Field of the Invention
[0001] The present invention relates to a tethering system for use with an array of modular
gravity anchors. In particular, but not exclusively, the invention relates to deployment
of an array of gravity anchors on a seabed, where the array of gravity anchors work
cohesively as a single anchor member.
Background to the Invention
[0002] An anchor is typically used to connect a vessel or underwater device, such as renewable
energy devices to the bed of a body of water, for example the seabed. Gravity or deadweight
anchors provide a holding force from the submerged weight of the anchor.
[0003] The holding force of the gravity anchor is proportional to its weight. Therefore,
if the holding force required is greater the weight of the anchor must be proportionately
greater. As the weight increases so does the dimensions of the anchor. It will be
appreciated that the ability to transport and maneuver gravity anchors will be affected
as the weight and dimensions increase. Large vessels are typically required to deploy
large/heavy gravity anchors.
[0004] Gravity anchors are historically formed from a dense material such as cast iron,
steel or lead. More recently, gravity anchors have been formed from concrete. The
holding power of the anchor is defined by its weight underwater (accounting for buoyancy),
although suction can increase this if it becomes buried. For instance, a solid concrete
anchor of dimensions 10 m by 5 m by 3.6 m would have a weight in air of 550 Tonnes
and a weight in water of 300 Tonnes. It will be appreciated that the holding force
of a concrete anchor placed underwater is considerably lower than a correspondingly
dimensioned iron, steel or lead anchor.
[0005] Large concrete anchors, formed in a conventional manner, are expensive to handle
and install because heavy works vessel are typically required to transport the anchor
to the seabed.
[0006] Concrete anchors are cheaper to manufacture than steel anchors, at less than a third
of the cost, approximately, per unit holding force.
[0007] Anchorage systems with a capacity of, for example, 700 tonnes may be provided by
single gravity anchors, subsea drilling or piling. Each of these activities involve
using expensive heavy lift vessels.
[0008] It is desirable to provide an anchor system which involves reducing the cost of deployment
and the cost of operational and maintenance (O&M) activities.
[0009] It is also desirable to provide an anchor system that does not require a heavy works
vessel to deploy the anchor system, thereby reducing the O&M costs associated with
conventional anchor systems.
[0010] It is desirable to provide improved means of installing a concrete gravity anchor
on the bed of a body of water, for example the seabed.
[0011] It is further desirable to provide an anchoring system that reduces the cost associated
with handling and/or installing a gravity anchor.
Summary of the Invention
[0012] A first aspect of the present invention provides a tethering system operable to tether
an array of modular gravity anchors to a bed of a body of water, the tethering system
comprising:
an elongate tether locatable on the bed of a body of water; and
a plurality of stop members distributable along the tether and fixedly attachable
to the tether, wherein at least one gravity anchor is connectable to each of the stop
members.
[0013] The arrangement of the elongate tether, stop members and modular gravity anchors
is such that the interaction of the stop members with a corresponding modular gravity
anchor combines the masses of each gravity anchor that are smaller and lighter than
typical gravity anchors to act as a single cohesive mass on the bed of the body of
water in which the system is deployed, for example the seabed.
[0014] For example a typical mooring system requiring two 700 tonnes (wet weight) anchors
is deployed to the sea bed using a heavy load vessel. Such large masses typically
cannot be deployed with a small multi-cat vessel, which typically has a winch capacity
of less than 100 tonnes. Accordingly, a system according to embodiments of the present
invention combines multiple smaller masses to provide a large mass on the seabed.
Therefore, the system is suitable for deployment using vessels smaller than those
conventionally used to deploy an equivalent single large mass whilst having the ability
to provide the required anchorage due to the cohesive affect provided by the tethering
system. As such a tethering system according to the embodiments described can be deployed
at less cost than conventional methods and has the added benefit of reducing the risks
associated with a single lift operation of large masses.
[0015] The tether may comprise a chain comprising a series of connected links wherein the
stop members are fixedly attached to the tether relative to one or more links of the
chain.
[0016] The stop members may comprise a surface against which the gravity anchor locates
when on the bed of a body of water. Alternatively, the stop members may comprise a
receiving member against which or upon which the gravity anchor is connectable when
it is lowered towards the stop member. In the embodiment where the gravity anchor
is connectable upon the receiving member, the receiving member may protrude from a
surface of the stop member and may be configured to be receivable in a correspondingly
shaped cavity provided at a surface of the gravity anchor.
[0017] The stop member may comprise a frame structure comprising at least two plate members
spaced apart by structural supports, wherein the structural supports act to engage
with the tether to fixedly attach the stop member to the tether. The structural supports
may comprise two rods or pins each secured to each plate and spaced sufficiently to
receive a section of the tether therebetween and to prevent relative movement of tether
and the stop member.
[0018] In an alternative embodiment the tether may comprise a series of longitudinal substantially
rigid members, each longitudinal member being connected by a hinge mechanism to an
adjacent longitudinal member, wherein each stop member is fixedly attached relative
to a longitudinal member and hinge mechanism and is configured to receive a gravity
anchor.
[0019] The stop members may comprise a receiving member upon which the gravity anchor is
receivable when it is lowered towards the stop member. The receiving member may protrude
from a surface of the stop member and may be configured to be receivable in a correspondingly
shaped cavity provided at a surface of the gravity anchor.
[0020] A second aspect of the present invention provides a mooring system comprising a tethering
system according to the first aspect and a plurality of gravity anchors, wherein at
least one gravity anchor is connectable to each stop member.
[0021] A mooring system of the second aspect provides a single cohesive system of multiple
relatively small masses to emulate a conventional large mass system, wherein applying
a load to the tether results in the tether and the stop members acting together to
transfer mooring loads to the anchors.
[0022] The at least one gravity anchor may comprise a pre-cast concrete block configured
for connection to the tethering system. Alternatively, the at least one gravity anchor
may comprise cast iron, steel or lead.
[0023] Connection of the gravity anchor to the tethering system may be by locating a gravity
anchor adjacent to a face of the stop member. Alternatively, connection of the gravity
anchor to the tethering system may be by being received upon a receiving member protruding
from each stop member.
[0024] The at least one gravity anchor may comprise a modular construction, wherein a plurality
of modular elements can be combined to form a gravity anchor connectable to each stop
member.
[0025] Each modular element may comprise a self aligning geometrical configuration comprising
complementary mating surfaces such that a plurality of modular elements are stackable
relative to the stop member.
[0026] This configuration effectively reduces the weight of each gravity anchor being located
on the bed of a body of water. Multiple modular elements can be transported to the
deployment location and each modular element can be deployed individually to the bed
of the body of water in engagement firstly with the tether and the stop member and
subsequently with a modular element already deployed.
[0027] The first modular element may comprise a void area on its underside from front to
back or side to side, wherein the void area straddles the tether when in use.
[0028] Each modular element may comprise a void area from front to back or side to side
on its underside and a correspondingly shaped raised area on its upper surface such
that in assembling the gravity anchor each modular element is aligned by engagement
of the raised area within the void area.
[0029] A further aspect of the present invention provides a method of deployment of a mooring
system according to a second aspect of the present invention comprising the steps:
locating a tethering system comprising an elongate tether and stop elements distributed
along the length of the tether on a bed of a body of water;
lowering at least one gravity anchor per stop element towards the bed of the body
of water;
locating each of the gravity anchors relative to a stop element;
pulling the tether thereby transferring the tether load to the gravity anchors via
engagement of the stop elements and the gravity anchors thereby combining masses of
each gravity anchor and providing a cohesive singular mass on the bed of the body
of water.
[0030] The step of lowering at least one gravity anchor per stop element may comprise lowering
a plurality of modular elements per stop element, firstly locating a first modular
element relative to the tether and each stop element and subsequently repeating lowering
a further modular element into engagement with a previously installed modular element
to connect a gravity anchor structure with each stop element.
Description of the Drawings
[0031] Embodiments of the present invention will now be described, by way of example only,
with reference to the accompanying drawings in which:
Figure 1 is a schematic representation of a mooring system according to an embodiment
of the present invention;
Figure 2 is a schematic representation of an assembly of an elongate chain tether
and a plurality of stop members according to an embodiment of the present invention;
Figure 3 is a schematic representation of a stop member attached to the tether as
illustrated in figure 2;
Figure 4 is a schematic representation of the stop member of Figure 3 showing engagement
of the stop member and the chain tether;
Figure 5 is a schematic representation of a tether system according to an embodiment
of the present invention; and
Figure 6 is a schematic representation of a modular gravity anchor system as used
with the tethering system of figures 2, 3 and 4.
Description of an Embodiment
[0032] Figure 1 illustrates a mooring system 10 comprising a tethering system 12 and a plurality
of gravity anchors 14 as located on the bed 16 of a body of water, for example a seabed
16.
[0033] In the illustrated example the tethering system 12 comprises a chain 18 made up of
a system of links 20 and a plurality of structural stop members 22 distributed along
the chain 18. Each structural stop member 22 is configured to engage with a link 20
of the chain 18 such that relative movement of the chain 18 and the stop member 22
is prevented (this is illustrated further in figures 3 and 4). The arrangement resembles
a train, with the structural stop members 22 and anchors 14 resembling carriages.
[0034] A gravity anchor 14 is located at each stop member 22. In the illustrated example
each anchor 14 comprises a void on the underside (not visible in figure 1). The void
straddles the chain 18 such that the chain 18 effectively runs freely beneath the
anchors 14. In the illustrated example the arrangement is such that pulling on the
chain 18 pulls the stop members 22 into contact with a corresponding gravity anchor
14 whereby the pulling force is transferred from the chain 18 to the gravity anchor
14. As such the arrangement combines multiple small masses to act as a single cohesive
mass on the seabed 16.
[0035] The mooring system 12 provides a modular gravity anchor train that facilitates deployment
of large mooring forces using multi-cat type vessels that typically have limited lifting
capacity, for example less than 100 tonnes.
[0036] A mooring system 12 as illustrated in figure 1 can be installed in stages by a multi-cat
class vessel. Therefore, significant cost savings can be made on installation activities.
Conventional deployment of a mooring system requiring large mooring forces uses large
vessels or multiple vessels. As such a system according to embodiments of the present
invention represents saving in respect of hire and mobilization costs. This means
that down time and delays become fewer and therefore less expensive.
[0037] Figure 2 illustrates the arrangement of the tethering system 12 including the chain
18 and a plurality of structural stop members 22. Figures 3 and 4 illustrate the arrangement
of the stop members 22 relative to the chain 18 and the chain links 20.
[0038] In the illustrated example, the stop member 22 comprises a structural steel framework
including two structural members 24, shown as tubular members, for example steel hollow
section. The structural members 24 are spaced apart to accommodate the chain 18 passing
between them. Two high strength steel rods or pins 26 are located between the structural
members 24 such that a link 20 is received between the rods 26 to prevent relative
movement of the chain 18 and the stop member 22.
[0039] The arrangement of the rods 26 is such that a vertically orientated chain link 21
is located between the rods 26 and the spacing is such that the adjacent horizontally
orientated chain links 20 are too wide to pass through the gap between the rods 26.
Therefore, movement of the stop member 22 and chain 18 relative to each other is limited
to the length of the chain link 21 located between the rods 26.
[0040] In the illustrated example the stop member 22 includes a stabilizing element 28 extending
from one face such that the support member 22 is stably located on the sea bed 16
and a clean face 30 against which the gravity anchor 14 is engaged when a load is
applied to the tethering system 12 via the chain 18.
[0041] Lifting rings 30 may be included at the upper face of the stop member 22as illustrated..
The lifting rings 30 are used to lift the rods 26 into place when assembling the stop
members 22. The stop members 22 are generally assembled on shore.
[0042] The tethering system 12 is deployed onto the seabed as an assembly of tether 18 and
stop members 22 with the anchors 14 being deployed after the tethering system 12 is
located on the seabed.
[0043] Figure 4 illustrates a cross-section through the centre of the stop member 22 as
illustrated in figure 3. Figure 4 illustrates the arrangement of the rods 26 relative
to the links 20 of the chain 18 and highlights how the spacing of the rods 26 is wide
enough to accommodate a vertically orientated chain link 20 between them and narrow
enough to stop adjacent horizontally orientated links 20 passing between the rods
26 when a load is applied to the tether 12. Therefore, relative movement of the chain
18 and the stop member 22 is limited.
[0044] The engagement of the chain 18 and the stop member 22 is such that when a load is
applied to the chain 18 the stop members 22 are pulled into contact with the associated
gravity anchor 14 and the load is transferred from the tethering system 12 to the
anchors 14 to provide an effective mooring system 10.
[0045] Figure 5 illustrates a further example of a tethering system 120 that can be used
with the individual anchor elements as illustrated in figure 1. In the illustrated
example the tethering system 120 includes a plurality of longitudinal substantially
rigid members, for example steel bars or rods 180, that are connected end to end with
a hinge mechanism 182. The hinge mechanism 182 is operable to join the longitudinal
members 180, whilst maintaining some flexibility to facilitate installation and movement
within the system when located on the seabed 16.
[0046] Stop members 220 are provided at the junction of adjacent longitudinal members 180.
In this example the stop members 220 each comprise a receiving member 222 against
which the gravity anchors 14 (not illustrated in figure 5) are located when they are
lowered to the seabed 16. In the illustrated example the receiving member is a vertically
orientated bar or pole upon which or against which the anchors 14 can be secured.
[0047] Figure 6 illustrates an example of modular elements 50 used to create each gravity
anchor 14 as used with the tethering system 12, 120 as illustrated in figures 1 to
5. Each modular element 50 includes a self aligning geometry such that the complete
anchor structure is stable when located on the seabed and that movement of each modular
element 50 relative to an underlying modular element is restricted. The gravity anchor
14 as illustrated in figure 1 is formed from a tower of the modular elements 50. In
the illustrated example (figure 1) four modular elements are used to form each gravity
anchor 14.
[0048] As illustrated in figure 6 an anchor 14 is formed by building a tower of modular
elements 50. An exploded assembly of two modular elements 50 is illustrated in figure
6 such that the interaction of the modular elements 50 is evident.
[0049] Each modular element 50 includes a void 52 in the underside. The void 52 runs along
the width, from the front 54 to the back 56, of the modular element 50. The top/upper
surface 58 of each modular element includes a raised portion 60. In the illustrated
example the cross sectional shape of the void 52 and the raised portion 60 is a trapezoid.
It will be appreciated that the shape and size of the void 52 and the raised portion
60 correspond and are shaped such that each modular element 50 is aligned relative
to a previously installed/underlying modular element 50.
[0050] In the illustrated example, the first modular element , which is first to be located
on the seabed includes a flat base from front to back and includes the void area 52
described above. The void area 52 in the first modular element 50 is provided to straddle
the tether 12, 120 when situated on the seabed 16.
[0051] At the back of the each subsequent modular element 50 a beveled void 62 is included
on the underside and a beveled step 64 is included on the upper surface to correspond
in shape and size with the beveled void 62.
[0052] The gravity anchor 14 is assembled by locating a first modular element 50 on the
seabed such that the void 52 straddles the tether 12 located on the seabed 16. A subsequent
modular element 50 is lowered onto the first modular element 50 such that the beveled
void 62 and the trapezoidal void 53 on the subsequent modular element mate with the
corresponding beveled step 64 and trapezoidal raised section 60 respectively on the
first modular element 50. The assembly process is repeated with subsequent modular
elements 50 being installed until the gravity anchors 14 are representative of the
required total effective mass.
[0053] The self-aligning geometry of the modular elements 50 reduces the required positional
accuracy compared with, for example a basket-type frame. The mooring system 10 as
illustrated is assembled more easily than a basket frame arrangement because the assembly
process is more open because there is no confined structure surrounding the blocks.
As such a wider approach angle can be adopted and the geometry of each modular element
50 assists in aligning the modular element when being lowered towards the seabed.
[0054] The self-aligning geometry of the modular elements simplifies deployment operations,
reducing the required positional accuracy. The known system using basket-type frames
is less easily handled by multi-cat vessels, if at all, and requires a clear, flat
landing zone on the sea-bed. Moreover, a greater degree of accuracy is required when
placing concrete blocks in the basket frame.
[0055] In the illustrated example each modular element 50 is made from a cast concrete block.
However, it will be appreciated that other materials may also be suitable, for example
cast iron, steel or lead.
[0056] It will be appreciated that the modular arrangement of the mooring system according
to the described embodiments provides improvements in how a gravity anchor system
is deployed onto the seabed. The mooring system according to the described embodiments
can be deployed using a multi-cat class vessel.
[0057] Such vessels are more readily available for use than larger working vessels and the
cost to use such vessels is generally an order of magnitude less expensive than the
larger vessels. Whilst the present embodiment involves multiple lifting operations
it will be appreciated that the smaller masses can be lifted, manoeuvred and located
on the seabed more easily than a single large load. As such the present invention
provides portability in a mooring system and substantial cost savings in cost of operational
and maintenance costs.
[0058] In deployment of any gravity anchor system local sea-bed conditions can be problematic,
for example the size and location of boulders etc may interfere with successful placement
of a gravity anchor. A mooring system according to the described embodiments is considered
adaptable to such seabed conditions by distributing the stop members along the tether
with knowledge of the seabed surface undulations. As such the modular elements/anchors
can be selectively placed to reduce the problems associated with an uneven seabed.
As such interference with the tethering system can be controlled and therefore unexpected
loadings or unstable deployment, presenting the risk of anchors toppling, can be monitored
and controlled.
[0059] It will be appreciated that installation of the modular mooring system may take more
time than installation of an equivalent large anchor. However, as discussed above
the cost of equipment involved in deploying the large anchor is an order of magnitude
more expensive than a smaller vessel, which is suited to installing multiple smaller
blocks. For the modular system described above the vessel day rate is vastly cheaper
than that for the single lift system therefore even though multiple passes/lifts are
required for the modular system it is still more cost effective to do so.
[0060] Whilst specific embodiments of the present invention have been described above, it
will be appreciated that departures from the described embodiments may still fall
within the scope of the present invention.
1. A tethering system operable to tether an array of modular gravity anchors to a bed
of a body of water, the tethering system comprising:
an elongate tether locatable on the bed of a body of water; and
a plurality of stop members distributable along the tether and fixedly attachable
to the tether, wherein at least one gravity anchor is attachable to each of the stop
members.
2. A tethering system as claimed in claim 1, wherein the tether comprises a chain comprising
a series of connected links and wherein the stop members are fixedly attached to the
tether relative to one or more links of the chain.
3. A tethering system as claimed in claim 1, wherein the tether comprises a series of
longitudinal substantially rigid members, each longitudinal member being connected
by a hinge mechanism to an adjacent longitudinal member, wherein each stop member
is fixedly attached relative to a longitudinal member and hinge mechanism and is configured
to receive a gravity anchor.
4. A tethering system as claimed in any of claims 1 to 3, wherein the stop members comprise
a surface against which the gravity anchor locates when on the bed of a body of water.
5. A tethering system as claimed in any of claims 1 to 3, wherein the stop members comprise
a receiving member upon which the gravity anchor is receivable when it is lowered
towards the stop member.
6. A tethering system as claimed in claim 5, wherein the receiving member protrudes from
a surface of the stop member and is configured to be receivable in a correspondingly
shaped cavity provided at a surface of the gravity anchor.
7. A tethering system as claimed in any preceding claim, wherein the stop member comprises
a frame structure comprising at least two structural members spaced apart by structural
supports, wherein the structural supports act to engage with the tether to fixedly
attach the stop member to the tether.
8. A tethering system as claimed in claim 7, wherein the structural supports comprise
two rods or pins each secured to each plate and spaced apart to receive a section
of the tether therebetween and being operable to restrict relative movement of tether
and the stop member.
9. A mooring system comprising:
a tethering system according to any of the preceding claims; and
a plurality of gravity anchors, wherein at least one gravity anchor is connectable
to each stop member.
10. A mooring system as claimed in claim 9, wherein connection of the gravity anchor includes
locating a gravity anchor adjacent to a face of the stop member.
11. A mooring system as claimed in claim 9, wherein connection of the gravity anchor includes
locating ethe gravity anchor to be received upon a receiving member protruding from
each stop member.
12. A mooring system as claimed in any of claims 9 to 11, wherein the at least one gravity
anchor comprises a modular construction, wherein a plurality of modular elements can
be combined to form a gravity anchor connectable to each stop member.
13. A mooring system as claimed in claim 12, wherein each modular element comprises a
self aligning geometrical configuration comprising complementary mating surfaces such
that a plurality of modular elements are stackable relative to the stop member.
14. A mooring system as claimed in claim 12 or 13, wherein a first modular element comprise
a void area on its underside from front to back or side to side, wherein the void
area straddles the tether when in use.
15. A mooring system as claimed in any of claims 12 to 14, wherein each modular element
comprises a void area from front to back or side to side on its underside and a correspondingly
shaped raised area on its upper surface such that in assembling the gravity anchor
each modular element is aligned by engagement of the raised area on a subsequent modular
element within the void area on a previous modular element.
16. A mooring system as claimed in any of claim 9 to 15, wherein the at least one gravity
anchor comprises a pre-cast concrete block configured for connection to the tethering
system.
17. A method of deployment of a mooring system according to any of claims 9 to 16 comprising
the steps:
locating a tethering system according to any of claims 1 to 8 on a bed of a body of
water;
lowering at least one gravity anchor per stop element towards the bed of the body
of water;
locating each of the gravity anchors relative to a stop element; and
pulling the tether thereby transferring the tether load to the gravity anchors via
engagement of the stop elements and the gravity anchors thereby combining masses of
each gravity anchor and providing a cohesive singular mass on the bed of the body
of water.
18. A method of deployment of a mooring system as claimed in claim 17, wherein the step
of lowering at least one gravity anchor per stop element comprises lowering a plurality
of modular elements per stop element, including firstly locating a plurality of first
modular elements relative to the tether and each stop element and subsequently repeating
lowering a plurality of further modular elements into engagement with the first installed
modular element to provide a gravity anchor structure at each stop element and repeating
the step of lowering a plurality of modular elements into engagement with previously
installed modular elements until the required anchorage is achieved.
19. A tethering system as described herein and with reference to the drawings.
20. A mooring system as described herein and with reference to the drawings.