Field of the Invention
[0001] The present invention relates to the field of electric power thermal automation,
and particularly to a control method for alternately opening the bypass valves of
a steam turbine.
Background of the invention
[0002] With continuous improvement in the parameters of steam turbogenerator units, steam
oxidation of metal as well as retention of fallen oxide skins in the boiler pipes
is increasingly threatening the safe operation of the units. The retention and accumulation
of oxide skins may easily happen in the boiler header. As shown in Figure 1, the main
reason for the accumulation of oxide skins lies in the fact that: after the inlets
of coiled pipes 1 distributed throughout the header have gathered steam 3 into a header
2, the gathered steam 3 is in turn discharged from steam pipes A and B that are connected
with both sides of the header 2. The steam flow rate varies from place to place in
the header when the steam is passing therethrough. The steam flow rate is maximum
on both sides of
A/B, and at the O-point in the header, the steam flow rate approximately approaches
zero, forming a position of the lowest flow rate where the steam flow rate is the
lowest, the impulse is minimum, and it is easy for foreign matters such as oxide skins
to accumulate.
[0003] With the same principle, as in other implementations, if the O-point of the header
is the steam outlet connected with the steam pipe, the steam flow rate at the corresponding
point A or point B of the header approximately approaches zero, forming a region of
the lowest flow rate (not shown).
[0004] The foreign matters (such as oxide skins) discharged from the coil pipe will stay
in the region of low flow rate after entering the header. The foreign matters which
have entered the header will gradually deposit and accumulate in the region of smaller
steam impulse. Only under special operating conditions, for example, when the main
steam door is unilaterally closed, these foreign matters can be blown out of the header.
Large quantities of granular foreign matters such as oxide skins deposited in the
region of low flow rate will endanger the safety of the pipelines connected with this
region as well as the safety of the whole unit.
[0005] Therefore, it is necessary to develop a technology to reach the goal of removing
the foreign matters such as oxide skins in the header, reducing the erosion rate of
solid particles in the turbine and thus improving the safety of the unit.
[0006] A method using water to discharge sludge in a lower branch pipe at a lower portion
of a steam boiler and difficult to be discharged with only a total blow is known from
JP 2002115805A. However, this method is unrelated to the goal of removing the foreign matters such
as oxide skins in a header.
Summary of the Invention
[0007] In view of aforesaid deficiency in the prior art, an issue to be addressed by the
present invention is to provide a low-cost but high-efficient control method so as
to reach the goal of reducing the foreign matters such as oxide skins in the header,
reducing the erosion rate of solid particles in the turbine and thus improving safety
of the unit.
[0008] To achieve the aforesaid object, the present invention provides a bypass control
method, comprising the following steps:
Step 1: during the starting period of the generating unit provided with a bypass system,
said boiler is firstly started in a conventional mode by means of said bypass system,
and its steam parameters have basically met the conditions for impulse starting the
turbine; said bypass system comprises a first-side bypass valve group and a second-side
bypass valve group that are respectively set on the main steam pipe and the reheat
steam pipe which are connected with both sides of said outlet header of the superheater
or reheater of the boiler:
Step 2: closing said second-side bypass valve group and at the same time forcing said
first bypass valve group to a wide open position, so that said steam that passes through
said header is unilaterally discharged only from said first-side bypass valve group
in the open state;
Step 3: after maintaining said first-side bypass valve group in the open state for
a required time period, closing said first-side bypass valve group and at the same
time opening said second-side bypass valve group, so that said steam that passes through
said header is discharged only from said second-side bypass valve group in the open
state via the other side;
Step 4: after maintaining said second-side bypass valve group in the turning-up state
for a required time period, restoring the conventional control state of said bypass
system and being prepared to impulse start the turbine.
[0009] Preferably□in said step 1, said boiler shall have completed the starting and be prepared
to impulse start the turbine.
[0010] Preferably, after said step 3, said steps 2 and 3 can be repeated, until it is sure
that the foreign matters in said header are removed and that the quality of said steam
reaches an acceptance value.
[0011] Preferably, said first-side bypass valve group and/or said second-side bypass valve
group are alternately opened /closed in a program-controlled mode.
[0012] Preferably□after said step 4, the conventional control mode of said bypass system
can be immediately restored and it is prepared to impulse start the turbine.
[0013] Preferably, said bypass system is a high-pressure bypass or a low-pressure bypass.
The control strategy of this method is also applicable to a low pressure bypass to
reduce the accumulation of foreign matters (such as oxide skins) in the outlet header
of the reheater.
[0014] Preferably, said first-side bypass valve group and said second-side bypass valve
group respectively comprise at least one bypass valve.
[0015] Preferably, the greater the capacity of said bypass valve group is, the better the
sweeping effect on the header is.
[0016] The bypass control method provided by the present invention realizes alternate changing
of the steam flow direction in the header by controlling the alternate opening of
the two sides of the bypass valves, without need of adding any hardware facility or
extra expenditure. Due to the alternate changing of the steam flow direction in the
header, the region of the lowest flow rate in the header is alternately shifted along
with the alternate changing of the steam flow direction, so that there is no fixed
position of the lowest flow rate in the header, i.e., no existence of dead point of
flow rate, and all regions in the header are swept in an all-side way, so as to reach
the goal of removing such foreign matters as oxide skin in the header, reducing the
erosion rate of solid particles in the turbine and thus improving safety of the unit.
[0017] The concept, the specific configuration and the resulted technical effects of the
present invention will be further described hereinafter in conjunction with the attached
drawings, in order to adequately understand the objects, features and effects of the
present invention.
Brief Description of the Drawings
[0018]
Figure 1 is a schematic diagram of the steam flow directions in a unit header according
to the conventional bypass control method of prior art.
Figure 2 is a schematic diagram of the arrangement of the unit provided with a bypass
system.
Figure 3 is a schematic diagram of the stream flow rate in the header at a stage of
alternately opening of the unit according to the bypass control method of the present
invention.
Figure 4 is a flow chart of the control method according to the present invention.
Detailed Description of the Preferred Embodiments
[0019] Figure 2 is a schematic diagram showing the arrangement of a one-reheating unit provided
with a bypass system. At least two main machines are provided in the thermoelectric
generating unit: a turbine 10 and a boiler 1, and the bypass system is the main component
to adjust and coordinate the two main machines. In the operating process of the unit,
the steam transmitted from the boiler 1 passes through a superheater 2 and enters
a superheater outlet header 5, then, after passing through a main steam pipe 11, the
steam enters an HP cylinder of the turbine 10 via a main intake door and an adjusting
door (not shown) of the turbine to do work, and the discharged steam enters a reheater
3 in the boiler after passing a cold section 4 of the reheater. The high-pressure
bypass is located between the outlet header 5 of the boiler and the cold section 4
of the reheater, and the low-pressure bypass is located between the outlet header
of the reheater and the condenser (not shown), and the embodiment described herein
is also applicable to a low pressure bypass. The bypass system to which the present
invention is applied comprises a first-side bypass valve group and a second-side bypass
valve group or a low-pressure bypass (not shown) that are respectively provided on
the main steam pipe and the reheat steam pipe, which are connected with both sides
of the outlet header of the superheater or reheater of the boiler. In this embodiment,
the first-side bypass valve group comprises bypass valves 6 and 7, and the second-side
bypass group comprises bypass valves 8 and 9.
[0020] Under normal operating conditions, the steam enters the HP cylinder of the turbine
10 via a main steam pipe 11 for doing work. However, under abnormal operating conditions
such as in the starting stage, an embodiment of the bypass control method according
to present invention comprises the following steps (the control method for a low pressure
bypass is the same):
Step 1: at the starting stage of the unit provided with a bypass system, the steam
transmitted from the superheater 2 of the boiler 1 passes through the bypass system
via an outlet header 5, and then enters the reheater of the boiler via the cold section
4. The bypass system comprises bypass valves 6 and 7 of the first-side bypass valve
group and bypass valves 8 and 9 of the second-side bypass valve group that are respectively
provided on the main steam pipe and the reheat steam pipe, which are connected with
both sides of the outlet header of the superheater 2 or the reheater 3 of boiler 1.
Step 2: at the starting stage, when the steam parameter has basically met the conditions
for impulse starting the turbine (by this time, both bypass valve groups shall be
in the open state), firstly closing the bypass valves 8 and 9 mounted on the outlet
pipeline on one side of the outlet header 5, and at the same time turning up the bypass
valves 6 and 7, so that the steam that has passed through the outlet header 5 is discharged
only via the bypass valves 6 and 7 in the open state. As shown in Figure 3, since
the bypass valves 6 and 7 are opened while the bypass valves 8 and 9 remain in the
closed state, the steam in the outlet header 5 is discharged from the pipeline on
the same side with the bypass valves 6 and 7 via Point A, and by this time, Point
B is a point of zero flow rate, and such foreign matters as oxide skins that are deposited
in the regions, excluding the neighboring regions of Point B, are blown out of the
outlet header 5 along with the steam, and the farther the distance from Point B is,
the greater the scouring momentum of the steam is.
Step 3: maintaining the bypass valves 6 and 7 in a wide open state, after the steam
pressure in the pipeline has become stable and remains the same for a required time
period, closing the bypass valves 6 and 7 and at the same time starting the bypass
valves 8 and 9, so that the steam that passes through the outlet header 5 is discharged
from the bypass valves 8 and 9 on the other side; since the bypass valves 8 and 9
are open, the steam that has passed through the outlet header 5 is discharged from
the pipeline located on the same side with bypass valves 8 and 9 via Point B, and
by this time, Point A is a point of zero flow rate, and such foreign matters as oxide
skins that are deposited in the regions, excluding the neighboring regions of Point
A, are blown out of the outlet header 5 along with the steam, and the farther the
distance from Point A is, the greater the scouring momentum of the steam is.
Step 4: maintaining the bypass valves 8 and 9 in the wide open state, after the steam
pressure in the pipeline has become stable and remains the same for a required time
period, restoring the conventional control state of the bypass system and being prepared
to impulse start the turbine.
[0021] The steps described above are shown in Figure 4.
[0022] According to the bypass control method of the present invention, the alternate changing
of the steam flow direction in the header is changed by controlling the alternate
opening of the two sides of the bypass valves, without need of adding any hardware
facility or extra expenditure. Due to the alternate changing of the steam flow direction
in the header, the region of the lowest flow rate in the header alternately changes
in position along with the alternate changing of the steam flow direction, so that
there is no fixed position of the lowest flow rate in the header, i.e., there is no
dead point of the flow rate, and all regions in the header are swept in an all-side
way, so as to reach the goal of removing foreign matters such as oxide skins in the
header, reducing the erosion rate of the solid particles in the turbine and thus improving
the safety of the unit.
[0023] The method of the present invention is not limited to aforesaid embodiment.
[0024] Preferably, in other embodiments of the present invention, a full program-controlled
mode can be adopted and all the control systems of the present invention can be included
in the unit starting program control, so as to automatically shift and realize the
operations of opening/closing the first-side bypass valve group and/or the second-side
bypass valve group, without the need of manual participation or intervention. Meanwhile,
this control method can be designed into the starting mode of the bypass itself, without
affecting starting time and operation safety of the unit.
[0025] Further, the control method of the present invention is not limited to a single opening/closing
alternate operation in said embodiment. According to actual requirements, after said
step 3, the process of repeating the step 2 and step 3 can be added for one or many
times, i.e., it includes unilaterally alternate opening/closing operations for many
times, until it is for sure that the foreign matters in said header have been removed
and that the quality of said steam reaches the acceptance value.
[0026] After the step 4, when the unit has completed the starting process, the conventional
control state of the bypass system is to be restored and it is prepared to impulse
start the turbine.
[0027] Said first-side bypass valve group and the second-side bypass valve group in the
present invention have no limitation on the quantity of the valves. In aforesaid embodiments,
the first-side bypass valve group and the second-side bypass valve group respectively
comprise two bypass valves in each group. In other embodiments of the present invention,
each bypass group may also comprise either one bypass valve or a plurality of bypass
valves, and the selection of the quantity of the bypass valves mainly depends on the
steam flow rate and the bypass capacity.
[0028] The method of the present invention can also be used in combination with other control
methods for bypass systems.
[0029] In summary, only several preferred embodiments of the present invention have been
described.
1. A bypass control method for a generating unit, comprising the following steps:
step 1: during the starting period of a generating unit provided with a bypass system,
a boiler (1) being firstly started by means of said bypass system in normal mode;
wherein said bypass system comprises a first-side bypass valve group and a second-side
bypass valve group that are respectively provided on the main steam pipe and/or the
reheat steam pipe, which are connected with both sides of an outlet header (5) of
a super heater (12) and/or reheater (3) of said boiler (1);
step 2: closing said second-side by-pass valve group and at the same time forcing
said first bypass valve group to a wide open position, so that said steam that passes
through said header (5) is unilaterally discharged only from said first-side bypass
valve group in an open state;
step 3: after maintaining said first-side bypass valve group in an open state for
a required time period, closing said first-side bypass valve group and at the same
time opening said second-side bypass valve group, so that said steam that passes through
said header (5) is discharged only from said second-side bypass valve group in the
open state;
step 4: after maintaining said second-side bypass valve group in a starting state
for a required time period, restoring a normal control state of said bypass system
and being prepared to impulse start a turbine.
2. The bypass control method of Claim 1, wherein in said step 1 should be carried out
prior to impulse starting said turbine.
3. The bypass control method of Claim 1, wherein after said step 3, said steps 2 and
3 can be repeated, until foreign matters in said header (5) have been removed and
that a quality of said steam reaches, an acceptance value.
4. The bypass control method of Claim 1, wherein said first-side valve group and/or said
second-side bypass valve group are alternately opened/closed in a program-controlled
mode.
5. The bypass control method of Claim 1, wherein after said step 4, the normal control
mode of said bypass system can be immediately restored and it is prepared to impulse
start the turbine.
6. The bypass control method of Claim 1, wherein said bypass system is a high-pressure
bypass or a low-pressure bypass.
7. The bypass control method of Claim 1, wherein said first-side bypass valve group and
said second-side bypass valve group respectively comprise at least one bypass valve.
1. Bypass-Steuerverfahren für eine Kraftwerkseinheit, das die folgenden Schritte umfasst:
Schritt 1: während des Startzeitraums einer Kraftwerkseinheit, die mit einem Bypass-System
versehen ist, wird zuerst ein Kessel (1) mittels des Bypass-Systems in einem Normalbetrieb
gestartet; wobei das Bypass-System eine Bypass-Ventilgruppe der ersten Seite und eine
Bypass-Ventilgruppe der zweiten Seite, die jeweils bei der Hauptdampfleitung und/oder
bei der Zwischendampfleitung vorgesehen sind, die mit beiden Seiten eines Austrittssammlers
(5) eines Überhitzers (12) und/oder eines Nachbrenners (3) des Kessels (1) verbunden
sind, umfasst;
Schritt 2: Schließen der Bypass-Ventilgruppe der zweiten Seite und gleichzeitig Bringen
der ersten Bypass-Ventilgruppe in eine weit offene Position, so dass der Dampf, der
durch den Sammler (5) läuft, nur von der Bypass-Ventilgruppe der ersten Seite in einem
offenen Zustand einseitig abgeführt wird;
Schritt 3: nach dem Halten der Bypass-Ventilgruppe der ersten Seite in einem offenen
Zustand für einen erforderlichen Zeitraum, Schließen der Bypass-Ventilgruppe der ersten
Seite und gleichzeitig Öffnen der Bypass-Ventilgruppe der zweiten Seite, so dass der
Dampf, der durch den Sammler (5) läuft, nur von der Bypass-Ventilgruppe der zweiten
Seite in dem offenen Zustand abgeführt wird;
Schritt 4: nach dem Halten der Bypass-Ventilgruppe der zweiten Seite in einem Startzustand
für einen erforderlichen Zeitraum, Wiederherstellen eines Normalsteuerungszustands
des Bypass-Systems und Schaffen der Bereitschaft für einen Impulsstart einer Turbine.
2. Bypass-Steuerverfahren nach Anspruch 1, wobei Schritt 1 vor einem Impulsstart der
Turbine ausgeführt werden sollte.
3. Bypass-Steuerverfahren nach Anspruch 1, wobei nach dem Schritt 3 die Schritte 2 und
3 wiederholt werden können, bis Fremdstoffe in dem Sammler (5) entfernt worden sind
und bis eine Qualität des Dampfs einen Akzeptanzwert erreicht.
4. Bypass-Steuerverfahren nach Anspruch 1, wobei die Ventilgruppe der ersten Seite und/oder
die Bypass-Ventilgruppe der zweiten Seite in einer programmgesteuerten Betriebsart
abwechselnd geöffnet bzw. geschlossen werden.
5. Bypass-Steuerverfahren nach Anspruch 1, wobei nach Schritt 4, die Normalsteuerungsbetriebsart
des Bypass-Systems unmittelbar wiederhergestellt werden kann und für einen Impulsstart
der Turbine bereit ist.
6. Bypass-Steuerverfahren nach Anspruch 1, wobei das Bypass-System ein Hochdruck-Bypass
oder ein Niederdruck-Bypass ist.
7. Bypass-Steuerverfahren nach Anspruch 1, wobei die Bypass-Ventilgruppe der ersten Seite
und die Bypass-Ventilgruppe der zweiten Seite jeweils wenigstens ein Bypass-Ventil
umfassen.
1. Procédé de commande en dérivation pour une unité de génération, comportant les étapes
suivantes :
étape 1 : pendant la période de démarrage d'une unité de génération munie d'un système
de dérivation, une chaudière (1) est d'abord démarrée au moyen dudit système de dérivation
en mode normal ; ledit système de dérivation comportant un groupe de vannes de dérivation
de premier côté et un groupe de vannes de dérivation de deuxième côté qui sont respectivement
placés sur la conduite principale de vapeur et/ou la conduite de vapeur resurchauffée,
qui sont raccordées avec les deux côtés d'un collecteur (5) de sortie d'un surchauffeur
(12) et/ou réchauffeur (3) de ladite chaudière (1) ;
étape 2 : fermer ledit groupe de vannes de dérivation de deuxième côté et imposer
en même temps audit premier groupe de vannes de dérivation une position grande ouverte,
de telle sorte que ladite vapeur qui traverse ledit collecteur (5) soit unilatéralement
refoulée uniquement à partir dudit groupe de vannes de dérivation de premier côté
à l'état ouvert ;
étape 3 : après avoir maintenu ledit groupe de vannes de dérivation de premier côté
à l'état ouvert pendant un laps de temps requis, fermer ledit groupe de vannes de
dérivation de premier côté et ouvrir en même temps ledit groupe de vannes de dérivation
de deuxième côté,
de telle sorte que ladite vapeur qui traverse ledit collecteur (5) soit refoulée uniquement
à partir dudit groupe de vannes de dérivation de deuxième côté à l'état ouvert ;
étape 4 : après avoir maintenu ledit groupe de vannes de dérivation de deuxième côté
dans un état de démarrage pendant un laps de temps requis, rétablir un état de commande
normale dudit système de dérivation et se préparer au démarrage par impulsion d'une
turbine.
2. Procédé de commande en dérivation selon la revendication 1, ladite étape 1 devant
être réalisée préalablement au démarrage par impulsion de ladite turbine.
3. Procédé de commande en dérivation selon la revendication 1, lesdites étapes 2 et 3
pouvant être répétées, après ladite étape 3, jusqu'à ce que des corps étrangers présents
dans ledit collecteur (5) aient été éliminés et qu'une qualité de ladite vapeur atteigne
une valeur d'acceptation.
4. Procédé de commande en dérivation selon la revendication 1, ledit groupe de vannes
de premier côté et/ou ledit groupe de vannes de dérivation de deuxième côté étant
ouverts/fermés en alternance dans un mode commandé par programme.
5. Procédé de commande en dérivation selon la revendication 1, après ladite étape 4,
le mode de commande normale dudit système de dérivation pouvant être immédiatement
rétabli et les préparatifs étant effectués pour le démarrage par impulsion de la turbine.
6. Procédé de commande en dérivation selon la revendication 1, ledit système de dérivation
étant une dérivation à haute pression ou une dérivation à basse pression.
7. Procédé de commande en dérivation selon la revendication 1, ledit groupe de vannes
de dérivation de premier côté et ledit groupe de vannes de dérivation de deuxième
côté comportant respectivement au moins une vanne de dérivation.