[0001] The invention relates to a segment of a motorway construction. The invention also
               relates to a motorway construction of this type and to a method of installing it.
 
            [0002] Given that the motorways are becoming increasingly crowded, means are being sought
               of increasing the capacity of the motorways. In the first instance, a conceivable
               approach would be to widen the motorways to provide more capacity, but in many locations,
               for example in urban areas, this is not possible. In addition, making motorways wider
               is costly and, in view of the problems involved in acquiring the land next to the
               motorways, time consuming. In many cases, widening a motorway is also not desirable
               in view of the larger area taken up and the environmental impact.
 
            [0003] It is an object of the invention to provide greater road capacity without road-widening
               being required. It is another object of the invention to provide greater road capacity
               against relatively low costs.
 
            [0004] Another object of the invention is to provide a method of building such a motorway.
               Still another object of the invention is to provide such a method which can be implemented
               relatively quickly.
 
            [0005] According to a first aspect of the invention, one of these objects is achieved by
               means of a segment of a motorway construction for a motorway, comprising a crash barrier
               construction which includes a crash barrier, a channel construction joined thereto
               and substantially parallel thereto, and fastening means for joining the crash barrier
               and the channel construction, and to which a plate is fitted, which is joined to the
               channel construction and serves as at least partial support for a lane of the motorway.
 
            [0006] This provides the basis for a construction which is simple to fabricate in an integrated
               manner and to install next to and under the hard shoulder, by means of which the hard
               shoulder can be converted into an additional lane. By installing an intelligent signalling
               and detection system to detect the road users on the motorway and the hard shoulder,
               and in particular to detect stranded vehicles on the hard shoulder, and by issuing
               signals to the road users, particularly the road users on the former hard shoulder
               in the event of, for example, a stationary vehicle on the hard shoulder, it is readily
               possible to use the current hard shoulder as an additional lane. The plate which is
               joined to the channel construction is meant to support the hard shoulder of a motorway,
               to carry the varied and heavy traffic making use of the hard shoulder when it serves
               as an additional lane. To prevent subsidence and the like, it is then possible to
               remove (part of) of the road surface of the hard shoulder, and doing away with the
               need for a sand bed which would first have to settle, the segments together with the
               plates can be installed. The plates distribute the point load of a lorry or car over
               a larger area, thus preventing subsidence. The plates can be supported by slabs or
               blocks of foamed plastic, and on top of the plates an underlayer is applied, if required,
               and a customary top layer such as asphalt. With the aid of the segments according
               to this preferred embodiment, the hard shoulder, which is to serve as an additional
               lane, can therefore be simply and rapidly made suitable to carry a great deal of road
               traffic.
 
            [0007] The conversion of hard shoulder to lane is in particular well implementable when
               the channel construction comprises a cable channel, through which the electricity
               cables and control cables for the detection system to detect the road users and the
               signalling or warning system for issuing signals to the road users can be run.
 
            [0008] Preferably, this cable channel is covered by a removable sealing element which serves
               to protect the cables. At the same time, the sealing element can serve as a footway
               when the channel is disposed on that side of the crash barrier which is to face away
               from the motorway. This footway can be used, for example, as an escape route and as
               a walking route to for example an emergency telephone for a stranded driver. Likewise,
               it is possible to use the sealing element for maintenance vehicles for maintaining
               the segments and the like to run on.
 
            [0009] Instead of a cable channel, the channel construction can also comprise a water drain
               channel, and the segment comprises preferably both a water drain channel and a cable
               channel. The water drain channel is particularly important in urban areas for removing
               rain water.
 
            [0010] According to a preferred embodiment, that side of the segment which is to face away
               from the motorway is fitted with attachment constructions for a noise barrier. Fitting
               a noise barrier along the motorway is then an easy matter after the segments have
               been installed, without requiring a separate foundation or the like. The noise barrier
               can, for example, consist of a steel-plate sandwich construction, a fibrous material
               such as mineral wool or glass wool being arranged between the steel plates.
 
            [0011] Preferably, that side of the segment which is to face away from the motorway is fitted
               with attachment constructions for one or more transceiver masts for signalling equipment
               and/or communications equipment. Since a good signalling system is required if the
               hard shoulder is used as an additional lane, and a communications system with the
               road users is also desirable, a great deal of signalling and communications equipment
               is required along the motorway with the motorway construction according to the invention.
               It is therefore highly advantageous for the segments of said motorway construction
               to be already provided with attachment constructions for transceiver masts for this
               equipment, so that these masts, after the segments have been installed along the motorway,
               can be put into position without much trouble, without further separate foundations
               and the like being necessary for this purpose. For that matter, such masts are also
               suitable for mobile telephone applications.
 
            [0012] Preferably, the attachment constructions are suitable both for installing transceiver
               masts and for noise barriers. Thus, the segments are kept as simple as possible. At
               the same time, this allows the motorway construction to be installed rapidly, whilst
               as many installation activities as possible will have been carried out beforehand
               by means of prefabrication. If desired, the noise barriers and the masts can also
               be attached to one another.
 
            [0013] According to a preferred embodiment, the segment on its side which is to face the
               motorway is provided with controllable signalling means. These signalling means can,
               for example, be lamps or arrows which are therefore located on the right-hand side
               of the additional lane on the hard shoulder, and which can be controlled via the signalling
               equipment. If the signalling equipment notices, for example, that a vehicle on the
               former hard shoulder reduces speed sharply and comes to a stop, the signalling equipment
               can warn the road users behind, so that they will move to the left and drive on what
               was originally the right-hand half of the road. This can be achieved, for example,
               by having the signalling means light up red. The signalling means can, for example,
               be attached to the crash barrier or be incorporated in the road surface.
 
            [0014] According to a preferred embodiment, pipe loops are disposed above the plate for
               a cooling or heating medium to be passed through. It is thus possible in the winter
               to pass warm water, for example, underneath the additional lane, so that, for example,
               no glazed frost will be formed. The water thus heated can, if required, be further
               processed with the aid of a heat pump and be used for other purposes. Equally, it
               is possible, with hot weather in the summer, to pass cool water through the pipe loops,
               so that no ruts will form.
 
            [0015] The pipe loops are preferably connected to a conduit present in the channel. This
               results in an integrated heating/cooling system.
 
            [0016] According to a preferred embodiment, the plate, on its side which is to face away
               from the crash barrier construction, is provided with controllable signalling means.
               This means that signalling means are also present in the additional lane or on the
               left-hand side of the additional lane, via which the road users can be warned, if
               necessary, that they must move to what was originally the right-hand lane.
 
            [0017] According to an advantageous embodiment, the crash barrier of the crash barrier construction
               is substantially connected to the road surface of the motorway. This is particularly
               important for motorcyclists who, in the event of a crash, will, with the current crash
               barrier, come to lie up against and half underneath the crash barrier, which may result
               in serious injury.
 
            [0018] Preferably, the segment is substantially made of steel. Steel has the strength and
               stiffness required for this type of segments.
               The invention also relates to a motorway construction comprising two or more of the
               segments as described above.
 
            [0019] The invention also relates to a method of installing a motorway construction comprising
               segments as described hereinabove, provided with a plate which is joined to the channel
               construction and serves as at least partial support for a lane of the motorway, wherein
               the lane adjoining the crash barrier construction is built by placing a layer consisting
               of slabs or blocks of foamed plastic on top of the road bed, placing two or more segments
               with their plate on top of the foamed plastic, possibly applying an underlayer, and
               applying a top layer, for example of asphalt.
 
            [0020] This provides a relatively simple and rapid method of using the said segments to
               build up a hard shoulder, which does not have a sufficiently high load-bearing capacity
               to be used as an additional lane, into an additional lane suitable for varied traffic,
               while at the same time providing at least the crash barrier construction and the channel
               construction.
 
            [0021] The invention will be explained below with reference to a specific embodiment and
               referring to the drawing.
 
            [0022] Figure 1, schematically and not to scale, shows a specific embodiment of a segment
               of a motorway construction according to the invention.
 
            [0023] The figure shows a segment 1 of a motorway construction according to the invention,
               into which as many of the desired functions are integrated as possible.
 
            [0024] The segment 1 consists of a crash barrier 2 which, with the aid of fastening constructions
               3, is attached to a channel construction 4. The channel construction 4, in the example
               shown, includes a water drain channel 5 and a cable channel 6. The water drain channel
               runs underneath the attachment constructions, in order to take up as little space
               as possible, and must be connected periodically to further water drain channels.
 
            [0025] The cable channel 6 is covered by a removable sealing element 7. The cables for,
               for example, transceiver masts and signalling equipment (see below) can be laid in
               the cable channel in a simple manner, without having to be buried in solid ground.
               Repair and replacement is thus much simpler, and it is also possible to lay other
               cables, which per se have nothing to do with the motorway, in the cable channel.
 
            [0026] The sealing element 7 must be installed to protect the cables against rain water
               and the like, and as a result, the sealing element can also do excellent service as
               a footway behind the crash barrier, for use as an escape route and as walking route
               for a stranded road user, for example to an emergency telephone. Likewise, maintenance
               vehicles for motorway construction and the like can be propelled on top of the sealing
               element.
 
            [0027] Extending on that side of the crash barrier 2 which faces the motorway is a steel
               plate 8 which, after the segment has been put into place, extends below the road surface.
               On top of the steel plate, an optional underlayer and a mandatory top layer of asphalt,
               for example, is applied, so that the rain water will flow into the water drain channel
               5 by itself. The steel plate can be planar, or to provide greater stiffness, be provided
               with a relief. On its side facing away from the crash barrier, the steel plate is
               provided with a raised edge 9, disposed within which at the top are signalling means
               in the form of e.g. LEDs 10, which usually emit white light, but in the event of a
               control signal light up red.
 
            [0028] Disposed above the steel plate 8 at regular intervals are pipe loops 11 which are
               connected to a conduit (not shown) which, for example, can run through the cable channel
               6. In winter, a heating medium such as warm water can be passed through the conduit
               and the pipe loops 11, for example to prevent glazed frost or cause snow to melt,
               and in summer cold water can be passed through to counteract ruts in excessively warm
               asphalt.
 
            [0029] Disposed on that side of the channel construction 4 which faces away from the motorway
               are attachment constructions 12 against the channel construction. These attachment
               constructions 12 are provided with a structure 13, to which transceiver masts 14 for
               signalling and communication equipment can be attached in a simple manner, and to
               which attachment fins 15 for noise barrier 16 can be attached. The attachment constructions
               12 at the end of the segment can also serve to interconnect the segments.
 
            [0030] The use of the segments as described hereinabove is as follows.
 
            [0031] If a hard shoulder must be converted into an additional lane, and the hard shoulder
               has not been designed to bear varied and heavy (freight) traffic, the hard shoulder
               and its subsoil must be dug away to a certain depth. A layer of foamed plastic is
               then arranged in the form of slabs or blocks. On top of the foamed plastic, the segments
               are then fitted, in such a way that the steel plates rest on the plastic base. The
               channel construction can, if required, project at the side of the plastic slabs or
               blocks, but must of course be supported. The sections are joined to one another, for
               example, by welding. On top of the steel plates of the segments an optional underlayer
               and finally a top layer of, for example, asphalt is then applied. The pipe loops are
               incorporated in this layer or layers. Then the transceiver masts can be mounted in
               the attachment construction in a simple manner and the noise barriers can be put into
               place.
 
            [0032] This method can be carried out relatively quickly and inexpensively, by virtue of
               using the integrated segments, and has the major advantage that it is not necessary
               for a sand bed to be left to settle, since the steel plates will divert the point
               loads from the cars or lorries over a larger area, so that the subsoil will not settle.
 
            [0033] The segments provided with a steel plate are also eminently suitable in the construction
               of new motorways.
 
          
         
            
            1. Segment of a motorway construction for a motorway, comprising a crash barrier construction
               which includes a crash barrier, a channel construction joined thereto and substantially
               parallel thereto, and fastening means for joining the crash barrier and the channel
               construction, and to which a plate is fitted which is joined to the channel construction
               and serves as at least partial support for a lane of the motorway.
 
            2. Segment according to claim 1, wherein the channel construction comprises a cable channel
               and/or a water drain channel.
 
            3. Segment according to any one of the preceding claims, wherein the channel construction
               is covered by a removable sealing element, wherein preferably the covered channel
               construction is arranged on that side of the crash barrier which is meant to face
               away from the motorway, and serves as a footway and/or roadbed for (maintenance) vehicles.
 
            4. Segment according to any one of the preceding claims, wherein that side of the segment
               which is to face away from the motorway is fitted with attachment constructions for
               a noise barrier.
 
            5. Segment according to any one of the preceding claims, wherein that side of the segment
               which is to face away from the motorway is fitted with attachment constructions for
               one or more transceiver masts for signalling equipment and/or communications equipment.
 
            6. Segment according to the preceding claim 4 or 5, wherein the attachment constructions
               are suitable for fitting both a noise barrier and transceiver masts.
 
            7. Segment according to any one of the preceding claims, wherein the segment on its side
               which is to face the motorway is provided with controllable signalling means.
 
            8. Segment according to any one of the preceding claims, wherein pipe loops are disposed
               above the plate for a cooling or heating medium to be passed through, wherein preferably
               the pipe loops are connected to a conduit present in the channel construction.
 
            9. Segment according to any one of the preceding claims, wherein the plate, on its side
               which is to face away from the crash barrier construction, is provided with controllable
               signalling means.
 
            10. Segment according to any one of the preceding claims, wherein the crash barrier of
               the crash barrier construction is substantially connected to the road surface of the
               motorway.
 
            11. Segment according to any one of the preceding claims, wherein the segment is substantially
               made of steel.
 
            12. Motorway construction comprising two or more of the segments according to any one
               of the preceding claims.
 
            13. Method of installing a motorway construction comprising segments according to any
               one of the preceding claims, wherein the lane adjoining the crash barrier construction
               is built by placing a layer consisting of slabs or blocks of foamed plastic on top
               of the roadbed, placing two or more segments with their plate on top of the foamed
               plastic, possibly applying an underlayer, and applying a top layer, for example as
               asphalt.