper drive motor timlng
belt 76 encircles and couples the drive shaft pulley 74 and a gripper drive motor
pulley 80 fixed to shaft 82 of a gripper drive motor 78. The sheet path lies between
tie belts 70 and 72.
[0013] First and second sheet grippers 84 and 86 are disposed across the sheet path with
their ends connected to the belts 70 and 72 so that the sheet grippers move with the
belts. The grippers are equally spaced on the belts, so that when one grippe is adjacent
the sheet entry station 18, the other is at the entrance to the sheet receiving station
22. Mounted on he frame 68 adjacent the sheet receiving station 22 is a levee actuated
sheet sensor switch 282, whose actuator lever is in the sheet path and engageable
by a sheet to detet the presence or absence of a sheet. The switch 282 has two pairs
of normally open contacts.
[0014] The first seet gripper 84 includes a first sheet gripper bar 88 which is bent to
form four V-shaped integral corrugations 92, 4, 96 and 98. The gripper bar 88 is disposed
perpendicular to the belts 70 and 72 and includes three integral shet gripper arms
104, l06 and 108. The arms extend forwardy from the bar 88 at right angles thereto
and are of diffeent lengths. The arm 104, nearest the belt 72 is short and the arm
lO8 nearest the belt 70 is long, so that the end. of the arms lie on a line disposed
at an angle to the bar 88. Fixed to the ends of the arms are sheet gripper clips 110,
112 and 114, respectively. On the end of the gripper bar 88 attached to the belt 70
is mounted a switch actuator comprising an elevated contour 100 for engagement by
the lever of the sheet gripper position switch 40, and a recessed contour 102 for
engagement by the lever of the sheet gripper position switch 42.
[0015] The second sheet gripper 86 includes a second sheet gripper bar 90 which is bent
to form four V-shaped integral corrugations 116, 118, 120 and 122, aligned with the
corrugations in the bar 88. Attached to the end of the bar 90 on the belt 70 is mounted
a switch actuator comprising an elevated contour 124 for engagement by the lever of
the sheet gripper position switch 42, and a recessed contour 126 for engagement by
the lever of the sheet gripper position switch 40. The gripper bar 90 is disposed
perpendicular to the belts 70 and 72 and includes three integral sheet gripper arms
128, 130 and 132. The arms extend forwardly from the bar 90 at right angles thereto
and are of different lengths. The arm 128, nearest the belt 70, is short and the arm
132, nearest the belt 72, is long, so that the ends of the arms lie on a line disposed
at an angle to the bar 90, equal and opposite to the angle between the bar 88 and
the line joining the ends of the arms 104, 106 and 108. Fixed to the ends of the arms
128, 130 and 132 are sheet gripper clips 134, 136 and 138, respectively. The arms
128, 130 and 132 are not aligned with the arms 108, l06 and 104, but are slightly
offset therefrom. The levers of the switches 38 and 282 are aligned with corrugations
94 and 118, so that the bars 84 and 86 do not operate the switches.
[0016] An entry cam plate 140 is fixed to the frame 68 across and below the path of the
gripper bars and has three first sheet gripper entry cams 142, 144 and 146 (Fig.2)
upset from its surface to engage and open simultaneously the first sheet gripper clips
110, 112 and 114 respectively, in order to grip a sheet to be processed. The plate
140 also has three second sheet gripper entry cams 148, 150 and 152 upset from its
surface to engage and cam open simultaneously the second sheet gripper clips 134,
136 and 138, respectively. To ensure simultaneously, the cams 142, 144 and 146 lie
on a line parallel to line joining the ends of the arms 104, l06 and 108 (Fig.l) and
the cams 148, 150 and 152 lie on a line parallel to.the line joining the ends of the
arms 128, 130 and 132.
[0017] With the first sheet gripper 84 (Fig.2) in position adjacent the sheet entry station
18, the clips 110, 112 and 114 are held open by the cams 142, 144 and 146, respectively.
The levers of the switches 40 and 42 rest on the actuator contours 100 and 102, respectively.
As the sheet 14 is driven forward by low friction rollers 28 and 30, the lever of
the sheet path switch 38 is engaged and lifted and the operation of the switches 38,
40 and 42 is signalled to the system control logic. The leading edge of the sheet
14 contacts the first sheet gripper clip 110 and is stopped thereby. Due to the low
friction drive of the rollers 28 and 30, forward drive by the roller 28 ceases while
forward drive is continued by the roller 30. Accordingly, the sheet 14 is skewed and
offset until the leading edge is driven into and contacts the first sheet gripper
clip 112, as shown in dotted lines. The gripper 84 then moves forward, the rollers
28 and 30 driving the sheet 14 to keep the leading edge in the clips 110 and 112,
until the clips 110, l12 and l14 disengage from the cams 142, 144 and 146 and close
firmly gripping the sheet 14. As illustrated, the sheet 14 is of a standard size,
e.g. A4, and engages the clips 110 and 112 with its longer side. Larger size paper
may be used e.g., 21.59 cm x 35.56 cm (8.5 in. x 14 in.), in which case the sheet
will be additionally gripped by first sheet gripper clip 114.
[0018] When the gripper 80 is in position adjacent the sheet entry station 18, the clips
134, 136 and 138 are held open by the cams 148, 150 and 152, respectively. The levers
of the switches 40 and 42 rest on the actuator contours 126 and 124, respectively.
As a sheet is driven forward by rollers 28 and 30, it will first engage and lift the
lever of the switch 38. Thereafter its leading edge will engage the clip 136 or 138,
according to the size of the sheet being driven. The roller 30 will begin to slip
on the surface of the sheet and the sheet will be skewed or offset by continued drive
of the roller 28, until the clip 134 is engaged. The skew or offset is in the opposite
direction to that given to a sheet engaging the clips on the gripper 84. Thereafter
the gripper 86 moves forward and the rollers 28 and 30 drive the sheet forward to
keep the leading edge in the clips, until they are disengaged from the cams 148, 150
and 152 and close to grip the sheet firmly.
[0019] The unitary bin sheet receiving station 22 includes a movable sheet platform 154
(Figs. 3 and 4) which has integral therewith four sheet platform support pulley blocks
156, 158, 160 and 162, arranged two on each side of the platform, with pulleys 164,
166, 168, and 170 respectively, rotatably mounted therein. The top of the frame 68
on one side is cut away at 172 and 174 to reveive rotatably mounted sheet platform
lift pulleys 176 and 178. A sheet . platform support cable 180 has an end secured
to the bottom of one side of the frame 68 and passes over sheet platform support pulley
164 and under sheet platform support pulley 164, with the other end of the cable secured
to the other side of the frame 68 between the top and bottom. Another sheet platform
support cable 182 has an end secured to the bottom of the one side of the frame 68
and passes over pulley 170 and under pulley 168, with the other end of the cable secured
to the other side of the frame 68 between the top and bottom. Thus, the platform 154
is capable of being raised or lowered while maintaining a balanced position relative
to the frame.
[0020] The raising or lowering of movable sheet platform 154 is effected by a pair of sheet
platform lift cables 184 and 186 whose one ends are secured to the pulley blocks 156
and 162, respectively. The cables pass over sheet platform lift pulleys 176 and 178,
respectively, and have their other ends wound around and secured to a sheet platform
lift shaft 188, rotatably mounted in spaced supports 190 and 192 secured to the frame
68. The shaft 188 extends beyond the frame 68 and carries a toothed pulley 202. A
sheet platform lift motor 194 is mounted on the frame 68 and has a shaft 200 carrying
a toothed pulley 198. A timing belt 196 is entrained around and couples the pulleys
198 and 202. Rotation of the motor 194 rotates the shaft 188 to wind up or out the
cables 184 and 186 to raise or lower the platform 154.
[0021] The platform 154 also has an arcuate cutout 212 (Fig. 6) in its edge closest to the
shaft 60. The edge of the platform 154 remote from the shaft 60 has a shape related
to the angular offset of sheets delivered by the grippers 84 and 86 and has upstanding
triangular sheet restraining tabs 204, 206, 208, and 210, for restraining the forward
motion of sheets delivered to the stack. The corrugations on the bars 88 and 90 are
such as to allow the bars to pass over the platform 154 and tabs.
[0022] Beyond the platform 154 in the direction of sheet movement is a stationary sheet
stack constrainer wall 214 (Figs. 1, 4 and 5), secured to the frame 68. The wall 214
is configured in the same manner as the adjacent edge of the platform 154, so that
the platform can rise and fall alongside the wall. The'lower face of the wall 214
has triangular cutout portions 216, 218, 220 and 222 aligned with the tabs 204, 206,
208 and 210, respectively so that the bars 88 and 90 can pass between the platform
154 and wall 214 in the position shown in Fig.4. The wall 214 is connected to a shaped
plate 224 (Fig.5) which is corrugated to match the cutout portions 216, 218, 220 and
222 and has three first sheet gripper exit cams 228, 230 and 232 and three second
sheet gripper exit cams 234, 236 and 238. The cams on the plate 224 are aligned with
the cams on the plate 140. The sheet gripper exit cams are situated so that the first
sheet gripper clips 110, 112, and 114 on the gripper 84 are cammed open simultaneously
by the first sheet gripper exit cam thereby releasing a sheet onto the sheet platform
154, the tabs 204 and 208 restraining forward motion of the sheet. Similarly, the
second sheet gripper clips 134, 136, and 138 of the gripper 86 are cammed open simultaneously
by the second sheet gripper exit cams thereby releasing a sheet onto the-.sheet platform
154, the tabs 206 and 210 restraining forward motion of this sheet.
[0023] It will be appreciated that the shape of wall 214 and the adjacent edge of the platform
154 is determined by the size of sheet to be stacked and the amount of offset given
by the clips on the gripper bars. If larger size sheets are to be handled, the wall
214 must be given an enlarged configuration on one side as shown in broken lines in
Figures 1 and 5. In such case, the cam 236 must be retractable, when not required
for small sheets, and the corresponding gripper clip 136 rendered inactive for larger
sheets by retraction of the cam 150.
[0024] The interaction between a cam and a clip is illustrated in Fig.6. The forward edge
of a sheet 14 of paper.is against a tongue 111 upset from the resilient material of
the clip. The forward portion of the sheet is gripped between the clip and a chamfered
edge of the arm 104. Engagement of the clip 110 with the cam 228 springs the clip
away from the arm 104, releasing the paper just before it strikes the tab 204 on the
platform 154.
[0025] A light source 238 is disposed on and seared to one side of the frame 68, and provides
a narrow light beam directed upon a sensor 2400 on the other side of the frame 68.
Also mounted on the other side of the frame 68 are lever actuated switches 242 and
244 which sense the sheet platform in upper and lower limit positions, respectively.
[0026] A sheet separator mechanism 246 (Fig.l) is disposed above the sheet path upon a mounting
bar 248 fixed to the sides of the frame 68. Pivoted to the bar 248 is one upstanding
end of a sheet separator and support arm 250. On the other horizontal end thereof
is a rotatably mounted friction reducing roller 252. Being freely rotatable, the roller
252 reduces the drag friction on sheets being separated and supported during collation.
Fixed to the one end of the arm 250 is a lever arm 254 (Fig.7) with an elongated slot.
[0027] A reciprocating position solenoid 256 is carried by a bracket 258 slidably mounted
on the bar 248 by screws 260 and 262 in slots in the bracket. The solenoid 256 has
a plunger 264 with a link 266 engaged in the slot in the lever arm 254. A spring 272
acts on the lever arm 254 to extend the plunger 264. Energisation of the solenoid
256 causes the arm 250 to be pivoted from a first position A to a second position
B within the arcuate cutout 212 of the platform 154.
[0028] A home position solenoid 268 is secured to the bar 248 and has a plunger 270 attached
to the slidable bracket 258. With both solenoids 256 and 268 energised, the arm 250
is pivoted to a third or home position C.
[0029] With both solenoids 256 and 268 de-energised, the return spring 272 causes the arm
250 to pivot to the first position A.
[0030] Prior to a stacking or collation operation, the platform 154 is located in a position
below the line of the beam from the light source 238 to the light sensor 240. In this
position (Fig.4), there is room for the gripper bars 88 and 90 to pass between the
wall 214 and the platform 154 and to release the sheets they carry to fall onto the
platform in offset fashion, that is with odd sheets in one position and even sheets
in another position. A large part of the sheets overlap, but there are portions of
the odd sheets which do not overlap the even sheets, and vice versa. The roller 252
on the arm 250 in position A is aligned with the non-overlapping portions of the odd
sheets and in position B with the non-overlapping portions of the even sheets. In
position C, the roller 252 and arm 250 are clear of all sheets. If the height of the
stack sheets on the platform 154 causes the beam between the source 238 and sensor
240,to be obscured, the platform 154 is lowered to allow further sheets to be stacked
thereon.
[0031] The following description assumes that nine sets, each of twentyfive sheets, need
to be collated, giving a total number of sheets of two hundred and twenty five.
[0032] Nine copies of sheet 1 are supplied in succession and delivered by the grippers 84
and 86 in alternate offset positions (Fig.9).
[0033] The arm 250 pivots between positions A and B, but does not affect the stack on the
platform 154 which is below the beam between source 238 and sensor 240. Alternate
insertion of sheets onto the platform 154 by grippers 84 and 86 continues until the
last sheet of the first sequence, that is sheet 1 of set 9, is inserted onto the platform
154 by first sheet gripper 84 (Fig.9). The sheets are stacked alternately in offset
fashion, the offset clearly demarcating each first sheet from adjacent first sheets.
[0034] The arm 250 is then pivoted to position C and the platform 154 raised until it is
above the top of the roller 252. The arm 250 is pivoted to position A, so that it
is beneath the sheets on the platform 154. The platform 154 is lowered and the non-overlapped
portions of the odd sheets of the stack are supported by the roller 252 of the arm
250 (Fig. 10). The platform 154 is lowered until the light beam is no longer obstructed,
leaving space for the insertion of sheet 2 of set 1 by the first sheet gripper 84.
The corner of sheet 1 of set 1 rests directly on the roller 252 of arm 250. The gripper
84 inserts sheet 2 of set 1 below sheet 1 of set 1, deposits the new sheet in alignment
with the previous sheet and passes out from between the platform 154 and the wall
214.
[0035] The arm 250 (Fig.ll) is pivoted to position B, thereby dropping sheet 1 of set 1
onto sheet 2 of set 1. The roller 252 of the arm 250 now supports the non-overlapped
portions of the even sheets on the platform 154, so that the corner of sheet 1 of
set 2 rests directly on the roller 252 of arm 250. Sheet 2 of set 2 is inserted by
second sheet gripper 86 below and deposited upon sheet 1 of set 2. After insertion,
deposition and passage of the gripper 86 beyond the wall 214, the arm 250 is pivoted
to position A, thereby dropping sheet 1 of set 2 onto sheet 2 of set 2.
[0036] The stack of offset sheets is now supported by the non-overlapped portions of the
odd sheets resting on the roller 252 of arm 250. Sheet 2 of set 3 is now inserted
and deposited, followed by pivotation of the arm 250, to drop sheet 1 of set 3 and
to prepare the stack for sheet 2 of set 4.
[0037] This action is repeated as will be understood, until sheet 2 of the last set, set
9 has been inserted and deposited. The arm 250 is pivoted to position B to release
sheet 1 of set 9 and then to position C to allow the platform 154 to be raised again
to its upper position above the roller 252 of arm 250. The arm 250 is pivoted to position
A and the platform 154 lowered to rest the corner of sheet 2 of set 1 upon the roller
252 of arm 250. The gripper 84 then inserts and deposits sheet 3 of set 1 below sheet
2 of set l. The arm 250 is pivoted to position B to release sheets 2 and 1 of set
1 to lie on top of sheet 3 of set 1- on the platform 154. The stack is thus prepared
for the insertion and deposition of sheet 3 of set 2 by gripper 86.
[0038] This action continues until all sets consist of three sheets. The platform 154 is
raised and lowered as before, with the arm 250 being pivoted to positions C and A
as before and the stack is ready to receive the fourth sheets of the sets.
[0039] Each time the platform 154 is lowered, it descends until the light beam between the
source 238 and sensor 240 is not obstructed. This leaves room for about twenty five
sheets to be deposited on the platform before the light beam is obscured.
[0040] When, during this operation, about twentyfive sheets have been deposited on the platform
154, the light beam between source 240 and sensor 238 is obstructed. This causes the
platform 154 to be lowered, until the light beam is no longer obstructed, allowing
another twentyfive sheets to be stacked.
[0041] When each of sets 1 to 7 has been completed with twenty- five sheets, the arm 250
(Fig.12) is moved to position B supporting the corner of set 8, which is not complete.
Sheet 25 of set 8 is inserted and deposited by second sheet gripper 86, thereby completing
set 8. At this stage in the operation, the platform 154 is lowered each time a new
sheet is inserted, because each set dropped by the movement of the arm 250 after insertion
of a new sheet consists of twenty-five sheets.
[0042] Figure 13 shows the final sheet 25 of set 9 being inserted by first sheet gripper
84. The arm 250 is in position A supporting the corner of set 9, which is not completed.
After insertion and deposition of the sheet, and removal of the gripper, the arm 250
is pivoted to position B, thereby dropping the sheets of set 9 onto sheet 25 of set
9 on the platform 154.
[0043] All nine sets are now completed and the arm 250 is pivoted to position C (Fig.14),
to allow the platform 154 to be raised to its upper position, making it convenient
for an operator to remove the collated stacked sets.
[0044] It will be appreciated that the number of sets and number of sheets in each set is
given only by way of example and may be varied withen practical limitations of weight
and height of stack and space available above and below the insertion level.
[0045] In the example given, the front side of each sheet is . uppermost, so that subsequent
sheets of a set must be inserted below existing sheets. If the front side of each
sheet were to face downwards, then subsequent sheets of a set would have to be inserted
above existing sheets, necessitating movement of the arm 250 to the other of positions
A and B than that described.
[0046] Offsetting alternate sheets by angular skewing is not the only method available for
carrying the invention into effect. Non-overlapping portions must be provided by which
the stack of overlapping offset sets of sheets may be alternately engaged and disengaged,
allowing division of the stack to permit additional sheet insertion.
[0047] An electro-mechanical logic control is provided to allow the functions of the apparatus
to be more or less mechanically automated, but it will be understood that, more sophisticated
logic control, for example, a microprocessor control may be used.
[0048] One example of such a logic control is illustrated in Figure 8. In this control,
there is an electro-mechanical counter 276, which can be set manually or automatically
to the number of sets to be collated, and counted down as each sheet arrives so that
it is at zero upon completion. The counter 276 is then reset, either manually or automatically,
to the number of sets for the next sheets to arrive, and this is repeated until all
the sheets of all the sets have arrived.
[0049] The counter 276 controls switches (not shown) which connect a platform homing signal
line 274 to earth line 273 only when at zero.
[0050] If the.apparatus is to be used in association with a copier, duplicator, printer
or like machine, the earth connection signals may be taken from the associated machine,
because such machines usually have incorporated therein a continuous counter which
is operated electromechanically on each copy cycle.
[0051] There are five relay coils Rl, R2, R3, R4 and R5 and two relay hold coils H3 and
H4. Relay coil Rl, when energised, closes normally open contacts Rl-l, Rl-3 and Rl-4
and opens normally closed contacts Rl-2 and Rl-5. Relay coil R2, when energised, closes
normally open contacts R2-1 and opens normally closed contacts R2-2. Relay R3, when
energised.and when held by energisation of hold coil H3, opens normally closed contacts
R3-1, R3-2 and closes normally open contacts R3-3 and R3-4. Relay R4, when energised
and when held by energisation of hold coil H4, closes normally open contacts R4-1
and R4-2. Relay R5, when energised, closes normally open contacts R5-l.
[0052] With the counter 276 at zero, at the end of an operation or before the beginning
of another, the earth potential on line 273 is connected to line 274 through the normally
closed contacts R3-1 to one side of relay Rl, whose, other side is connected to a
power supply line 277. Comtacts Rl-3 and Rl-4 are closed and energise the solenords
256 and 268, respectively, thus holding the arm 250 in position C. Contacts Rl-2 are
opened, preventing energisation of relay R-2. Contacts Rl-l are closed, energising
relay R5 whilst the contacts of sheet platform upper limit switch 242 remain closed.
Energisation of relay R5 closes contacts R5-l, thereby energising sheet platform reversible
lift motor 194 to raise the platform 154 until in the upper position the limit switch
242 is actuated to open its contacts. When this occurs, relay R5 is de-energised,
the contacts R5-1 open and the motor 194 is de-energised, causing the platform 154
to come to rest in the upper position. When the number of sets to be stacked is entered
in the counter 276, manually or automatically, earth potential is removed from line
274. Relay Rl becomes de-energised, the contacts Rl-3 and Rl-4 open, allowing the
arm 250 to return to position A. Contacts Rl-l open to maintain de-energisation of
relay R5. Contacts Rl-2 close. The'platform 154 in the upper position obstructs the
light beam from source 238 to sensor 240. The source 238 and sensor 240 form part
of a sensor unit 278 connected to earth line 273 and power supply line 277 and including
a signal amplifier. With the light beam obstructed, the sensor unit 278 provides an
earth potential to sheet height sensor output line 280 which is connected through
normally closed contacts R3-2, the contacts of sheet platform lower limit switch 244
and contacts Rl-2, to relay R2. Energisation of relay R2 causes contacts R2-1 to close
and motor 194 to be energised to lower the platform 154 until the light beam is unobstructed.
The earth potential on line 280 increases to the supply voltage thus de-enerc Lng
relay R2, opening contacts R2-1 to de-energise motor 19 The momentum of the system
causes the platform 154 to come to rest below the light beam leaving room for about
twenty- five sheets before obstruction occurs.
[0053] The gripper 84 is in position to receive a sheet, so that the normally open contacts
of switch 40 are closed and the normally closed contacts open by contour 100. When
a sheet actuates the switch 38, relay R3 is energised.
[0054] Contacts R3-1 and R3-2 are opened, disabling relays Rl and R2. Contacts R3-3 and
R3-4 are closed. Closure of contacts R3-3 does not energise the hold coil H3 because
the normally closed contacts of switch 40 are open. When the switch 38 is closed,
a signal is sent over line 275 to the counter 276 to cause a count-down to the next
lower number. If first sheet gripper 84 is in the position to receive a sheet, the
normally open contacts of switch 40 are closed by counter 100. Relay R4 is not energised
because both sets of contacts of switch 282 are open as the gripper 86 at the entrance
to station 22 does not hold a sheet.
[0055] The contacts R3-4 close upon energisation of relay R3, energising gripper drive motor
78 to advance the first sheet gripper 84 towards the station 22 and the second sheet
gripper 86 to advance through the station 22 and to a position to receive the next
sheet. Shortly after the start of such advance, the lever of the switch 40 disengages
the contour 100, so energising the holding coil H3 through the contacts R3-3 and de-energising
the relay R4, which is however latched by its holding coil H4. The gripper 84 advances
a sheet towards the station 22 and its presence there is sensed by closure of the
switch 282. As the gripper 86 reaches the position to receive the next sheet, the
switch 42 is operated by the contour 124. This opens the normally closed contacts
and de-energises the holding coil H3 and thus releases relay R3. This de-energises
the motor 78, bringing the grippers 84 and 86 to rest.
[0056] The next sheet arrives and operates the switch 38, energising the relay R3 and thus
the motor 78 grippers 84 and 86 are advanced and the switch 42 is released from contour
124. The relay R3'is then latched on by holding coil H3 and the gripper 84 draws the
first sheet into the station 22 where it is released on to the platform 154, with
the arm 250 in position A (though not in this case performing its later function).
Gripper advance continues until the gripper 84 reaches the position to receive a sheet,
where the switch 40 is operated by contour 100. Opening of the normally closed contacts
of switch 40 de-energises the holding coil H3 to release the relay R3, because closure
of one pair of contacts of the switch 282 at this time has no effect since line 274
is not at earth potential. The relay R4 is energised through the closure of the other
pair of contacts of switch 232 and the normally open contacts of switch 40 and is
held on by holding coil H4 through normally closed contacts of switch 42. This energises
solenoid 256, which moves the arm 250 to position B.
[0057] The arrival of a third sheet to operate switch 38 restarts this double cycle which
is repeated as further sheets arrive, until the sheet for the last set arrives. At
this point, the counter 276 is counted down to zero and earth potential applied to
line 274. However, energisation of relay R3 and consequential opening of contacts
R3-1 prevents energisation of relay Rl. If the number of sets is an odd number, e.g.
nine, the gripper 84 receives the last sheet and the switch 40 is operated by the
contour 100. This causes the solenoid 256 to pivot the arm 250 to position B. Energisation
of relay R3 causes the grippers 84 and 86 to be advanced and the relay R3 is latched
on when the lever of the switch 40 disengages the contour 100. The grippers continue
to advance through the apparatus until the gripper 84 reaches the position to enter
the station 22. At this point the gripper 86 is in position to receive another sheet
and the switch 42 is operated by contour 124. However, the holding coil H3 continues
to be energised through the closed contacts of switch 282 which connect it to the
line 274 at earth potential. The gripper 84 continues through the station 22 until
it reaches the position to receive sheets and the switch 40 is operated by contour
100. At this point, the holding coil H3 is de-energised, because the switch 282 has
re-opened due to the absence of a sheet in gripper 86. Relay R3 is de-energised and
the apparatus stops with the gripper 84 -in position for the second sheet of the first
set.
[0058] If the number of sets is an even number, the last sheet will be conveyed by gripper
86. When the switch 38 is operated by the sheet, the switch 42 is open due to contour
124. However, holding coil H3 will be energised through switch 282 which is operated
by the previous sheet. When the gripper 86 arrives in front of the station 22, the
switch 282 is again operated by a sheet and the holding coil H3 continues to be energised
through switch 282 until the lever of the switch 40 disengages the contour 100, and
energisation is then through the normally closed contacts of switches 40 and 42. When
the gripper 86 reaches the position to receive a sheet the switch 42 opens, but a
connection from the line 274 to between the switches 40 and 42 enables continued energisation
of the holding coil
H3 until the gripper 84 reaches that position. The normally closed contacts of switch
40 are opened and the holding coil H3 de-energised, releasing relay R3.
[0059] The relay Rl is energised through the normally closed contacts R3-1 from the line
274. The relays R2 and R3 are disabled by opening of contacts Rl-2 and Rl-5. The solenoids
256 and 268 are energised by closure of contacts Rl-3 and Rl-4. The relay R5 is energised
by closure of contacts R1-1. This closes the contacts R5-1 which energise the motor
194 to raise the platform 154 to the upper position, carrying the stack of first sheets
of the sets in alternate offset configuration. On reaching the upper position, the
switch 242 is opened, the relay R5 de-energised.
[0060] When the second sheets of the sets are to be delivered, the number of sets to be
stacked is entered in the counter 276, manually or automatically, and earth potential
removed from the line 274.
[0061] The operation then commences and continues as above described, the first function
being the lowering of the platform 154 with the arm 250 in position A. The stack of
sheets is thus left in position for the second sheet of the first set to be inserted.
The arm 250 cannot be moved from this position until a sheet is at the entrance to
station 22, as sensed by switch 282, and the gripper 84 is in position to receive
a sheet as sensed by operation of switch 40 by contour 100.
[0062] With the second sheet of the second set to be inserted, the arm 250 is moved to position
B, allowing the first sheet of the first set to drop on to the second sheet of the
first set on the platform 154. Offset collation continues until all the second sheets
are in the stack and the platform and stack are returned to the upper position with
the arm 250 in position C.
[0063] The operation as before described is then repeated as many times as necessary until
all sheets of all sets are collated. As sheets are stacked on the platform 154, the
light beam from source 238 to sensor 240 may be obstructed causing the sensor unit
278 to earth the line 280. At this point, the relay R3 is held by holding coil H3
or energised through switch 38. Thus the relay R2 cannot be energised, because the
contacts R3-2 are open. When a sheet has passed the switch 38 and the next gripper
has reached the position to receive a sheet, normally closed contacts of switches
40 and 42 are opened, de-energising holding coil H3 and releasing relay R3. Contacts
R3-2 close and the relay R2 is energised. The platform 154 is lowered until'the sheets
are spaced below the light beam, as described above. During this operation, the relay
R3 cannot be energised, because the contacts R2-2 are opened.
[0064] Finally, after the last sheet of the last set has been stacked on the platform 154,
and the platform 154 raised to the upper position, an operator can conveniently remove
the collated stacked sets. If the full capacity of the apparatus is reached before
the finishing of a job, the platform 154 operates the lower limit switch 244 to open
the normally closed contacts thereof. This prevents energisation of relays 2 and 3,
thus stopping the collation process. The line 274 is earthed automatically or manually,
for example, by setting the counter 276 to zero, and the relay Rl energised to raise
the platform 154 to the upper position.
[0065] The collated stack of sheets is then removed and the sequence restarted, by resetting
the counter.
[0066] In the timing diagram of Figure 9, time TO represents the time before operation begins
and time Tl the time at which the first sheet arrives at switch 38. Between times
TO and Tl, the counter 276 is set, disconnecting the line 274 from earth. The solenoids
256 and 268 are de-energised and the arm 250 pivots to position A. The motor 194 is
energised to lower the platform 154 until sensor unit 278 indicates non-obstruction
of the light beam.
[0067] At time Tl, the arrival of the first sheet of set 1 initiates advance of the grippers
by energisation of motor 78. Shortly after, switch 40 is released from contour 100.
When switch 42 is engaged by contour 124, motor 78 is de-energised.
[0068] At time T2, the arrival of the first sheet of set 2 restarts advance of the grippers
by energisation of motor 78. Shortly after, switch 42 is released from contour 124.
The first sheet of set 1 is deposited on platform 154. When switch 40 is engaged by
contour 100, motor 78 is de-energised. As the first sheet of set 2 has operated switch
282 at the entrance to station 22, the relay R4 is energised and held by the holding
coil H4. This energises the solenoid 256 to move the arm 250 to position B.
[0069] At time T3, the arrival of the first sheet of set 3 restarts advance of the grippers
by energisation of motor 78. Shortly after, switch 40 is released from contour 100.
[0070] The first sheet of set 2 is deposited on the first sheet of set 1 on platform 154.
When switch 42 is engaged by contour 124, motor 78 is de-energised.
[0071] This sequence continues until time T9 when the first sheet of set 9 arrives. This
initiates a cycle similar to that after time Tl, except that line 274 is at earth
potential. Holding coil H3 continues to be energised by closure of switch 282, when
switch 42 is engaged by contour 124, so that motor 78 continues to be energised at
and after time T10, when no further sheet arrives (compare time T250). The first sheet
of set 9 is deposited on the first sheet of set 8 on the platform 154. When switch
40 is engaged by contour 100, motor 78 is de-energised.
[0072] There is now no sheet to operate switch 282, so that holding coil H3 is de-energised,
releasing relay R3. Relay Rl is energised through earthed line 274 and contacts R3-l.
This energises solenoids 256 and 258 to pivot arm 250 to position C and relay R5 to
energise the motor 194 to raise the platform and stack to the upper position.
[0073] Before time Tll, when the second sheet of set 1 arrives, the counter 276 is reset
and the relay Rl de-energised. This de-energises the solenoids 256 and 268 to allow
the arm 250 to return to position A, and allows the sensor unit to energise relay
R2 to drop the platform 154 to below the light beam, leaving a corner of the stack
supported by the roller 252 on the arm 250 as described above.
[0074] At time Tll, the second sheet of set 1 arrives and the cycles of operation at times
Tl to T10 are repeated, the second sheets being inserted in the stack which is separated
to receive them in collated fashion. The operation is repeated as the additional sheets
of all the - sets arrive, with no significant change in operation until the height
of the stack obscures the light beam as depicted by one example between the times
T
198 and T199.
[0075] At time T
198, the twentieth sheet of set 8 actuates switch 38. The sensor unit provides an earth
potential on line 280 as set 7 is lowered onto the platform 154 by pivotation of the
arm 250 to position B. This causes the motor 194 to be energised to lower the platform
154, until the light beam is not obstructed. Then, the operation continues.
[0076] At time T
199, the twentieth sheet of the set 9 arrives and the counter 276 goes to zero and applies
an earth potential to line 274. Relay R3 is energised at this time, so that relay
Rl cannot be energised and relay R3 remains held by holding coil H3 from time T
199 until after time T
200, when no sheet arrives, but the twentieth sheet of set 9 is inserted into the stack.
After such insertion, switch 282 is no longer operated and when switch 40 engages
contour 100, holding coil H3 is de-energised, releasing relay R3, so that relay Rl
is energised. This energises relay R5 which energises the motor 194, causing the platform
154 to be raised.
[0077] After time T
248' when the twentyfifth sheet of set 8 arrives, the operation is similar to that after
time T198.
[0078] At time T
249, the twentyfifth sheet of set 9 arrives and the operation continues as previously
described after time T
199. At time T
250, when no sheet arrives, the relay R3 continues to be held by holding coil H3, as
there is a sheet operating switch 282 and still to be inserted. After.insertion of
the last sheet, the gripper 84 arrives in position to receive a sheet, the switch
40 being actuated by contour 100. The relay Rl is energised, energising the relay
R5 and the solenoids 256 and 268. The arm 250 is moved to position 3 and the motor
194 energised to lift the platform 154 and stack of collated sheets.
[0079] With the platform 154 in the upper position, the switch 242 is opened and the relay
R5 de-energised. This stops the motor 194 and the apparatus at time T
251 is in the same condition as at time TO.
[0080] It will be observed that with an odd number of sets to be collated, the apparatus
performs that number plus one cycle for each sheet. With an even number of sets to
be collated, the apparatus will perform that number plus two cycles for each sheet
in order to bring the first gripper 84 back to the home position. It will be appreciated
that many variations may be made in the precise mechanical and control details of
apparatus for performing the invention within the scope of the appended claims.
1. A method of collating sets of sheets, which are received serially in groups of
similar sheets, comprising the steps of stacking the sheets of the first group received
in individually offset fashion, demarcating each first sheet from adjacent first sheets,
and inserting individual sheets of the next group in the same offset fashion contiguous
to individual first sheets, and thereafter inserting, if necessary, individual sheets
of subsequent groups in the same contiguous to individual prior-inserted sheets of
the same set to form collated sets of sheets.
2. A method according to Claim 1, including the steps of separating adjacent stacked
sheets at the appropriate location prior to the insertion of a sheet.
3. A method according to Claim 1 or 2 in which the first inserted sheet of each group
after the first is inserted behind the previously inserted sheet of the first set.
4. A method according to Claim 3, in which the first inserted sheet of each group
after the first is inserted below the previously inserted sheet of the first set.
5. A method according to Claim 1, 2, 3 or 4, in which the offset is achieved by skewing
sheets alternately in opposite directions prior to stacking or insertion.
6. A method according to Claim 5, including the steps of lifting an offset corner
of stacked sheets, inserting the next sheet, dropping the stacked sheets, and lifting
the next opposite corner of stacked sheets prior to insertion of the next following
sheet, and so on.
7. Apparatus for collating sets of sheets, which are received serially in groups of
similar sheets, comprising means to stack the sheets of the first group received in
individually offset fashion, demarcating each first sheet from adjacent first sheets,
and means to insert individual sheets of the next group in the same offset fashion
con- . tiguous to individual first sheets and to insert, if necessary, individual
sheets of subsequent groups in the same fashion contiguous to individual prior inserted
sheets of the same set to form collated sets of sheets.
8. Apparatus according to Claim 7, including a movable sheet platform for receiving
and maintaining sheets in offset fashion.
9. Apparatus according to Claim 8, in which the movable sheet platform is movable
vertically.
10. Apparatus according to Claim 7, 8 or 9, including means for separating adjacent
stacked sheets at the appropriate location prior to insertion of a sheet.
ll. Apparatus according to Claim 7, 8, 9 or 10, including offsetting means operable
to skew sheets alternately in opposite directions prior to stacking or insertion.
12. Apparatus according to Claim 11, in which the offsetting means comprises alternately
offset sheet gripping means movable to co-operate with camming means to open the gripping
means to receive a sheet and to release a sheet.
13. Apparatus according to Claim 11 or 12, including means to lift alternate corners
of adjacent stacked sets prior to individual sheet insertion.