Technical Field
[0001] The present invention relates to a heat source side unit and a refrigeration air-conditioning
apparatus. Particularly, the present invention relates to an apparatus which can wash
an existing refrigerant pipeline and recover foreign substances and the like when
the air-conditioning apparatus is installed.
Background Art
[0002] Hitherto, when a refrigeration air-conditioning apparatus, which is a so-called split
refrigeration cycle apparatus, is installed in a building or the like, the installation
might be accomplished by using an existing refrigerant pipeline (hereinafter referred
to as an existing pipeline). For example, a heat source side unit and a load side
unit to be removed are replaced by a new heat source side unit (outdoor unit) and
load side unit (indoor unit) and they are connected to the existing pipeline to perform
the installation. In such installation, since it is not necessary to replace the refrigerant
pipeline with a new one, labor, cost and time required for the replacement work of
the refrigerant pipeline can be reduced. Also, since it is only necessary to replace
the heat source side unit and the load side unit, large-scale construction work in
the building or the like in which the refrigeration air-conditioning apparatus is
installed is not required, and reliability of the refrigeration air-conditioning apparatus
is improved.
[0003] When the existing pipeline is used as described above, in the refrigeration air-conditioning
apparatus, usually after the heat source side unit and the load side unit are replaced,
old refrigerator oil (mineral oil) remaining in the existing pipeline and other foreign
substances such as depleted substances (hereinafter referred to as foreign substances
and the like) are recovered (See Patent Literature 1, for example).
Citation List
Patent Literature
[0004] Patent Literature 1: Japanese Unexamined Patent Application Publication No.
2004-333121 (Fig. 2)
Summary of Invention
Technical Problem
[0005] In the refrigeration air-conditioning apparatus as above, a new refrigerant is made
to circulate through a refrigerant cycle through which a refrigerant is circulated,
for example, so that the foreign substances and the like remaining in the existing
pipeline are washed out by the refrigerant and recovered (hereinafter the operation
for washing and recovering the foreign substances and the like is referred to as a
recovery operation). Thus, a recovery unit (recovery tank) which catches and recovers
the washed-out foreign substances and the like by a filter, gravity separation or
the like becomes necessary. Also, an oil tank is also needed to replenish new refrigerator
oil (hereinafter referred to as refrigerator oil) whose amount becomes insufficient
during the recovery operation.
[0006] The recovery unit or oil tank as above is means which occupies a large capacity in
the heat source side unit and is left in the heat source side unit even after the
recovery operation, for example, until it is replaced by the subsequent heat source
side unit. Here, the oil tank is disposed independently of the refrigerant cycle and
has pipeline connection or the like to replenish the refrigerator oil in a compressor
separately from an oil separator mounted in the refrigerant cycle.
[0007] Also, the recovery unit is disposed on a pipeline of another system connected in
parallel with the refrigerant cycle. Here, when an outside air temperature is low,
for example, the refrigerant stagnation occurs in the recovery unit and the refrigerant
can collect in the recovery unit more than necessary. If it is judged that the refrigerant
is not sufficient in the refrigerant cycle, and the refrigerant is replenished in
this state, a charged amount of the refrigerant might be inadvertently large. As a
result, excess charging of the refrigerant increases a cost or an excess refrigerant
overflows from an accumulator, which might make liquid return into the compressor
excessive and break the compressor or the like.
[0008] The present invention was made to solve the above problems and an object thereof
is to provide a heat source side unit and a refrigeration air-conditioning apparatus
in which a tank can be effectively used or the like, efficient recovery can be made,
and a refrigerant amount can be made appropriate.
Solution to Problem
[0009] A heat source side unit according to the present invention is a heat source side
unit, which has a compressor and a heat source side heat exchanger and forms a refrigerant
cycle by connecting an expansion device and a load side heat exchanger by a pipeline,
including an oil tank to feed and supply refrigerator oil to the compressor due to
a lack of refrigeration oil caused by washing the refrigerant cycle. The oil tank
is disposed in the refrigerant cycle. Also, the oil tank and a recovery unit are integrally
formed having a partition with pressure resistance between them. Advantageous Effects
of Invention
[0010] According to the present invention, since the oil tank is disposed in the refrigerant
cycle so that the refrigerant can pass therethrough, the refrigerant cycle can be
simplified, workability is improved, and a manufacturing cost can be reduced. Also,
pulsation of the refrigerant discharged from the compressor can be reduced or the
like in the oil tank. Moreover, by integrally forming the oil tank and the recovery
unit, temperature drop of the recovery unit is prevented, and stagnation of the refrigerant
in the recovery unit can be prevented. Thus, a refrigerant amount which has been decreased
by the recovery operation can be judged with accuracy, and an appropriate amount of
the refrigerant can be replenished. Therefore, a risk of liquid return of the excess
refrigerant to the compressor is reduced, and a system with high reliability can be
realized.
Brief Description of Drawings
[0011]
[Fig. 1] Fig. 1 is a diagram illustrating a configuration of a refrigeration air-conditioning
apparatus according to Embodiment 1.
[Fig. 2] Fig. 2 is a diagram illustrating a procedure related to replacement including
a recovery operation.
[Fig. 3] Fig. 3 is a flowchart illustrating processing related to charging of a refrigerant
into a refrigerant cycle during the recovery operation. Description of Embodiments
Embodiment 1.
[0012] Fig. 1 is a configuration diagram of a refrigeration air-conditioning apparatus according
to Embodiment 1 of the present invention. In this embodiment, a refrigeration air-conditioning
apparatus, which is a refrigeration cycle (heat-pump cycle) apparatus, will be described.
The refrigeration air-conditioning apparatus in Fig. 1 is provided with a heat source
side unit (outdoor unit) 100 and a load side unit (indoor unit) 200, and these units
are connected by refrigerant pipelines so as to form a refrigerant cycle (hereinafter
referred to as a refrigerant cycle) through which a refrigerant is circulated. Among
the refrigerant pipelines, a pipeline through which a gas refrigerant flows is referred
to as a gas pipeline 300, and a pipeline through which a liquid refrigerant (liquid
refrigerant, or a gas-liquid two-phase refrigerant in case) flows is referred to as
a liquid pipeline 400. In this embodiment, the heat source side unit (outdoor unit)
100 and the load side unit (indoor unit) 200 are assumed to be new units after the
replacement. Also, the gas pipeline 300 and the liquid pipeline 400 are assumed to
be existing pipelines. Here, the magnitude of the pressure is not determined by a
relationship with a pressure that serves as a reference (numerical value). The magnitude
of the pressure is assumed to be expressed on the basis of a relative level in the
refrigerant cycle as the result of control of pressurization of a compressor 101,
an open/closed state (opening degree) of each expansion device (flow control device)
and the like. The same also applies to temperature.
[0013] With regard to the refrigerant to be circulated through the refrigerant cycle, a
non-azeotropic refrigerant mixture (R407C or the like), a near-azeotropic refrigerant
mixture (R410A, R404A or the like), a single refrigerant (R22, R134a or the like),
a natural refrigerant (carbon dioxide, propane or the like) can be used. Here, the
type of refrigerant used before and after the replacement may be the same or may be
different.
[0014] The heat source side unit 100 of this embodiment has the compressor 101, an oil separator
102, a four-way valve 103, a heat source side heat exchanger 104, a heat source side
fan 105, an accumulator 106, a heat source side expansion device (expansion valve)
107, a second heat source side expansion device (expansion valve) 133, an on-off valve
134, a refrigerant supply on-off valve 108, a refrigerant charging port on-off valve
109, an oil tank 110, an inter-refrigerant heat exchanger 113, and check valves 114
and 115 in the refrigerant cycle. Also, in a system different from the refrigerant
cycle, a recovery unit 111 and a capillary tube 112 are connected. A heat source side
control device 120 is provided in order to control each device (means) in the refrigerant
cycle. The oil tank 110 and the recovery unit 111 are integrally formed and have a
mirror plate made of copper or the like therebetween.
[0015] The compressor 101 is formed of an inverter circuit, a compressor motor and the like.
A rotation speed (operation frequency of the compressor 101) of the compressor motor
is controlled by the inverter circuit, and the refrigerant used in the refrigeration
cycle is compressed and circulated through the refrigerant pipeline. Also, the oil
separator 102 separates, from the refrigerant, the refrigerator oil which is mixed
with the refrigerant, discharged from the compressor 101 and becomes lubricant oil.
Then, the separated refrigerator oil is made to flow into the oil tank 110 through
an oil pipeline 116 and to return to the compressor 101 through the oil tank 110 so
as to unify a path of return oil.
[0016] The four-way valve 103 switches the flow of the refrigerant according to a cooling
operation and a heating operation on the basis of an instruction from the heat source
side control device 120. Also, the heat source side heat exchanger 104 exchanges heat
between the refrigerant and the air (outside air). For example, the heat exchanger
functions as an evaporator during the heating operation and exchanges heat between
a low-pressure refrigerant and the air so as to evaporate and gasify the refrigerant.
Also, the heat exchanger functions as a condenser during cooling operation and exchanges
heat between the refrigerant having been compressed in the compressor 101 and flowed
in from the four-way valve 103 and the air so as to condense and liquefy the refrigerant.
In the heat source side heat exchanger 104, the heat source side fan 105 is disposed
so as to exchange heat between the refrigerant and the air efficiently. The heat source
side fan 105 may also have an inverter circuit so that the operation frequency of
the fan motor is arbitrarily changed so as to finely change the rotation speed of
the fan.
[0017] The accumulator 106 is means which collects an excess liquid refrigerant, for example.
In this embodiment, the accumulator also plays the role of separating foreign substances
and the like. The heat source side expansion device 107 adjusts the flow rate and
pressure of the refrigerant flowing from a pipeline through which mainly a liquid
refrigerant flows to a pipeline through which mainly a gas refrigerant flows, for
example. Moreover, the second heat source side expansion device 133 mainly adjusts
the pressure by a using saturation value on the basis of detection performed by a
downstream-side pressure sensor (not shown) in accordance with a withstanding pressure
of the liquid pipeline 400 during the cooling operation. Also, the expansion device
adjusts a liquid back amount flowing back to the accumulator 106 by using a discharge
superheat degree of the compressor 101 during the heating operation.
[0018] The oil tank 110 is filled with the refrigerator oil, and when the refrigerator oil
mixed into the refrigerant and discharged from the compressor 101 during a recovery
operation, for example, collects in the recovery unit 111 and does not return and
the amount thereof becomes insufficient, the refrigerator oil in the compressor 101
is replenished. Here, in this embodiment, the oil tank has a refrigerant inflow pipe
port 110A and a refrigerant outflow pipe port 110B, and the oil tank 110 is disposed
(connected by pipeline in series) in the refrigerant cycle particularly between the
oil separator 102 (compressor 101) and the four-way valve 103 (when the four-way valve
103 is not provided, the heat source side heat exchanger 104). Also, in this embodiment,
one housing is partitioned by a mirror plate or the like so as to form two spaces,
one of which is used as the oil tank 110 and the other as the recovery unit 111. Though
not particularly illustrated, an on-off valve is provided so that the refrigerator
oil does not leak from the oil tank 110 at shipment. The details of the oil tank 110
and the like will be described later.
[0019] The recovery unit 111 has a sufficient space or the like so that foreign substances
precipitate (settle) by use of a filter or gravity and recovers foreign substances
and the like carried with the refrigerant and having collected on the bottom part
of the accumulator 106 and returns the refrigerant flowing with the foreign substances
and the like to the accumulator 106 in the recovery. Thus, a circuit for recovery
different from the refrigerant cycle is formed by a recovery pipeline 117 between
the recovery unit and the accumulator 106. Also, a recovery on-off valve 118 is disposed
in the recovery pipeline 117 and is closed except when the foreign substances and
the like are recovered by the recovery unit 111, for example, so that the foreign
substances and the like do not leak out.
[0020] In the oil pipeline 116 which feeds the oil to the suction side of the compressor
101 from the oil tank 110, the capillary tube 112 adjusts the amount of refrigerator
oil to be fed to the compressor 101 from the oil tank 110. Here, the amount of refrigerator
oil may be adjusted by using a solenoid valve, a flow control device or the like instead
of the capillary tube 112. Also, by arranging the capillary tube 112 and the solenoid
valve in parallel, the solenoid valve may be opened so that the refrigerator oil is
supplied to the compressor 101 in a state in which the amount of refrigerator oil
is not sufficient such as immediately after washing.
[0021] The inter-refrigerant heat exchanger 113 exchanges heat between the refrigerant flowing
into/out of the liquid pipeline 400 and the refrigerant flowing into/out of the gas
pipeline 300. Particularly in this embodiment, since the gas-liquid two-phase refrigerant
has a pipeline washing effect higher than that of a gas or liquid single-phase refrigerant,
the gas-liquid two-phase refrigerant is made to pass through the liquid pipeline 400
and the gas pipeline 300 by heat exchange during the recovery operation. Also, during
the usual cooling operation, heat is exchanged between the liquid refrigerant to be
fed out to the load side unit 200 and the refrigerant from the load side unit 200
side so as to supercool the liquid refrigerant. Then, during the usual heating operation,
the check valves 114 and 115 are disposed for bypassing so that the refrigerant flowing
in from the load side unit 200 does not pass through the inter-refrigerant heat exchanger
113.
[0022] Also, the refrigerant supply on-off valve 108 is a valve which forms the flow of
the refrigerant from the compressor 101 discharge side to the suction side by being
opened so that the refrigerant flows from a refrigerant charging port which becomes
a supply port through which the refrigerant is charged from the outside (refrigerant
cylinder or the like) to the compressor 101 suction side. The refrigerant charging
port on-off valve 109 is a valve which supplies the refrigerant through the refrigerant
charging port for refrigerant charging.
[0023] The heat source side control device 120 is formed of a microcomputer and the like,
for example. The heat source side control device is capable of performing wired or
wireless communication with a load side control device 204 and executes operation
control of the entire refrigeration air-conditioning apparatus by controlling each
means related to the refrigeration air-conditioning apparatus such as operation frequency
control of the compressor 101 by inverter circuit control and the like on the basis
of data related to detection performed by various detecting means (sensors) in the
refrigeration air-conditioning apparatus, for example.
[0024] A discharge temperature sensor 130 and a discharge pressure sensor 131 are temperature
detecting means that detect the temperature and pressure of the refrigerant discharged
by the compressor 101. A heat source side heat exchange temperature sensor 132 is
temperature detecting means that detects the temperature of the refrigerant related
to condensation particularly when the heat source side heat exchanger 104 functions
as a condenser in this embodiment.
[0025] On the other hand, the load side unit 200 is formed of a load side heat exchanger
201, a load side expansion device (expansion valve) 202, a load side fan 203, and
the load side control device 204. The load side heat exchanger 201 exchanges heat
between the refrigerant and the air. For example, the load side heat exchanger functions
as a condenser during the heating operation, exchanges heat between the refrigerant
flowing in from the gas pipeline 300 and the air, condenses and liquefies the refrigerant
(or makes it into the gas-liquid two-phase state) and allows the refrigerant to flow
out to the liquid pipeline 400 side. On the other hand, during the cooling operation,
the load side heat exchanger functions as an evaporator, exchanges heat between the
refrigerant having been turned into a low-pressure state by the load side expansion
device 202 and the air, makes the refrigerant take heat away from the air so as to
evaporate and gasify the refrigerant, and allows the refrigerant to flow out to the
gas pipeline 300 side. Also, in the load side unit 200, the load side fan 203 which
adjusts the flow of the air used for heat exchange is disposed. The operation speed
of this load side fan 203 is determined by setting performed by a user, for example.
The load side expansion device 202 is disposed so as to adjust the flow rate of the
refrigerant so as to adjust the pressure of the refrigerant in the load side heat
exchanger 201 by changing the opening degree.
[0026] The load side control device 210 is also formed of a microcomputer and the like and
is capable of performing wired or wireless communication with the heat source side
control device 120, for example. The load side control device controls each device
(means) of the load side unit 200 so that the inside of the room has a predetermined
temperature, for example, on the basis of an instruction from the heat source side
control device 120, an instruction from a resident and the like. Also, the load side
control device transmits a signal containing data related to detection performed by
the detecting means disposed in the load side unit 200. The load side heat exchange
temperature sensor 220 is temperature detecting means that detects the temperature
of the refrigerant related to condensation when the load side heat exchanger 201 functions
as a condenser particularly in this embodiment.
[0027] In this embodiment, the oil tank 110 is disposed (in series) in the refrigerant cycle.
Particularly, the oil tank is disposed between the compressor 101 and the four-way
valve 103 so that the oil tank functions as a muffler which reduces pulsation of the
refrigerant discharged from the compressor 101 or the like due to the discharge characteristics
such as cyclic motion and the like caused by reciprocal motion and rotation in the
compressor 101. Hitherto, the pulsation of the refrigerant has been reduced or the
like by expanding a part of the refrigerant pipeline in the refrigerant cycle or by
disposing a special device or the like, but in this embodiment, the oil tank 110 which
has a space inside after the recovery operation is used.
[0028] Here, if the internal capacity of the oil tank 110 is too small, for example, the
frequency band which can be reduced is narrowed or the like, and the oil tank can
no longer function as a muffler. Thus, in this embodiment, in order to widen the frequency
band that can be reduced or the like, the oil tank 110 is configured so as to have
an internal capacity of 2 liters or more.
[0029] Also, in the oil tank 110, the refrigerator oil has been already sealed before the
recovery operation is started, that is, before shipment, for example. In this embodiment,
since the gas refrigerant passes through the oil tank 110, if the distance between
the refrigerant outlet and the oil level is close to each other, for example, the
oil level becomes wavy due to the flow of the inflow refrigerant or the like, and
the refrigerator oil can flow out in a large amount with the refrigerant through the
refrigerant outlet. Also, with regard to the refrigerant inlet, if the distance from
the oil level of the refrigerator oil is small, the gas refrigerant can make the oil
level wavy, for example.
[0030] Thus, in this embodiment, the internal capacity of the oil tank 110 is made sufficiently
larger than the required charged amount of the refrigerator oil. Also, the oil tank
110 is formed so as to have a cylindrical shape, and the refrigerant is made to flow
in so as to follow the tangental direction of the cylindrical shape. As a result,
an advantage of preventing the liquid level from becoming wavy, which is caused by
the inflow of the refrigerant, can be obtained. Then, in the initial state (when the
recovery operation is started), too, in order to ensure that there is sufficient distance
(space) between the oil level of the refrigerator oil and the refrigerant inflow pipe
port 110A as well as the refrigerant outflow pipe port 110B in the oil tank 110, the
refrigerant inflow pipe and the refrigerant outflow pipe are disposed at positions
on the upper face of the oil tank 110. Here, the distance is preferably three times
or more as large as the diameters of the refrigerant inflow pipe port 110A and the
refrigerant outflow pipe port 110B, respectively, for example. Moreover, the diameter
of the oil tank 110 having a cylindrical shape is preferably eight times or more as
large as the diameters of the refrigerant inflow pipe port 110A and the refrigerant
outflow pipe port 110B. As a result, even if the oil level is somewhat made wavy and
an oil droplets are generated, they precipitate under the gravity (its own weight),
and outflow of the refrigerator oil can be prevented.
[0031] Then, in the refrigeration air-conditioning apparatus of this embodiment, by disposing
the oil tank 110 between the compressor 101 and the four-way valve 103, heating and
cooling can both be performed in the load side unit 200 even during the recovery operation.
[0032] Also, in this embodiment, two spaces are formed in one housing, and one of them is
used as the oil tank 110, and the other as the recovery unit 111 so that heat in the
oil tank 110 is transmitted to the recovery unit 111. The recovery unit 111 is basically
disposed in parallel with a refrigerant pipeline through which the refrigerant having
passed through the gas pipeline 300 and the liquid pipeline 400 passes. Thus, if the
temperature of the refrigerant is low and the outside air temperature is also low,
stagnation of the refrigerant might occur. Thus, as described above, a configuration
is adopted such that the high-temperature refrigerant from the compressor 101 passes
through the oil tank 110 and the heat is transmitted to the recovery unit 111 in the
same housing so as to warm the recovery unit 111, and the stagnation of the refrigerant
can be prevented. As a result, the operation can be performed with the refrigerant
in an appropriate state all the time. Also, by judging the refrigerant amount with
accuracy, excess supply of the refrigerant is avoided, and thus, excess refrigerant
which collects in the accumulator 106, for example, is reduced, the risk of liquid
returning to the compressor 101 is lowered, and a system with high reliability can
be obtained.
[0033] Here, the relationship between the oil separator 102 and the oil tank 110 will be
described. The oil separator 102 and the oil tank 110 both feed the refrigerator oil
into the compressor 101. Since the oil tank 110 is used for the recovery operation,
the oil separator and the oil tank are configured to feed the refrigerator oil into
the compressor 101 by pipelines that are independent of each other.
[0034] In this embodiment, the oil pipeline 116 is connected between the oil separator 102
and the oil tank 110 so that the refrigerator oil separated by the separator 102 from
the refrigerant is fed to the oil tank 110. Thus, not only during the recovery operation
but also during the usual operation, the refrigerator oil is supplied to the compressor
101 from the oil tank 110 through the capillary tube 112. Thus, the quantity of pipelines
can be reduced and the pipelines can be simplified. Also, the refrigerator oil can
be temporarily stored in the oil tank 110. The oil separator 102 may be omitted, and
the refrigerator oil may be separated and stored only in the oil tank 110. In this
case, drop of the separation efficiency of the refrigerator oil is a concern, but
by measuring the amount of the refrigerator oil which would worsen the separation
efficiency and be circulated (taken out) through the refrigerant cycle and by charging
a large amount of the refrigerator oil in advance, reliability can be ensured.
[0035] FIG. 2 is a diagram illustrating a procedure related to the replacement including
the recovery operation. First, updating of the refrigeration air-conditioning apparatus
is started (STEP 1). The existing heat source side unit 100 and the like are removed
(STEP 2). A new unit is installed (STEP 3). The gas pipeline 300 and the liquid pipeline
400 are connected to the new unit (STEP 4). After the liquid pipeline 400, the gas
pipeline 300, and the load side unit 200 are vacuumed, the refrigerant for the load
side unit 200 is charged (STEP 5). Then, the on-off valve (not shown) located between
the heat source side unit 100 and the liquid pipeline 400 as well as the gas pipeline
300 are opened, and the recovery operation is performed (STEP 6). The recovery on-off
valve 118 is closed and a trial operation of the cooling/heating operation is performed
(STEP 7) and then, the updating is completed (STEP 8).
[0036] Subsequently, the recovery operation performed at STEP 6 will be described. First,
operation control when the recovery operation is performed while cooling operation
is performed in the load side unit 200 will be described on the basis of the flow
of the refrigerant. The operation control related to the recovery operation is assumed
to be executed by the heat source side control device 120.
[0037] A high-temperature and high-pressure gas refrigerant discharged from the compressor
101 reaches the heat source side heat exchanger 104 through the oil separator 102,
the oil tank 110, and the four-way valve 103 and is condensed and liquefied therein.
The condensed and liquefied liquid refrigerant is cooled by the inter-refrigerant
heat exchanger 113 and flows into the liquid pipeline 400 through the check valve
114 as a supercooled refrigerant.
[0038] The gas-liquid two-phase refrigerant having flowed into the liquid pipeline 400 flows
into the load side unit 200 while taking away the foreign substances and the like
in the liquid pipeline 400 through the flow of the refrigerant. The refrigerant containing
the foreign substances and the like having flowed into the load side unit 200 is expanded
by the load side expansion device 202 to a low pressure, takes heat away from the
periphery in the load side heat exchanger 201, a part of the liquid refrigerant is
evaporated so as to cool an air-conditioning space, and becomes the gas-liquid two-phase
refrigerant and flows out of the load side unit 200 and flows into the gas pipeline
300.
[0039] The gas-liquid two-phase refrigerant having flowed into the gas pipeline 300 flows
into the heat source side unit 100 while taking away foreign substances and the like
in the gas pipeline 300. The gas-liquid two-phase refrigerant containing the foreign
substances and the like having returned to the heat source side unit 100 is, as described
above, fully gasified through heat exchange with the condensed and liquefied liquid
refrigerant. Then, the refrigerant is sucked into the compressor 101 through the four-way
valve 103 and the accumulator 106 and, as described above, compressed and discharged
so as to be circulated.
[0040] Here, the foreign substances and the like are separated from the refrigerant by gravity
or the like in the accumulator 106 and precipitate on the bottom part of the accumulator
106. If the recovery on-off valve 118 is opened, while a part of a dynamic pressure
in the refrigerant changes to a static pressure inside the accumulator 106, the pressure
in the recovery unit 111 becomes lower than the pressure of the accumulator 106, and
thus, the flow of the foreign substances and the like from the accumulator 106 to
the recovery unit 111 is generated in accordance with the differential pressure. As
a result, the foreign substances and the like separated in the accumulator 106 pass
through the recovery pipeline 117 through the recovery on-off valve 118 and flow into
the recovery unit 111 so as to be recovered.
[0041] At this time, with regard to the refrigerator oil, the oil separator 102 makes the
separated refrigerator oil pass through the oil pipeline 116 and feeds it to the oil
tank 110. Also, from the oil tank 110, the refrigerator oil for replenishment is fed
to the compressor 101 through the capillary tube 112.
[0042] After the operation described above has been allowed to continue for a predetermined
time, the heat source side control device 120 controls each device so that the refrigerant
flowing through the liquid pipeline 400 becomes a liquid refrigerant. Also, the heat
source side control device executes control so that the refrigerant flowing through
the gas pipeline 300 becomes a gas refrigerant. As described above, refrigerant-amount
adjustment control is executed such that the refrigerant distribution state becomes
the same as that in the usual operation related to cooling.
[0043] Fig. 3 is a flowchart illustrating processing related to charging of the refrigerant
into the refrigerant cycle during the recovery operation. The control related to this
processing is assumed to be also executed by the heat source side control device 120.
The recovery operation corresponding to the above-described STEP 6 is started (STEP
11). Particularly in the initial state of the recovery operation, only the refrigerant
having been charged into the heat source side unit 100 in advance and the refrigerant
for the load side unit 200 charged after the vacuuming are charged in the refrigerant
cycle, and the amount of refrigerant is not sufficient. Thus, it is judged whether
a value Td of the temperature of the refrigerant discharged by the compressor 101
detected by the discharge temperature sensor 130 is larger than an upper limit value
Tdmax of the discharge temperature set in advance (Td > Tdmax) or not (STEP 12).
[0044] If it is judged to be Td > Tdmax, the refrigerant supply on-off valve 108 and the
refrigerant charging port on-off valve 109 are opened, and the refrigerant is charged
(STEP 14). On the other hand, if it is judged not to be Td > Tdmax, the refrigerant
supply on-off valve 108 and the refrigerant charging port on-off valve 109 are closed
(STEP 13). Then, the above processing (STEP 15) is performed until a predetermined
time related to the recovery of the foreign substances and the like has elapsed. Here,
with regard to the judgment at STEP 12, since the refrigerant stagnation does not
occur in the recovery unit 111 in this embodiment, decrease of the refrigerant amount
circulating through the refrigerant cycle can be prevented, and wasteful refrigerant
charging can be prevented.
[0045] If the predetermined time has elapsed, the heat source side control device 120 starts
the above-described refrigerant-amount adjustment control (STEP 16). The heat source
side control device 120 waits for the processing until it is judged that the determined
time has elapsed again (STEP 17).
[0046] Then, a saturated temperature Tsat (Pd) is calculated on the basis of the discharge
pressure Pd of the refrigerant detected by the discharge pressure sensor 131 (STEP
18). Then, a difference SC from the temperature Tcout of the refrigerant flowing out
of the heat source side heat exchanger 104 detected by the heat source side heat exchange
temperature sensor 132 is calculated (STEP 19). Moreover, the difference SC and a
target value SCm are compared and if it is judged to be SC≥ SCm (STEP 20), the refrigerant
supply on-off valve 108 and the refrigerant charging port on-off valve 109 are closed
(STEP 21), and the recovery operation is finished (STEP 23). When it is judged not
to be SC ≥ SCm (SC < SCm), the refrigerant supply on-off valve 108 and the refrigerant
charging port on-off valve 109 are opened (STEP 22), the refrigerant is charged for
a determined time (STEP 16), and the processing at STEP 17 and after is performed
again. If the condition of the refrigerant charging completion is not satisfied for
a predetermined time or more, the fact may be displayed on display means (not shown)
provided in the heat source side unit 100, a remote controller (not shown) or the
like. Also, completion of the refrigerant charging may also be informed from the heat
source side unit 100, a remote controller (not shown) or the like. Moreover, the fact
of the completion of the refrigerant charging may be stored in storage means (not
shown) of the heat source side control device 120 so that it can be checked later.
At this time, it may be stored with the operation state.
[0047] Subsequently, the operation control when the recovery operation is performed while
heating is performed in the load side unit 200 will be described on the basis of the
flow of the refrigerant. The high-temperature and high-pressure gas refrigerant discharged
from the compressor 101 becomes a gas-liquid two-phase refrigerant through the oil
separator 102, the oil tank 110, the four-way valve 103, and the inter-refrigerant
heat exchanger 113, while the refrigerant having flowed into the gas pipeline 300
flows into the load side unit 200 while taking away foreign substances in the gas
pipeline 300 by the flow of the refrigerant.
[0048] The refrigerant containing the foreign substances having flowed into the load side
unit 200 transfers heat to the periphery in the load side heat exchanger 201, condenses
and heats the air-conditioning space and is expanded to an intermediate pressure in
the load side expansion device 202, becomes the gas-liquid two-phase refrigerant containing
the foreign substances and the like, flows out of the load side unit 200 and flows
through the liquid pipeline 400. The gas-liquid two-phase refrigerant having flowed
into the liquid pipeline 400 flows into the heat source side unit 100 while taking
away also the foreign substances and the like in the liquid pipeline 400.
[0049] The gas-liquid two-phase refrigerant containing the foreign substances and the like
having returned to the heat source side unit 100 partially flows into the heat source
side heat exchanger 104 through the check valve 115, while the remaining part flows
through the inter-refrigerant heat exchanger 113 and the on-off valve 134 and flows
to the refrigerant inflow side (upstream side) of the accumulator 106. The refrigerant
having been evaporated and gasified in the heat source side heat exchanger 104 is
sucked into the compressor 101 through the four-way valve 103 and the accumulator
106 and is compressed and discharged as described above and is circulated. The gas-liquid
two-phase refrigerant having flowed into the inter-refrigerant heat exchanger 113
exchanges heat with the high-temperature and high-pressure gas refrigerant discharged
by the compressor 101 and is evaporated, and flows to the refrigerant inflow side
of the accumulator 106 through the on-off valve 134. After the above operation is
performed for a predetermined time, the refrigerant-amount adjustment control is executed
so that the refrigerant distribution state becomes the same as that in the usual operation
related to heating.
[0050] At this time, as described above, the foreign substances and the like separated in
the accumulator 106 pass through the recovery pipeline 117 via the recovery on-off
valve 118 and flow to the recovery unit 111 and are recovered therein. Also, the refrigerator
oil to compensate for the shortage is also fed from the oil tank 110 to the compressor
101.
[0051] Also, the processing related to charging of the refrigerant while heating is performed
in the load side unit 200 is basically the same as the processing described on the
basis of Fig. 3. However, with regard to the temperature Tcout, the temperature of
the refrigerant flowing out of the load side heat exchanger 201 detected by the load
side heat exchange temperature sensor 220 is assumed to be the temperature Tcout.
When a plurality of the load side units 200 are installed, an average value of the
temperatures detected by the load side heat exchange temperature sensor 220 is the
temperature Tcout.
[0052] As described above, when a new unit is installed for updating by using an existing
pipeline, even if the shape of the existing pipeline is embedded in the wall or ceiling,
the correct refrigerant amount can be judged and the refrigerant can be charged and
thus, time for construction can be reduced. Also, since the refrigerant amount can
be judged whether it is cooling or heating, reliability on the refrigerant amount
can be improved whether the pipeline is existing or not.
[0053] As described above, according to the refrigeration air-conditioning apparatus of
Embodiment 1, during the recovery operation, the oil tank 110 that collects the refrigerator
oil to be replenished into the compressor 101 is disposed in series in the refrigerant
cycle and the gas refrigerant discharged by the compressor 101 is made to pass therethrough,
and thus, the oil tank can be used as a muffler that stirs the refrigerant in the
space inside the oil tank 110 and reduces the pulsation of the refrigerant generated
by the discharge characteristics of the compressor 101. As a result, the pulsation
of the refrigerant is not transmitted to the other devices in the heat source side
unit 100, the load side unit 200 and the like, and thus, vibration, noise and the
like generated in the apparatus (pipelines and devices) by the pulsation of the refrigerant
can be reduced, and an apparatus in which breakage can be prevented and reliability
is improved by prolongation of the life can be obtained. Also, by using the oil tank
110 as a muffler, the oil tank 110 having a large space can be effectively used, and
by omitting the muffler, reduction of the capacity of the heat source side until 100,
size reduction, cost reduction through reduction of materials can be realized. Also,
since the pipelines can be simplified, productivity can be improved.
[0054] Also, since the oil tank 110 is disposed at a position where the gas refrigerant
discharged by the compressor 101 passes regardless of the operation state, even if
the load side unit 200 is performing cooling or heating during the recovery operation,
the pulsation of the refrigerant can be reduced. Moreover, by setting the size of
the oil tank at a predetermined size (2 liters, for example) or larger, the pulsation
of the refrigerant can be reduced in accordance with a wide frequency range and wavelength
related to the pulsation. Even if the refrigerant inflow pipe and the refrigerant
outflow pipe are disposed at positions on the upper face of the oil tank 110, and
the oil level of the refrigerator oil collecting in the oil tank 110 is at the highest
position (usually a stage before the recovery operation is started), since the sufficient
distance (space) is ensured between the refrigerant inflow pipe port 110A as well
as the refrigerant outflow pipe port 110B and the oil level, excessive fluctuation
of the oil level position and outflow from the refrigerant outflow pipe port 110B
can be prevented. Thus, shortage of the refrigerator oil in the compressor 101 can
be prevented, and a refrigeration air-conditioning apparatus with high reliability
can be obtained. Also, since the capacity of the inside of the oil tank 110 is increased
in order to ensure the space, the effect of reducing the refrigerant pulsation can
be further improved.
[0055] Also, by transmitting the heat of the gas refrigerant passing through the oil tank
110 during the recovery operation or the usual air-conditioning operation to the recovery
unit 111 and by heating the recovery unit 111, the stagnation of the refrigerant in
the recovery unit 111 can be prevented. Therefore, judgment on shortage of the refrigerant
amount in the refrigerant cycle can be made with high accuracy, and charging of an
inadvertently large amount of refrigerant can be prevented. Thus, cost reduction and
environmental preservation can be realized.
[0056] Also, since the refrigerator oil separated by the oil separator 102 is returned to
the compressor 101 through the oil tank 110, the pipeline path related to oil can
be unified into one system, and the pipelines can be simplified. Thus, cost reduction
and productivity improvement can be realized.
Embodiment 2.
[0057] In the above-described embodiment, the two spaces obtained by partitioning the inside
of one housing with a mirror plate are used as the oil tank 110 and the recovery unit
111, but this is not limiting as long as the heat of the oil tank 110 can be transmitted
to the recovery unit 111. For example, the two tanks, that is, the oil tank 110 and
the recovery unit 111 may be brought into contact with each other and combined.
Embodiment 3.
[0058] In Embodiment 1, the refrigeration air-conditioning apparatus in which the heat source
side unit 100 and the load side unit 200 are connected one each was described. The
present invention is not limited by that but can be applied to a multiple refrigeration
air-conditioning apparatus in which a plurality of the heat source side units 100
and the load side units 200 are connected, respectively. At this time, the number
of the heat source side units 100 having a recovering function may be one or the total
of the units.
[0059] Also, in the above-described embodiments, the four-way valve 103 is disposed so that
the load side unit 200 can perform cooling/heating, but the configuration without
the four-way valve 103 is possible. In such a case, the oil tank 110 is disposed between
the oil separator 102 (compressor 101) and the heat source side heat exchanger 104.
[0060] Also, in the above-described embodiments, the description was made that the load
side unit 200 is also replaced, but the present invention can be also applied to a
case in which only the heat source side unit 100 is replaced by a new one.
[0061] Moreover, in the above-described embodiments, the recovery operation is performed
by the refrigerant cycle in which the load side unit 200 is connected by pipeline,
but it may be configured such that after the gas pipeline 300 is connected to the
liquid pipeline 400 by a bypass pipeline and the recovery operation is performed,
the load side unit 200 may be connected by a pipeline, for example.
Industrial Applicability
[0062] In the above-described embodiments, application to a refrigeration air-conditioning
apparatus was described, but the present invention can be also applied to other refrigeration
cycle apparatuses forming a refrigerant cycle such as a heat pump apparatus, a freezing
apparatus, cold storage apparatus and the like. Reference Signs List
[0063] 100 heat source side unit, 101 compressor, 102 oil separator, 103 four-way valve,
104 heat source side heat exchanger, 105 heat source side fan, 106 accumulator, 107
heat source side expansion device, 108 refrigerant supply on-off valve, 109 refrigerant
charging port on-off valve, 110 oil tank, 110A refrigerant inflow pipe port, 110B
refrigerant outflow pipe port, 111 recovery unit, 112 capillary tube, 113 inter-refrigerant
heat exchanger, 114, 115 check valve, 116 oil pipeline, 117 recovery pipeline, 118
recovery on-off valve, 120 heat source side control device, 130 discharge temperature
sensor, 131 discharge pressure sensor, 132 heat source side heat exchange temperature
sensor, 200 load side unit, 201 load side heat exchanger, 202 load side expansion
device, 203 load side fan, 210 load side control device, 220 load side heat exchange
temperature sensor, 300 gas pipeline, 400 liquid pipeline.